BUILDING STRONG ® U.S. Army Corps of Engineers Tulsa District US Army Corps of Engineers BUILDING STRONG ® ® Gene Snyman Tulsa District Small Business Deputy Tulsa SAME Post Membership 16 AUG 2016 Joint SAME – ASCE August Post Program
2
BUILDING STRONG ® Agenda Orientation to Tulsa District Military Project Status/Forecast Environmental Contract Status
3
BUILDING STRONG ® Tulsa District 700 people Arkansas River and Red River Basins in Oklahoma, Southern Kansas and Northern Texas Major Missions of the Corps of Engineers War Fighting Navigation Hydropower Flood Control (Flood Risk Management) Military Construction Regulatory/Environmental Homeland Security
4
BUILDING STRONG ® Engineering Control Tower Vance AFB Air Defense Artillery School Fort Sill Medical Facility Tinker AFB Environmental Management Construction Installation Support Vance AFB Tinker AFB Altus AFB Fort Sill McAlester Sheppard AFB KC 46A Program Altus AFB ENJPT Training Facility Sheppard AFB Reserve Center McAlester Army Ammunition Plant Military Mission Pantex
5
BUILDING STRONG ® Honors Cottage, Skiatook Lake Grand Lake Webbers Falls Turbine Tenkiller Lake Inland Navigation (MKARNS) 5 locks & dams 3 major ports Hydroelectric Power 8 power plants produce 585,000 kw capacity Generates power to 8 million customers Water Supply Environmental Stewardship Recreation 267 recreation areas at 33 projects 22.5 million visitors in 2012 Flood Risk Management 38 Corps dams + 10 others 15,950,000 acre feet of flood storage Arkansas River Basin: $11,144B in cumulative flood damage reductions Red River Basin: $1,936B in cumulative flood damage reductions 50% of Corps water supply contracts 18 lakes, 104 water supply customers 2.2 million people served Enhances municipal, industrial, irrigation usage Protects endangered species Improves degraded streams Water Quality Red River Chloride, Area VI Tenkiller Low Flow Pipe Supersaturated Dissolved Oxygen System (SDOX) Civil Works Mission
6
BUILDING STRONG ® FY16 Small Business Status-AUG 6 42.6 % 43.0% 23.6% 23% 13.0% 5.9 % 8% (FY15 6.8%) 4.9 % 4.0% 5.5 % 50.1% 55.1% 44.9% 18.6% 5.1% 4.8% 5.2% JUL16 $741M $128.5M subject to available funds
7
BUILDING STRONG ® FY15 Tinker AFB KC-46A Two Bay Depot Maintenance Hangar $50M-$100M Project separated from previous combined solicitation with the FY-15 Infrastructure project. Options: AF Above Threshold Reprograming (Award MAR 17) Repackage single bay (Award TBD) Repackage two bay with lesser scope (Award TBD)
8
BUILDING STRONG ® FY15 Tinker AFB Heat Recovery and Controls, Paint Hanger, B3225 $1M-$5M D-B SB Set Aside Energy project for Paint Hangar, B3225, to add redundant fans, heat recovery coils, variable speed drives, control actuators, sensors, and system metering. Construction Award SEP 2016. (Existing IDIQ)
9
BUILDING STRONG ® FY16 Tinker AFB KC-46A Depot Maintenance Dock $25M-$50M D-B Full and Open Ph I advertisement issued 9MAR16; Proposals received 19MAR16 Ph II advertisement issued 2JUN16; Proposals received 28JUL16 Award SEP16.
10
BUILDING STRONG ® FY16 Tinker AFB Air Traffic Control Tower $10M-$25M D-B Full and Open Final RFP submittal was delayed waiting on AF to determine proper tower height. Phase One selection completed. Phase Two advertisement scheduled for 31AUG16. Construction award scheduled JAN17 Opportunity to award in first quarter, depending on availability of resources and construction funding.
