Structured / Unstructured Market Trials Weekly Update – Friday Meeting September 13, 2013
2
Call Reminders Please help to minimize disruptions: Mute your phones Do not dial-in from a recorded line Do not put the call on hold, even if you are on mute When asking a question on the phone, please state your name and the entity you represent 2
3
Agenda TCR Update (5 min) 9 – 9:05A Analysis Sept 2 – Sept 8 (30 min) 9:05 – 9:35A Settlements (15 min) 9:35 – 9:50A Announcements & Outstanding Questions (10 min) 9:50 – 10:A COP True-Up Report (10 min) 10 – 10:10A Commitment Parameters (20 min) 10:10 – 10:30A Look-Ahead Sept 16 – 22(15 min) 10:30 – 10:45A Updates (10 min) 10:45 – 10:55A Release Scorecard Migration Report Known Issues Log Questions (5 min) 10:55 – 11A 3
4
TCR Market Trials Submit Your Historical Peak Load Who: Only those MPs with NITS Service What: Historical Peak Loads (Load + Transmission Losses) for 2010, 2011 & 2012 for the historical coincident peak load for your system. Why: Validation purposes to compare against what we pull from settled EIS transmission settlements. When: by September 18, 2013 Go Live Planning TCR Go Live Discussion held on September 11th (CWG Meeting Materials)CWG Meeting Materials Publish Go/No-Go Data for CWG Review on October 3rd CWG Go/No-Go Recommendation Due on October 7th Go-Live team Decision on October 11th 4 Brett Crane
5
Phase 2 Monthly Processes Good Participation is Requested/Expected Allocation Nominations: Auction Bids/Offers: 5 September 1234567 891011121314 15161718192021 22232425262728 2930 9 1617 September 9 September 16-17, 23-24 August 123 45678910 11121314151617 18192021222324 25262728293031 27 2324 4 TCR Market Trials Brett Crane
6
Analysis: Sept 2 – Sept 8 6 Alan Adams Structured Market Trials Statistics posted the day after each OD Structured Market Trials Statistics spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder > Structured Market Trials Presentations, Statistics, MP Meetings Analysis of Sept 3, 4, 5, and 6 Operating Days posted Tues to spp.org Analysis spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder > Structured Market Trials Presentations, Statistics, MP Meetings
7
Market Settlement System (MSS) Known Issues KIL# 647 Determinant Report issue with DaMccHrlyPrc not producing for Sink Locations. Fix is expected to be installed in Production by September 16. Initial Settlement for 9-12 OD will include missing determinants. KIL# 659 Prevents RtSE5minQty/RtSELoss5minQty/RtResMtrHrlyQty from being mapped to the determinant reports for MP shadowing. Fix is expected to be installed in Production by September 16. Initial Settlement for 9-12 OD will include missing determinants. 7 Tony Alexander
8
Market Settlements Charge Types & Scenarios How will MPs hit Charge Types and Scenarios? Settlements will provide the Market Operators a list of MPs that have not hit certain Charge Types and Scenarios. The Market Operators will work with MPs to submit the offers that would trigger the Scenario(s). Scenarios will be triggered on Tuesday, Wednesday, or Thursday Operating Dates. 8 Tony Alexander
9
Market Settlements Charge Types & Scenarios 9 SCENARIOSPLAN FOR HITTING DURING SMT ‘Base’ Energy and Operating Reserve Settlement Settlements will identify missing MPs. Market Operators will work with these MPs to trigger this scenario one-by-one by 9/30. Make-Whole PaymentWaiting on Commitment Data to pass through to Settlements. Regulation Non-PerformanceWaiting on Commitment Data to pass through to Settlements Contingency Reserve Deployment Failure Settlements will identify missing MPs. Market Operators will work with these MPs to trigger this scenario one-by-one by by 9/26. Day Ahead Non-Asset Energy This Scenario requires an Import, Export, or BSS. Some MPs will not have these types of transactions so this Scenario is optional. Real Time Non-Asset Energy This Scenario requires an Import, Export, or BSS. Some MPs will not have these types of transactions so this Scenario is optional. ‘Base’ Energy Import/Export This Scenario requires an Import, Export, or BSS. Some MPs will not have these types of transactions so this Scenario is optional. Energy Import/Export – Make Whole Payment DistributionWaiting on Commitment Data to pass through to Settlements. Real Time Regulation Adjustment Settlements will provide the Market Operators a list of MPs that have not hit this scenario. Market Operators will work with these MPs to trigger this scenario on 9/16. Out Of Merit Energy and ReserveMarket Operations triggered OOME scenarios for all MPs on 9/11. ‘Base’ Virtual Energy TransactionAfter Scenario 3 on 9/23, we should hit a number of these. ‘Base’ TCR Auction Settlements This Scenario requires a TCR Auction transaction. Some MPs will not have these types of transactions so this Scenario is optional. TCR Auction Settlement - End of Month This Scenario requires a TCR Auction transaction. Some MPs will not have these types of transactions so this Scenario is optional. ‘Base’ TCR Settlement This Scenario requires a TCR transaction. Some MPs will not have these types of transactions so this Scenario is optional. TCR Settlement - End of Month This Scenario requires a TCR transaction. Some MPs will not have these types of transactions so this Scenario is optional. Tony Alexander
