Presentation is loading. Please wait.

Presentation is loading. Please wait.

V. 2. © Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 4. Project Integration Management PMP Prep Course Based on the PMBOK ® Guide 3 rd.

Similar presentations


Presentation on theme: "V. 2. © Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 4. Project Integration Management PMP Prep Course Based on the PMBOK ® Guide 3 rd."— Presentation transcript:

1 v. 2. © Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 4. Project Integration Management PMP Prep Course Based on the PMBOK ® Guide 3 rd Edition

2 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 2 Project Integration Management – Includes the processes and activities to identify, define, combine, unify, and coordinate the various processes and project management activities within the Project Management Process Groups. *Source: PMBOK ® p.77 4. Project Integration Management

3 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 3 Integration – Is primarily concerned with effectively integrating the processes among the Project Management Process Groups that are required to accomplish project objective within an organization's defined procedures. *Source: PMBOK ® p.78 4. Project Integration Management Not all processes may be required, but they all must be addressed.

4 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 4 A significant role of the Project Manager is to perform Integration. To put all the pieces of the Project together into a cohesive whole that gets the project done faster, on Scope with defined Quality, for less costs and resources. *Source: PMBOK ® p.78 4. Project Integration Management

5 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 5 Project Management Process Groups InitiatingPlanningExecuting Monitoring & Controlling Closing Project Integration Knowledge Area Processes 4.1 Develop Project Charter (3.2.1.1) 4.2 Develop Preliminary Project Scope Statement (3.2.1.2) 4.3 Develop Project Management Plan (3.2.2.1) 4.4 Direct and Manage Project Execution (3.2.3.1) 4.5 Monitor and Control Project Work (3.2.4.1) 4.6 Integrated Change Control (3.2.4.2) 4.7 Close Project (3.2.5.1) 4. Project Integration Management *Source: PMBOK ® p.70

6 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 6 4.1 Develop Project Charter Project Charter – The document that formally authorizes a project. Provides the project manager the authority to apply organizational resources. The project manager should be assigned prior to the start of planning, and preferably while the project charter is being developed. *Source: PMBOK ® p.81

7 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 7 4.1 Develop Project Charter The Charter – documents business needs, project justification, current understanding of the customer's requirements, and the new product, service, or result that is intended to satisfy those requirements. *Source: PMBOK ® p.81

8 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 8 4.1 Develop Project Charter The charter addresses: Stakeholder requirements, expectations Business needs Project purpose or justification Assigned Project Manager and authorities Assumptions; Constraints *Source: PMBOK ® p.82 Summary milestone schedule Stakeholder influences Functional organization responsibilities Business case justification Summary budget

9 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 9 4.1 Develop Project Charter *Source: PMBOK ® p.82

10 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 10 4.1 Develop Project Charter RFP responses; Vendor bids Product scope descriptions Strategic plans Organization culture and structure Government and industry standards Market place conditions Policies; Procedures Historical information Lessons learned

11 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 11 4.1 Develop Project Charter Benefit measurement method Mathematical models PM method (not the construction method e.g., System Development Life Cycle - SDLC) E-Mail; Desktop applications; Enterprise systems Industry groups; Consultants; Stakeholders

12 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 12 4.1 Develop Project Charter A specific document (physical or electronic) Signed by a person (sponsor) at a level that is appropriate to funding the project.

13 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 13 Scope Statement – The definition of the project – what needs to be accomplished. The process addresses and documents the characteristics and boundaries of the project and its associated products and services, as well as the methods of acceptance and scope control. *Source: PMBOK ® p.86 4.2 Develop Preliminary Project Scope Statement

14 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 14 4.2 Develop Preliminary Project Scope Statement A scope statement includes: Project, product objectives Product/service requirements and characteristics Acceptance criteria Project boundaries Project requirements and deliverables Project constraints, assumptions *Source: PMBOK ® p.86 Initial project organization Initial defined risks Schedule milestones Initial WBS Order of magnitude cost estimate Project configuration management requirements Approval requirements

15 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 15 Budget Schedule Scope Staff 4.2 Develop Preliminary Project Scope Statement Constraints – Factors that will limit the project team’s options: Legal/Contractual Political Cultural

16 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 16 4.2 Develop Preliminary Project Scope Statement

17 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 17 4.2 Develop Preliminary Project Scope Statement Approved Project Charter Clear descriptions in Project Statement of Work Assumptions and Constraints in your Enterprise that will affect this Project Organization structure, culture and key resources.