11
BUILDING STRONG ® FY16 Fort Sill Training Barracks Upgrade Program B5970 $25M-$50M D-B Full and Open Schedule: Advertise Ph2 : 18JUL16 Award: 29SEP16 Way Ahead: Critical SRM project must meet FY16 year end award
12
BUILDING STRONG ® FY16 Fort Sill Training Support Facility $10M-$25M D-B-B SB Set-Aside Construct 70K SF TSF - facilities include open high-bay vehicle storage space, offices, classrooms, latrines, arms room, consolidated entry and reception area Schedule: Final Design: 30SEP16 Advertise: 14OCT16 Award Contract: 23DEC16
13
BUILDING STRONG ® FY16 Fort Sill Reception Barracks Complex Ph2 $50M-$100M D-B-B Full and Open Construct 256K SF RBC. Primary facilities include company operation facilities and barracks w/ special foundations. Schedule: Final Design: 15NOV16 Advertise: 28DEC16 Award: 15MAR17 Concerns: Flood plain mitigation, FEMA safe room, sloped roof
14
BUILDING STRONG ® FY16 Altus AFB 120-Airman Dormitory $10M-$25M DB SB Set-Aside Planning and Design Funds received from AFCEC - 30OCT15 Design Charrette w/ AE contractor scheduled 22AUG16 RTA D/B RFP Package - MAR17 Award Construction Contract - SEP17
15
BUILDING STRONG ® FY17 Tinker AFB KC-46A Depot System Integration Laboratory $10M-$25M D-B Small Business Set-Aside Design Charrette kickoff held 29- 31 March. Ph I advance notice issued for advertisement Advertise: OCT16 Award MAR17
16
BUILDING STRONG ® FY17 Altus AFB KC-46A FTU FTC Simulator Facility Phase 2 $10M-$25M D-B-B Small Business Set-Aside Currently in design Advertise scheduled SEP16 Award TBD
17
BUILDING STRONG ® FY17 Sheppard AFB Medical/Dental Clinic Replacement $50M-$100M D-B Full and Open RFP Development in process. Final design is scheduled to be submitted o/a 20SEP16 Final design review meeting is scheduled for the week of 17OCT. Phase 1 RFP solicitation is scheduled for 19JAN17 Planned Award JUL 2017
18
BUILDING STRONG ® FY19 Tinker AFB KC-46A Depot Maintenance & Fuel Hangars/Infrastructure $100M-$150M D-B-B Full and Open Scope to include 1 four bay PDM Hangar and 1 two bay Fuels Hangar, Aircraft parking and infrastructure. Planning Charrette held 20-24 Jun. An alternative linear program site layout was considered that resulted in a preliminary total of higher program estimate. Draft Planning Charrette Report (PCR) currently in review.
19
BUILDING STRONG ® Pantex-NNSA High Explosive Science & Engineering Facility $50M-$100M Complex to consolidate 15 facilities: Admin; Light Lab; Small HE Storage Bunker; Demolition (not part of our scope) AE Contract awarded April 2016 Charrette & Formal Partnering Session held. Construction Date and Acquisition Plan TBD.
20
BUILDING STRONG ® FY17 Regional Planning and Env Center TitleROMSet AsideSolicitationContractAwardNotes MEGA ECS $60M8a1QFY17 Mar-17Priority 1 Env AE Svcs (Master Planning) $49.90SB/LG1QFY17 W912BV- 16-S-2005 2QFY17 Priority 2 Sources Sought closed 27JUL; Anticipated $30M for LB pool and $19.9 SB pool MEGA ERS $45MSB1QFY17 2QFY17 Priority 3 Fort Worth District Contracting Office
21
BUILDING STRONG ® Questions? Gene Snyman gene.snyman@usace.army.mil 918-669-7010 Current Forecast and list of IDIQs: http://www.swt.usace.army.mil/Business- With-Us/Small-Business-Office/ Fedbizops – Search “W912BV”