1 Preinjectors Status D. Raparia April 26, 2016 Time Meeting

2 Tandem Status Ru with pulse, 12 pulses in TTB
Will start D+ May 4th in TTB ( for present schedule, May 7) D. Raparia

3 EBIS Status EBIS running smoothly Au with 12 pulses
NSRL last week: Silicon, Helium NSRL this week: Iron, Titanium, Carbon, Laser 3: change with spare one Laser 3 send back to factory for repair D. Raparia

4 Au at IHLinac for 12 pulses
D. Raparia

5 Linac Status Linac running for BLIP at 117 MeV BLIP at 150 -160 uA
4/19-4/25: 200 MeV to BLIP 4/25-4/29: 200 MeV PP 4/25-4/29: 200 MeV PP to Polarimeter 4/19: Switch to 200 MeV for BLIP (2 HRS) 4/20: PQ49 PS adjustment (0.5 HRS) 4/21: Tank 6 sparking (0.5 HRS) 4/25: switch back to 117 MeV (1 HRs) D. Raparia

6 Average Current for BLIP & Beam on HRS/day
Beam on HRS out 168 HRS Energy Change 200 MeV D. Raparia

7 J. Nelepa D. Raparia

8 Beamline Location 21’ 14’ plunging harp plunging harp (opposite side)
6.50” collimator bellows (3x) raster magnet steering magnets (existing, 2x) 4.00” collimator plunging harp (opposite side) laser profile monitor beam current transformers (2x) beam position monitor beryllium window (existing) aluminum bellows (existing)