Download presentation
Presentation is loading. Please wait.
Published byRhoda Wheeler Modified over 8 years ago
1
National Workshop on Drafting of Commercial Agreements Organised by : ASSOCHAM 3 rd September 2016 New Delhi Presented by S. Ravi Shankar, Arbitration lawyer & Senior Partner Law Senate Law Firm – New Delhi, Mumbai ravi@lawsenate.com www.lawsenate.com
2
Binding and Enforceable Contracts To bind a party fully a contract is required to be neither void or voidable Void Contracts are not enforceable A contract signed by an unauthorised person is void A contract with no consideration is void (S.25) A contract for an illegal activity is void A contract which prohibits a Doctor from practising as Doctor for three years, if he resigns from the hospital (S.27) A contract which restricts the legal rights of a party (S.28) (BSNL Vs Motorola 2009 (2) SCC 337 A contract with uncertainty is Void (S.29) www.lawsenate.com
3
Voidable Contracts If an agreement is enforceable by law at the option of one party and not at the option of the other is voidable contract (S.2.i) Means contract is enforceable until repudiated by one party Example is a contract, after the period mentioned in the contract and where time is the essence (S.55) A Contract entered into by coercion S.19 A Contract entered by undue influence S.19A. Impossibility created by one party S.53 Refusal of Party refusing to perform. S.39 www.lawsenate.com
4
Damages - Features Damages is a compensation for an injury (S.73) Damages is not a Penalty (Subramania Satri Vs KS Raghavan 1987(2) SCC 424) So Damages have to be reasonable ONGC Vs SAW pipes (2003) 5 SCC 705 Damages is a compensation for Loss Loss is a pre condition for claiming damages Damages can not be determined by a party Damages have to be determined in an Adjudication www.lawsenate.com
5
Liquidated Damages S.74 Pre-estimated loss can be quantified and incorporated into a contract, as liquidated damages (BSNL Vs Reliance Communication (2011) 1 SCC 394)) Liquidated Damage amount is the maximum damage which can not be granted since it is in the contract (BSNL Vs Reliance) Parties claiming liquidated Damages also have to prove that they incurred loss (Kailash nath Associates Vs Delhi Development Authority 2015 SCC Liquidated Damages specified in the contract must be granted when it is not possible to ascertain the actual damages Chunilal Vs Century Spinning 1962 Supp (3) SCR 549 Damages/ Liquidated damages is not a debt. Union of India Vs Ramon Iron Foundary 1974(2) SCC 231 www.lawsenate.com
6
Time is the Essence of the Contract & Liquidated Damages Specifying a date of completion in a contract does not mean “ Time is the essence” Contract stating many times “ Time is the essence of the contract” is not sufficient to make time the essence of the contract Time is the Essence means parties wanted to complete the contract on a particular date If the contract is not completed on the date specified in the contract, then it is voidable (S.55) If the contract work is allowed to be completed after the said date mentioned in the contract, then time is not the essence of the contract If time is not the essence of the contract then contract can be completed within a reasonable time so Liquidated Damages does not apply www.lawsenate.com
7
Time is the Essence of the Contract & Liquidated Damages If time is not the essence of the contract, then liquidated damages can not be claimed Even in contracts where time is not the essence and Liquidated damages are prescribed – Damages can be claimed for the delay If Liquidated Damages are prescribed for delay of one day, delay of one week, delay of one month etc., then the parties did not have the intention to complete the contract on a particular date hence time is not the essence. In the contracts where time is not the essence, time can be made as the essence of the contract by issuing a notice fixing the revised date for completion Hind Construction Vs State of Maharashtra (1979) 2 SCC 70 If the owner waives a right to impose Liquidated Damages, then even when time is essence the liquidated damages are not payable J G Engineers Vs Union of India (2011) 5 SCC 758 www.lawsenate.com
8
Bank Guarantee & Legal Position Bank Guarantee can be Conditional & Unconditional Bank Guarantee is an independent contract between the beneficiary and the Bank The Beneficiary (Alone) can invoke the Bank Guarantee (Hindustan Construction Vs State of Bihar (1999) 8SCC 436) Injunction restraining invocation of an Unconditional Bank Guarantee can be granted only on the grounds of fraud and irreparable loss to one party Mahatma Gandhi Shakra Vs National Heavy Eng Corporation 2007 (6) SCC 470 Injunction restraining invocation of a Conditional Bank Guarantee can be granted, if conditions are not fulfilled by the beneficiary (Hindustan Construction Vs State of Bihar (1999) 8SCC 436) www.lawsenate.com
9
THANKS www.lawsenate.com
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.