18 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 18 4.2 Develop Preliminary Project Scope Statement Processes that help control changes to the scope statement Automated systems that help generate the scope statement, track changes, and represent the approved version Judgment regarding technical and management details pertinent to the project, from experience, expert consultants or trade knowledge.

19 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 19 4.2 Develop Preliminary Project Scope Statement A specific document (physical or electronic) A revised version of a previously released scope statement

20 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 20 Developing the plan – Includes the actions necessary to define, integrate, and coordinate all subsidiary plans into a project management plan – a plan that defines how the project is executed, monitored and controlled, and closed. *Source: PMBOK ® p.88 4.3 Develop Project Management Plan The plan documents the outputs of the processes of the Planning Process Group. (see PMBOK, page 70)

21 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 21 4.3 Develop Project Management Plan Sample plan content: (not limited to) PM processes How work will be executed How changes will be controlled What tools will be used Key management review processes Communication channels *Source: PMBOK ® p.88/89 Subsidiary plans / baselines: Scope management plan Cost management plan Quality management plan Staffing management plan Risk management plan Schedule, cost, quality baselines

22 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 22 4.3 Develop Project Management Plan *Source: PMBOK ® p.88/89

23 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 23 4.3 Develop Project Management Plan The outputs of the processes of the Planning Process Group from the other knowledge areas Historical information (esp. lessons learned) Organizational, industry, government policies and standards - Personnel - Legal - Procurement - Financial - etc.

24 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 24 4.3 Develop Project Management Plan Project management methodology Structure used by PM team PMIS Tools used by PM team Expert judgment Resources available to PM team

25 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 25 Project Management Methodology – A structured approach which aids a project management team in developing and controlling changes. Simple – uses standard forms and/or templates Complex – Requiring simulation Manual or Electronic Formal or Informal 4.3 Develop Project Management Plan – Tools and Techniques

26 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 26 Project Management Information System (PMIS) – Tools and techniques used to: Gather Integrate Disseminate the outputs of the other project management processes. Support all aspects of the project from initiation to closing. Includes both manual and automated systems. 4.3 Develop Project Management Plan – Tools and Techniques

27 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 27 Expert Judgment (Stakeholder Skills & Knowledge) – The project team must develop an environment in which the stakeholders can contribute their expertise to the project. Valuable Sources of Information PM Must Be Open to Input In-House Advisors Involved Stakeholders are Less Disruptive 4.3 Develop Project Management Plan – Tools and Techniques

28 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 28 4.3 Develop Project Management Plan Project management plan Formal, approved document Used to manage and control the project Integrated supporting organization input Will change over time!!!

29 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 29 Project Charter Strategy Scope Statement including deliverable and objectives WBS Cost Estimates Schedule Performance Measurement Baselines Major milestones Key or required staff Organization structure Subsidiary plans Risk assessment, including constraints, and assumptions Open issues 4.3 Develop Project Management Plan – Typical Content

30 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 30 Supporting Detail Outputs from other plans Additional information Technical documentation (e.g. requirements, design and specifications) Documentation of relevant standards Organized to facilitate use in executing the plan 4.3 Develop Project Management Plan

31 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 31 4.4 Direct and Manage Project Plan Execution The project manager & team perform multiple actions to accomplish the work defined. – The primary process for carrying out the project plan. The vast majority of the project’s budget will be expended in performing this process.

