Southeast Rail Extension Update RTD Board of Directors FasTracks Monitoring Committee March 3, 2015
2
Project Background Included in FasTracks Plan – Approved by voters in 2004 Would extend transit service 2.3 miles from Lincoln Avenue to RidgeGate Pkwy Includes a Kiss-n-Ride station at Sky Ridge and at the future Lone Tree City Center Includes an end-of-line station at RidgeGate with a 1,300 space Park- n-Ride facility (Opening Day) Project Cost: $207 Million
3
Engineering and Environmental Status Engineering and Design 65% Engineering completed 2014 Basic station design elements determined and presented to Lone Tree City Council and Planning Commission Environmental Environmental Assessment (EA) completed and Finding of No Significant Impact (FONSI) received October 2014
4
FTA New Starts Funding Timeline September 2012: Submitted request for entry into Preliminary Engineering/Project Development (requesting $92 Million) April 2013: Received approval to enter Project Development (2-years to complete this step) July 2014: RTD Board approval to revise the project schedule with an opening day of 2019. This revision, which was necessary to maintain eligibility for Federal New Starts funding, was submitted to DRCOG for inclusion in the 2040 RTP October 2014: Submitted request to enter Engineering
5
FTA New Starts Funding Next Steps February 2015: Included in the President’s 2016 budget for $92 Million February 2015: DRCOG Board approval of 2040 RTP March 2015: Anticipate receipt of entry into Engineering Summer 2015: Submit final request for Full Funding Grant Agreement (FFGA) Spring 2016: Anticipate receipt of FFGA
6
Procurement Process Timeline November 2014: Advertised Request for Qualifications (RFQ) January 2015: Received statements of qualifications from 7 teams 4 teams were selected to continue through the procurement process –Balfour Beatty Infrastructure with Parson Brinkerhoff (serving as prime contractor and performing systems and design work) –Graham – Kraemer Joint Venture (prime contractor); Modern Railway Systems (systems); Stantec (design) –Kiewit (prime contractor); Mass Electric (systems); Hatch Mott McDonald (design) –Stacy Witbeck – Herzog – Wadsworth Joint Venture; Modern Railway Systems (systems); STV (design)
7
Procurement Process Next Steps March 2015: Advertise Request for Proposals (RFP) May 2015: Receive Proposals May – July 2015: Evaluate Proposals and Make Recommendations for RTD Board Approval August 2015: RTD Board Approval Fall 2015: Issue Notice to Proceed (NTP) for Phase I (Design)/Groundbreaking Spring 2016: Issue NTP for Phase II (Construction)
8
Southeast Rail Extension Questions?