10
Settlements Charge Type Scorecard Starting with the 9/20 Scorecard: The status will be Green when an MP has hit a Charge Type or Scenario 1 time. Charge Type status by Market Participant. Ability to view MP Charge Types by OD. Scenario status by Market Participant. Scenario to Charge Type Mapping added. 10 Tony Alexander
11
Market Settlements Dispute Submission All MPs need to submit a dispute. Readiness Metric - STL-05: Submit Dispute Market Participants have the ability to submit disputes. RMS Link https://spprms.issuetrak.com/login.asphttps://spprms.issuetrak.com/login.asp Actual disputes will be counted as passed. You can submit a test dispute by typing “Test Dispute” in the subject line and filling in all required information. Submitting one dispute is all it takes to pass (Actual or Test). 11 Tony Alexander
12
Announcements & Outstanding Questions SPP is adding a Daylight Savings Time Scenario to be executed Nov 3 SPP will notify MPs when Scenario Document is posted to spp.org Scenarios 3 and 3A will not be executed in September as planned SPP will notify MPs as soon as Scenarios 3 and 3A are rescheduled Questions on Tag Validation Criteria for MT Testing?Tag Validation Criteria for MT Testing spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder > Structured Market Trials Reference Documents Daily Calendar – DA Market Operating Day clarification DA Operators work Monday – Friday; therefore, Results in ‘supported’ solutions are posted for OD s Tuesday – Saturday All of the actual DA work activity occurs Monday – Friday 12 Ginny Watson / Jeff Fruit
13
COP True-Up Report 13 Gary Cate Temporary work around for the Commitment history that is not being adequately displayed in the Markets UI Emailed daily around midnight Contains previous 24 hour’s commitments Captures data points that Participants need to determined the commitment times and reasons for resources
14
Sample COP True-Up Email and Report 14 Gary Cate PARTICIPANTNAMEASSETOWNERNAMERESOURCEASSETNAMEEFFECTIVETIMETERMINATIONTIMECASETYPEACTIONACTIONTIME GoodMPGoodAOGoodAsset'2013-09-11 00:00:00''2013-09-11 01:00:00'DAMKTCOMMIT'2013-09-10 16:00:16' GoodMPGoodAOGoodAsset'2013-09-11 01:00:00''2013-09-11 02:00:00'DAMKTCOMMIT'2013-09-10 16:00:16' GoodMPGoodAOGoodAsset'2013-09-11 04:00:00''2013-09-11 05:00:00'DAMKTCOMMIT'2013-09-10 16:00:16' GoodMPGoodAOGoodAsset'2013-09-11 05:00:00''2013-09-12 00:00:00'DAMKTCOMMIT'2013-09-10 16:00:16' GoodMPGoodAOGoodAsset'2013-09-11 02:00:00''2013-09-11 04:00:00'DA_RUCCOMMIT'2013-09-10 18:47:42' GoodMPGoodAOGoodAsset'2013-09-11 00:00:00''2013-09-11 10:00:00'TRUE_UPCALLOFF'2013-09-10 23:20:57' GoodMPGoodAOGoodAsset'2013-09-11 22:00:00''2013-09-12 00:00:00'TRUE_UPCALLOFF'2013-09-10 23:20:57' GoodMPGoodAOGoodAsset'2013-09-11 10:00:00''2013-09-11 11:00:00'TRUE_UPCALLOFF'2013-09-11 07:35:11'
15
COP True-Up Report Column Definitions 15 Gary Cate ASSETOWNERNAME:AO Name RESOURCEASSETNAME:Asset Name EFFECTIVETIME:Commit/Decommit Start Time TERMINATIONTIME:Commit/Decommit End Time CASETYPE: Will be one of: "DAMKT" - Day Ahead Market committed / decomitted this resource "DA_RUC" - Day Ahead RUN committed/decommited this resource "TRUE_UP" - COP True Up committed/decommitted this resource ACTION: Will be one of: "COMMIT" - Resource was committed "CALLOFF" - Resource was decommited ACTIONTIME:Time notification was created
16
Resource Offer Commitment Parameters 16 Commitment Parameters Presentation Commitment Parameters Presentation posted to spp.org: spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder > Structured Market Trials Reference Documents Carrie Simpson
17
Look-Ahead: Sept 16 – Sept 22 17 Sept 16 – Sept 22 Daily Calendar Sept 16 – Sept 22 spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder Includes some Settlements Dates. All details on Settlements Calendar marketplace.spp.org > Public > Settlements > CalendarsSettlements Calendar Scheduled Scenarios 16.1 DA Offer Curve Mitigation 16.2 RUC Offer Curve Mitigation 16.3 RTBM Mitigation 31.0 Block Demand Response Official Operating Days Monday - Friday Friday Maintenance Saturday reserved for MP Testing Ginny Watson
