Dana Point Lantern District Del Prado Construction October 23, 2014
2
Dana Point Lantern District Phase 2 & 3 Improvements 6,100 LF of Water Mains 2,354 LF of Gravity Sewer 600 LF of Recycled Water Mains DEL PRADO SANTA CLARA AVE. PACIFIC COAST HIGHWAY LA PLAZA SAN MARINO PL. BLUE LANTERN SEVILLE PL. RUBY LANTERN GRANADA DR. LA SERENA DR. AMBER LANTERN EL ENCANTO ST. LANTERN SAN JUAN AVE. WATER SEWER RECYCLED INSTALLED ALL DATES ARE TENTATIVE GOLDEN LANTERN 11/11–11/21 10/23–10/29 VIOLET 11/24 – 12/12 Complete 10/24 10/25 10/28 – 11/10 10/30–11/10 11/11 – 11/20 11/22 – 12/12 11/1
3
Outreach Information Construction Schedule Contract: August 5, 2014 – February 10, 2014 Trenching began September 15, 2014 Saturday work to begin October 25, 2014 Blackout dates (11/11, 11/26-11/28, 12/24-12/25, 12/31-1/1) Goal to complete water & sewer work on Del Prado by 12/24 What to Expect Sewer service connections will not affect service Water service tie-ins will be arranged to limit downtime (9:00 am – 4:00 pm) 48 hours notice Temporary water service as needed Increased Coordination with Local Business Message boards will be updated with detours and directions Coupons and advertisements included in e- mail blasts Maintaining access to parking More frequent email blasts & coordination with impacted businesses
4
Violet Lantern Traffic Control Shift (1 OF 2) Two right hand travel lanes will be closed through Violet Lantern intersection until 10/24 DEL PRADO VIOLET LANTERN INSTALLED BY 10/24 EXISTING TRAFFIC CONTROL *PROPOSED WATER LINE NOT SHOWN
5
Violet Lantern Traffic Control Shift (2 OF 2) Left hand travel lane to be closed through Violet Lantern intersection starting 10/27 DEL PRADO VIOLET LANTERN INSTALLED BY 10/24 PLANNED TRAFFIC CONTROL STARTING 10/27 *PROPOSED WATER LINE NOT SHOWN
6
Current: “Businesses Open” signage “Parking in Rear” signage Doheny / Ocean Institute / Harbor signs PCH-1 / PCH Alternate sign Del Prado Detour signs Del Prado archway priority construction Del Prado digital Mama Says/Business Names Newspaper advertisement program Support our local businesses verbiage in e-blasts Del Prado Business Support Efforts During Construction
7
Proposed: Holiday lights at Lantern District entryways Posters of Del Prado Streetscape “Coming Soon” Entry banners/balloons Business spotlight articles Dana Point Lantern District Website Passport Stamp Raffle Further relaxed temporary sign ordinance Del Prado Business Support Efforts During Construction
8
Questions???