Gloucester Parkway Entrance Enhancements IFB# 2016-009-RAR.00028 Pre-Bid Conference & Site Visit August 16, 2016
2
1.Site Work at Gloucester Pkwy Entrance 2.Reclaimed Water Entrance Feature 3.50’ Wide Loudoun Water Monument Sign 4.6” Reclaimed Water Main and Services to RPZs 5.Gloucester Pkwy Buffer Enhancements 6.Reclaimed Water Irrigation System along Gloucester Pkwy Buffer 7.Loudoun County Parkway Buffer Enhancements 8.Extend Reclaimed Water Irrigation System along Loudoun County Parkway Buffer Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
3
Site Work at Gloucester Pkwy Entrance Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
4
Site Work at Gloucester Parkway Entrance DEMOLITION
5
Site Work at Gloucester Parkway Entrance
8
Reclaimed Water Entrance Feature Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
9
Reclaimed Water Entrance Feature: Fountain
10
Reclaimed Water Entrance Feature: Shade Sail Structure
11
50’ Wide Loudoun Water Monument Sign Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
12
50’ Loudoun Water Monument Sign
13
6” Reclaimed Water Main and Services to RPZs Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
14
6” Reclaimed Water Main and Services to RPZs
15
Gloucester Pkwy Buffer Enhancements Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
16
Gloucester Parkway Buffer Enhancements
17
Reclaimed Water Irrigation System along Gloucester Pkwy Buffer Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
18
Reclaimed Water Irrigation System along Gloucester Parkway Buffer
19
Loudoun County Parkway Buffer Enhancements Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
20
Loudoun County Parkway Buffer Enhancements
21
Extend Reclaimed Water Irrigation System along Loudoun County Parkway Buffer Project Overview ASF O&M AQUIARY WAY LOUDOUN WATER WAY
22
Extend Reclaimed Water Irrigation System along Loudoun County Parkway Buffer AQUIARY WAY LOUDOUN COUNTY PARKWAY
23
Section 00200 – Instructions to Bidders Article 3 – Qualifications (Include) Article 4 – Bidder Site Inspections (Paragraph 4.05) Article 7 – Interpretations and Addenda Submit to constructionbids@loudounwater.orgconstructionbids@loudounwater.org Addenda will be posted to Loudoun Water website Deadline 7 days prior to bid opening Article 8 – Bid Security (Bids >$100,000 » 5%) Article 14 – Basis of Bid; Comparison of Bids (Lump Sum) Article 15 – Submittal of Bid (Procedures) Bid Phase – Procedural Highlights
24
Other Considerations Contract Times: Substantial Completion – 210 days from NTP Final Completion – 30 days following Substantial Completion Permits: Grading Plan Approved – Grading Permit Issued at Pre-Con Loudoun County Building Permits – Attached to Supplementary Conditions
25
Other Considerations Borrow Material for Berms and Boulders for Landscaping Features LOUDOUN COUNTY PARKWAY REUSE LANE GLOUCESTER PARKWAY
26
Procurement Schedule DateMilestone August 4, 2016Bid Advertisement August 16, 2016Pre-Bid Conference & Site Visit September 8, 2016Bid Opening at 2:00 PM – Loudoun Water ASF Building September 28, 2016Loudoun Water CIP Committee Meeting October 13, 2016Loudoun Water Board Meeting
27
Questions