18
16.1 DA Offer Curve Mitigation Scenario Description Offer Curve Subject to Mitigation –Mitigated offers for Energy, Start-up and No-Load product shall be submitted on a daily basis by the MP in accordance with the Mitigated Offer Development Guidelines. –Mitigated offers may be updated up to 11A on the day before the OD for use in the DA Market –MPs should submit Mitigated Offers for Energy, Start-up and No-Load such that each offer type is subject to mitigation by SPP 18 Alan Adams
19
16.1 DA Offer Curve Mitigation Expected Result SPP will apply mitigation measures by replacing the Energy, Start-up and No-Load offer with the mitigated offer if: –The Resource’s Energy, Start-up, No-Load Offer exceeds the applicable threshold; and –The Resources is subject to mitigation measures; and –The Resource fails the Market Impact Test An Energy Offer below $25/MWh will not be subject to mitigation measures. 19 Alan Adams
20
16.1 DA Offer Curve Mitigation MP Activities *Applicable to MPs with Resources Submit Energy, Start-up, and No-Load offers for at least one Resource such that the difference between the Normal Offer and the Mitigated Offer exceeds the threshold as described in the following 2 bullets: –The Energy Offer Curve threshold is a 25% increase above the Mitigated Energy Offer –The Start-Up and No-Load Offer threshold is a 25% increase above the Mitigated Offer for the applicable offer –The Energy Offer Price must be at least $25 or higher After DA Market results are posted, MP should confirm that resources cleared in DA reflect the mitigated offer for each product as applicable –Only committed resources will be mitigated Verify mitigated flag / notification in either the; –MUI under the Mitigated column of the Resource Offers tab > Market Results > Commitments –XML / API notifications 20 Alan Adams
21
16.1 DA Offer Curve Mitigation MP Activities *Applicable to MPs with Load Continue to submit Production-Like demand bids for the MPs expected forecast of the Demand 21 Alan Adams
22
16.2 RUC Offer Curve Mitigation Scenario Description RTBM Mitigated offers for Energy, Start-up and No-Load product shall be submitted on a daily basis by the MP in accordance with the Mitigated Offer Development Guidelines. –Mitigated offers may be submitted up to 1700 hours or one hour following the posting of the DA Market Results –MPs should submit RTBM Offers for Energy, Start-up and No-Load such that each offer type is subject to mitigation by SPP 22 Alan Adams
23
16.2 RUC Offer Curve Mitigation Expected Result SPP will apply mitigation measures by replacing the Energy, Start-up and No-Load offer with the mitigated offer if: –The Resource’s Energy, Start-up, No-Load Offer exceeds the applicable threshold; and –The Resources is subject to mitigation measures; and –The Resource fails the Market Impact Test –The START/STOP notification in the Market User Interface will indicate the Resource has been mitigated An Energy Offer below $25/MWh will not be subject to mitigation measures. 23 Alan Adams
24
16.2 RUC Offer Curve Mitigation MP Activities *Applicable to MPs with Resources Submit Energy, Start-up, and No-Load offers on a resource with a DA Market Commit Status of “Not Participating” such that the difference between the Normal Offer and the Mitigated Offer exceeds the threshold as described below: –The Energy Offer Curve threshold is a 25% increase above the Mitigated Energy Offer for all Resources –The offer threshold for the Start-up Offer is a 25% increase above the Mitigated Offer for the applicable Start-up Offer –The offer threshold for the No-Load Offer is a 25% increase above the Mitigated Offer for the applicable Start-up and No- Load Offer Submit RMS ticket titled “Scenario 16.2” indicating the unit chosen for the scenario for your organization. Following execution of the Day-Ahead RUC, MPs who submitted offers subject to mitigation and received a DARUC commitment for that Resource should confirm that their Resource received a mitigation START/STOP. –This can be performed by checking the Mitigation flag in the START/STOP notifications in the Market User Interface (MUI) (Between 1900-2000 CPT). The START/STOP notifications are located on the Resource Offers tab > Date > Market Results > Commitments > View 24 Alan Adams
25
