1
MVD COOLING STATUS COOLING PLANT: -UPDATE of THE HYDRAULIC SYSTEM -INTEGRATION OF THE MVD COOLING CIRCUIT PATHS INSIDE THE PANDA AREA -DEFINITION OF THE PACKAGE SECTION OF ALL THE COOLING TUBE ALONG THE PATH -INSERTION OF PATCH PANELS -OPEN QUESTIONS S.COLI - DEC.20141
2
MVD HYDRAULIC CIRCUIT PNEUMATIC VALVES TEMPERATURE SENSORS FLOW METERS PRESURE REGULATORS HEAT EXCHANGER -PUMP -VACUUM PUMP -PLC -CONTROLS PRESSURE SENSORS COOLING PLANT PNEUMATIC VALVES S.COLI - DEC.20142
3
PIXEL : 42 TUBES 65 m INLET and RETURN outside the magnet 2,5 m INLET and 2,5 mt RETURN inside the magnet 2,3 m in the MVD WATER VOLUME: about 160 liters MASS FLOW RATE: about 16 lit/min STRIP : 44 TUBES 65 m INLET and RETURN outside the magnet 2,5 m INLET ad 2,5m RETURN inside the magnet 2, 7m in the MVD WATER VOLUME: about 190 liters MASS FLOW RATE: about 10 lit/min SERVICES : 64 TUBES 65 m INLET and RETURN outside the magnet 2 m INLET ad 2m RETURN inside the magnet 1 m in front of MVD WATER VOLUME: about 270 liters MASS FLOW RATE: about 30 lit/min HYDRAULIC CIRCUIT for MVD SYSTEM (PIXEL + STRIP + SERVICES): S.COLI - DEC.2014 3 SUMMARING About 640 lit About 56 lit/min About 75 circuits 150 Tubes TUBES FROM COOLING PLANT TO MAGNET: - 150 TUBES in STAINLESS STEEL = 0,65 m* 0,15m total section IN FRONT OF THE MAGNET DOOR (PP4) -150 Pressure sensors + tube fittings -150 Readout cables and Power supply AT THE COOLING PLANT -PLC -Tank -Vacuum pump -Inlet pump + filter -Water cleaning unit -Manifolds and 75 inlet tubes -Manifolds and 75 return tubes -Heat exchanger -75 pressure regulator, + 75 flow meters + 75 valves on return lines + 75 water Temperature sensors -150 pneumatic valves -Other sensors (tank level indicator, pump pressure sensors, water temperature sensors…)
4
PANDA AREA S.COLI - DEC.2014 4 PANDA in ASSEMBLY POSITION PANDA FINAL POSITION MVD COOLING PLANT MVD TUBES PATH
5
S.COLI - DEC.20145 MVD COOLING PLANT – OUTSIDE THE PIT INLET RACKS (PIXEL, STRIP, SERVICES) PLC HEAT EXCHANGER (?) 3,8 mt 3,5 mt
6
S.COLI - DEC.2014 6 MVD COOLING PLANT – IN THE PIT RETURN RACKS (PIXEL, STRIP, SERVICES) TANK+ VACUUM PUMP INLET PUMP + WATER CLEANING UTIT
7
S.COLI - DEC.2014 7 MVD COOLING SYSTEM – INLET AND RETURN TUBES PATH INSIDE PANDA AREA TUBE PAKAGE SECTION ALL ALONG THE PATH [0,65m X 0,15 m] h= 2 mt INLET LINES RETURN LINES
8
S.COLI - DEC.2014 8 MVD COOLING SYSTEM – INLET AND RETURN TUBES PATH INSIDE PANDA AREA TUBE LENGHT:~ 65 m
9
S.COLI - DEC.2014 9 MVD COOLING SYSTEM– PATCHPANELS PP1: TRANSITION (FLEX-METAL TUBES) PP2: FOR ASSEMBLY PP3: FINAL PP4: PRESSURE SENSORS AND FITTINGS, AFTER CAL INSERTION PATH ? BEFORE CAL INSERTION
10
S.COLI - DEC.2014 10 MVD COOLING SYSTEM– REQUEST 1 THE RETURN TUBES AT THE HEIGHT OF THE FLOOR? CROSSING PROBLEM?
11
S.COLI - DEC.201411 MVD COOLING SYSTEM– REQUEST 2 CAN THE MVD OCCUPY THE RIGHT SIDE OF THE PIT? CROSSING PROBLEM? AVAILABLE AREA?
12
S.COLI - DEC.2014 12 MVD COOLING SYSTEM – QUESTIONS Can the return tube be located on the floor along the external wall? Can the MVD cooling plant occupy the right side of the pit ? From where does the cold water arrive? AIR line at 6 bar? Where? Is the door a passage? Can we put the patch panels? The small patch panel4 on the floor held by the CAL support (charriot)? After CAL insertion, we need to cut tubes to patch panel 4 (?) The path for the flex tubes from PP3 to PP4?