32 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 32 4.4 Direct and Manage Project Plan Execution

33 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 33 4.4 Direct and Manage Project Execution - Inputs Project Management Plan: Risk Management Plan Scope Management Plan Procurement Plan… Approved Corrective Actions Authorized Directions to bring project into conformance Approved Preventative Actions Reduce probability of negative consequences

34 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 34 4.4 Direct and Manage Project Execution - Inputs Approved Change Requests: Documented Authorized to expand or contract project scope Affects, cost, schedule and scope Approved Defect Repair Product Correction found in inspection or audit

35 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 35 4.4 Direct and Manage Project Execution - Inputs Validate Defect Repair Re-inspection or re-audit Administrative Closure Procedure All activities, interactions and related roles needed for closure

36 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 36 4.4 Direct and Manage Project Execution Project Management Methodology The project manager is the “general manager” of the project. GM skills include: leading, communicating, negotiating, problem solving, influencing, etc. Taking away all the excuses. Ambassador to the customer. PMIS System, complex or simple to track the project

37 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 37 4.4 Direct and Manage Project Execution Deliverables: Unique Verifiable product or result Requested Changes: Expansion or reduction in Scope. Direct or Indirect, Formal or Informal Internal or Contractual Optional or Mandatory Implement Change Requests: Get approval from Stakeholders and implement

38 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 38 4.4 Direct and Manage Project Execution – Outputs Implement Corrective Actions: Project Team brings into conformance Implement Preventive Actions Project team works to reduce consequences of project risks Implement Defect Repair: Product or Project defect corrections

39 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 39 4.4 Direct and Manage Project Execution – Outputs Work Performance Information: Schedule progress information Deliverables completed and not completed Schedule activities started Quality achievements Costs authorized and incurred (PM Budget) Estimates to Completion % physically complete Lessons Learned Resource Utilization

40 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 40 4.5 Monitor and Control Project Work This process is performed to monitor project processes associated with initiating, planning, executing and closing. Continuous monitoring gives the project team insight into the health of the project and identifies areas needing attention. *Source: PMBOK® p.94

41 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 41 4.5 Monitor and Control Project Work *Source: PMBOK® p.94

42 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 42 4.5 Monitor and Control Project Work Project management plan Constantly compare to original plan Work Performance Information: Schedule progress information Deliverables completed and not completed Rejected Change Requests Understand and communicate disposition

43 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 43 4.5 Monitor and Control Project Work Project management methodology Constantly compare to original plan PMIS: Use the system to measure and communicate Earned value management Understand how actions affect on the Project budget Expert Judgment: How do you avoid mistakes? Who has been here before?

44 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 44 4.5 Monitor and Control Project Work Recommended corrective actions: Documented to bring project into conformance Recommended preventative actions: Reduce probability of negative Forecasts: Estimates and predictions based on knowledge Recommended defect repair: Correct problems found in audits Requested Changes: Control and Insure they are beneficial

45 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 45 4.6 Integrated Change Control Process begins at project inception through completions. Projects rarely run exactly according to the plan. Identify if change is really needed Get needed changes approved Implement approved changes Maintain integrity of baselines Insure Scope, Cost, Schedule & Quality are integrated into change process, understand Risk

46 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 46 4.6 Integrated Change Control

47 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 47 4.6 Integrated Change Control Project management plan: Maintain baseline against which changes are compare Requested changes Insure they are needed Work performance information: Status of work being performed Requested changes Recommended preventative actions Understand & communicate impact

48 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 48 4.6 Integrated Change Control – Inputs Recommended corrective actions: Bring the project into conformance to original or approved project management plan Recommended defect repair: Corrections from inspections or audits Deliverables: Unique and verifiable results, capabilities, products or services as identified in in work packages, scope or statements of work

49 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 49 4.6 Integrated Change Control Project management methodology: Maintain baseline against which changes are compare PMIS Record your control process and report Expert judgment: Estimates and predictions based on knowledge gained in past projects

50 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 50 Change Control System – A collection of formal, documented procedures that define the steps by which official project documents may be changed. Defines levels of change Includes: A logging mechanism A tracking system An approval process with various types of changes 4.6 Integrated Change Control

51 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 51 Change Control System (PMIS) Change Control Board (CCB) Reviews all changes Approves or reject all change requests Chaired by the project manager Well defined responsibilities Approved by major stakeholders 4.6 Integrated Change Control

52 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 52 Configuration Management – A documented procedure to apply technical and administrative direction to: Identify and document the functional and physical characteristics of an item or system. Control any changes to characteristics. Record and report the change and status. Audit to verify conformance to requirements 4.6 Integrated Change Control

