Download presentation
Presentation is loading. Please wait.
Published byBelinda Watson Modified over 8 years ago
1
Meeting Nantucket’s demand for electricity, today and tomorrow. Upgrading Nantucket’s Electric Grid
2
2 Serving Nantucket Currently two undersea cables serve the electric demand to the island. Due to increasing demands for electricity, a third cable is forecasted to be needed in about 15 years. In an attempt to delay the need for the third cable, measures are currently being implemented through energy efficiency initiatives.
3
Bunker Road Generation Project
4
4 The existing generation is intended to serve as a back-up source of electricity in the event a problem occurs with one of the submarine cables that interrupts service to the island. Currently, one of the undersea cables and generators would be able to provide electricity to most, but not all customers on Nantucket during the peak summer months. If Nantucket experienced a long outage during the summer months, National Grid would bring large mobile, or "roll on," generators to the island to serve customers. This Project will increase on island generation capacity and reduce reliance of roll on generation during a supply contingency.
5
5 Bunker Road Generation Project Phase 1: Upgrade Diesel Generation Replace the two existing 3MW diesel generation units with a new 10MW diesel generator. New generator would improve National Grid’s ability to serve customers if the island experiences a cable-related service interruption. Phase 1 Timeline: June 2016: National Grid issues request for proposal (RFP) for bidders to supply and install the generator September 2016: Deadline for responses to RFP December 2016: Final Design / Construction Start
6
6 Bunker Road Generation Project Phase 1: Upgrade Diesel Generation
7
7 Bunker Road Generation Project Phase 2: Install Battery Storage or Second Diesel Generator National Grid proposing to install a Battery Electric Storage System (BESS). Requesting information from industry experts to asses whether battery storage is cost-effective and viable solution. If battery is not a feasible solution, National Grid will install a second 10MW diesel generator. If battery is chosen, it would be the first of its kind at National Grid. Phase 2 Timeline: May 2016: National Grid issues request for information (RFI) June 2016: Deadline for responses to the RFI August 2016: National Grid to review proposals and determine which project will move forward
8
8 Bunker Road Generation Project Phase 2: Install Battery Storage or Second Diesel Generator
9
9 Example of Battery Electric Storage System (BESS)
10
Candle Street Station Flood Mitigation Project
11
Candle Street Flood Mitigation National Grid is proposing to install flood mitigation controls at its Candle Street Substation. The Project is part of a Company-wide effort to protect our major assets from floods based off of FEMA’s base flood elevation calculations. National Grid has received approval to proceed with Phase One of the project through the Nantucket Conservation Commission and the Nantucket Historical Commission. Project team is currently reviewing the current design and making modifications to the plan. 11 Timeline: May 2016: Project engineering team reviewing and reassessing the overall design October 2016: Construction Start Phase 1 Spring 2017: Construction Start Phase 2
12
Existing Protections Sandbag Protection at Switchgear. 12
13
Type of Work Proposed 13 Phase 1 (Short Term) Improve Sandbag Systems currently protecting the switchgear Seal conduits at designated manholes and riser locations Phase 2 (Long Term) Permanently Raise Equipment Switchgear Transformer Panels
14
14 Public Outreach National Grid is committed to keeping local officials, residents, businesses and community groups informed and educated on the status of the projects through public meetings, site visits and direct mailings. Upcoming Events: July 2016: Informational Open House highlighting the two projects. August/September 2016: Site Visit with Town officials to be scheduled if we proceed with battery option. Informational Open House to inform stakeholders on the Company’s decision regarding the battery storage.
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.