Presentation is loading. Please wait.

Presentation is loading. Please wait.

AS Webex meeting – January 27, 2010

Similar presentations


Presentation on theme: "AS Webex meeting – January 27, 2010"— Presentation transcript:

1 AS Webex meeting – January 27, 2010
AAP Review Marc Ross AS Webex meeting – January 27, 2010

2 Background: Please read:
‘Initial comments on last week's AAP Review of SB2009’ (sent by PM Wednesday 13 Jan) and (last week’s Newsline Director’s corner) and (last week’s Newsline Research Director’s corner).

3 AAP AAP is intended to provide critical review of technical, management and strategic activities to the Project Director. Their report is due to Barry in a week or so. They met last Friday. We launched ‘SB2009’ to achieve cost constraint – capital construction cost – against an anticipated rise in high-tech component costs. Goal set by Project Director and Regional Directors: No increase in Value Estimate in 2012. AAP expected many 0.1% cost reduction activities – consistent with the original short-lived ‘2007 EDR’ plan.  ‘engineering-driven’ We don’t have resources for this and do not expect what is needed to appear in TDP2. SB2009 consists of several few % cost reductions – the best possible path.

4 AAP (2): recommended greater conservatism v/v technical risk
An expanded cost assessment that includes projected operations costs for a given integrated luminosity (per 2004 scope document) recommended more strict interpretation of scope – luminosity vs E. Aside: I believe the LOI preparation process provided a more precise understanding of scope

5 Single Tunnel – cost reduction with little impact on scope
Our priority: safety and availability R & D on HLRF – to be developed and acceptance during TDP2. Two systems, which provide ‘site’ flexibility, a very important approach, recommended at Dubna, 2008. Energy overhead, radiation, installation, commissioning mentioned

6 Low Power operation Positron – low energy operation
what R & D is required to allow it ‘to be adopted when / if needed’? Impact on scope – but largest SB2009 cost saving Ring studies  Positron – low energy operation Scope interpretation: Contiguous operation from 200 to 500 GeV.   Technically conservative choice: Quarter wave transformer vs Flux concentrator à complication of SB2009; unrelated to cost-reduction Apply this change to RDR design…

7 Cost Constraint How much cost increase must we be able to offset?
SRF is by far the largest R & D activity. To be a central topic at Beijing.  XFEL costs, design gradient changes, mass-production schemes, regional industrial basis – all will impact TDP2 SRF cost estimate SB2009 savings roughly equivalent to a doubling of the cryomodule cost wrt RDR.


Download ppt "AS Webex meeting – January 27, 2010"

Similar presentations


Ads by Google