53 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 53 Configuration Management A subset of Change Control Used to ensure that the product or service description is correct and complete. Manages the product or service configuration and any changes to it. 4.6 Integrated Change Control

54 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 54 Performance Reporting Processes Techniques such as Earned Value Analysis Used to measure variances to the plan Identifies areas to apply corrective action 4.6 Integrated Change Control

55 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 55 4.6 Integrated Change Control Approved change requests Includes signatures and communication to the Stakeholders Rejected change requests Communication to all Stakeholders Project management plan Updates Approved corrective action Documented and communicated

56 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 56 4.6 Integrated Change Control – Outputs Approved preventative actions Insure stakeholders and team members understand how to implement Approved defect repair Re-inspect for conformance Validate defect repair Insure cause is also addressed Deliverables Approved by Integrated Change Control process

57 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 57 Lessons Learned – Items to be documented so that they become part of the historical database for project within the organization, to include: The causes of variances The reasoning behind the corrective action Other types of lessons learned to insure it is not repeated 4.6 Integrated Change Control

58 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 58 4.7 Close Project Involves performing the project closure portion of the project management plan. In multi-phase projects, this process closes out the portion of the project scope and associated activities completed in this phase.

59 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 59 4.7 Close Project Administrative Closure Details performing the project closure portion of the project management plan Includes analysis, lessons learned and archiving of project information Contract Closure Formal, written, product and project verification including all signatures and payment records. Identifies final results and supporting details Can be repeated for each phase of large contracts

60 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 60 4.7 Close Project

61 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 61 4.7 Close Project Project management plan Compare plans with results Contract documentation Compare contract with results Enterprise environmental factors Understand all processes per requirements and culture Organizational process assets Understand utilization and resource reassignment

62 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 62 4.7 Close Project – Inputs Work performance information Compare plans with results Is everything complete and to Scope Deliverables Gate Reviews audited Deliverables confirmed Changes completed Everything signed off

63 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 63 4.7 Close Project Project management methodology Compare original to final PMIS Use system to confirm all deliverables Use as baseline for future projects Expert Judgment Compare to success of past projects Check Lessons Learned Build Knowledge Base

64 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 64 4.7 Close Project Administrative closure procedure Contains all activities and roles and responsibilities of project team Contract closure procedure Step by step methodology to insure conditions of contract are complete Final product, service or result Formal acceptance or handover Includes formal statement that all terms and requirements are met

65 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 65 4.7 Close Project – Outputs Organization al Process Assets Formal Acceptance Documentation Signatures on acceptance Project Files Finished and unfinished deliverables Completed and unfinished projects Project Closure Documents Transferred responsibilities and agreements Historical Information Build a Knowledge Base

66 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 66 Integration Management Successful integration management provides the framework for the Project Manager to take the correct action to keep the project on track when unexpected problems arise.

67 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 67 Characteristics of effective integration: Overlapping processes Effective change control and communications Reduced development time and cost Early and on-going involvement of all stakeholders Early visibility of results Early problem identification and resolution Use all relevant expertise at earliest meaningful time Integration Management

68 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 68 Integration Management Summary Know what components are included in integration management. Know the integration management processes and to which process group they belong. Understand the inputs, tools and techniques, and outputs for each of the integration management processes

69 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 69 Integration Management Summary Recognize that the project plan includes many components and these document the basis for all project decisions Use the information about integration management to understand the authority and limits to authority for the project manager, especially regarding project scope

70 v. 2.© Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 12/07/05 Integration - 70 Recognize that all changes to the project should be guided by a documented process in the project plan. Know Rita Mulcahy’s “QUICKTEST TOPICS” in the Integration Management, chapter 4 in the PMP EXAM PREP. Integration Management Summary

71 v. 2. © Copyright and all rights reserved – 2005 PMI Mile Hi Chapter Questions ? Thank you 4. Project Integration Management


Download ppt "V. 2. © Copyright and all rights reserved – 2005 PMI Mile Hi Chapter 4. Project Integration Management PMP Prep Course Based on the PMBOK ® Guide 3 rd."

Similar presentations


Ads by Google