16.3 RTBM Mitigation Scenario Description Mitigated offers for Energy shall be submitted for each OD in accordance with the Mitigated Offer Development Guidelines. MPs should offer Energy such that it is subject to mitigation by SPP Expected Result SPP will apply mitigation measures by replacing Energy Offers with the mitigated offer if: –The Resource’s Energy Offer exceeds the applicable Behavior Test threshold; and –The Resources is subject to mitigation measures; and –The Resource fails the Market Impact Test An Energy Offer below $25/MWh will not be subject to mitigation measures. 25 Alan Adams
26
16.3 RTBM Mitigation MP Activities *Applicable to MPs with Resources Submit at least one Energy offer for an online Resource such that the difference between the normal offer and the Mitigated Offer exceeds the 25% threshold –SPP requests that several of the highest cost resources that are online will have energy offers that exceed the threshold Following execution of the RTBM SCED, MPs should confirm that their resource’s corresponding Energy Curves are mitigated appropriately via user interfaces and indicators on XML dispatch instructions 26 Alan Adams
27
31.0 Block Demand Response Scenario Description Verify functionality specific to BDRs. BDRs achieve their response through reduction of the effective load. BDRs are dispatched in hourly blocks according to their existing COP dispatch MW and are not dispatched in RTBM Expected Result BDR Block Energy Dispatch: –Committed BDRs should be able to be dispatched for energy in hourly blocks. Energy dispatch should not exceed the block level initially committed. BDR Reserve Clearing: –Eligible for contingency reserve clearing when qualified and committed. –Ineligible for offline supplemental reserve clearing. Non-Committed BDR Dispatch: –BDRS without a COP commitment should be dispatched to 0 MW. 27 Alan Adams
28
31.0 Block Demand Response MP Activities *Applicable to MPs with BDR resources Verify that BDRs have valid offer data for all products –Offers should be such that the BDR will clear contingency reserves if qualified. –Offer should include a small fixed offer for contingency reserves with a monetary offer that could allow more contingency reserves to clear above their fixed amount. Ensure that all required real-time measurements are defined and being submitted to SPP via ICCP Submit hourly DRL forecasts when required for BDR resources Submit meter data for time that BDR is dispatched –Some hours have the meter data be greater than the hourly DRL forecast –Some hours have the meter data be less than the hourly DRL forecast 28 Alan Adams
29
Release Scorecard 29 Release ScorecardRelease Scorecard posted to spp.org: spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder Ginny Watson
30
Migration and Maintenance Report 30 Migration and Maintenance Report Migration and Maintenance Report posted to spp.org spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder MT Tagged Transactions MT Tagged Transactions documentation posted to spp.org spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder > Structured Market Trials Reference Documents Wendy Reynolds
31
Known Issues Log 31 Market Trials Known Issues Log Market Trials Known Issues Log posted to spp.org spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder Leann Poteet Issue #ComponentSynopsisSeverity 550 Markets Notifications Mitigation flag not set correctly on commitments that are mitigated. This is an issue in the API and Notifications. Severity 2: High 709 Markets Systems Capacity Shortage: Ramp Rate VRL not being applied correctly in the First online interval in DAMKT Severity 2: High 710 Markets Systems Resources with Eco Min = Eco Max not eligible for Dispatch or Commitment in Cap Shortage Severity 2: High 711Markets UI Markets UI/API should reject Eco Min and Eco Max equal to zero. Severity 3: Medium
32
Scheduled Scenarios 32 Sept 16 – Sept 20 16.1 – DA Offer Curve Mitigation 16.2 – RUC Offer Curve Mitigation 16.3 – RTBM Mitigation 31.0 – Block Demand Response Sept 23 – Sept 27 21.0 – RTBM Scarcity Shortages 15.0 – Commitment Mismatch Ginny Watson
33
Market Trials Useful Resources SMT Hotline: 501-482-2222 for critical & high issues Mon-Fri 8A – 5P Please submit all other inquiries via the Request Management System (RMS)Request Management System (RMS) Settlements Calendar marketplace.spp.org > Public > Settlements > Calendars Integrated Marketplace Market Trials Project Documentation Folder spp.org > Integrated Marketplace > Market Trials > Structured/Unstructured Test > Integrated Marketplace Market Trials Project Documentation Folder Documents found here include: Daily Calendar, Release Scorecard, Migration Report, Known Issues Log, Market Participant Guidehere SMT Presentations, Statistics, MP Meetings Folder SMT Reference Documents Folder New! Tag Validation Criteria for MT TestingTag Validation Criteria for MT Testing SMT Scenarios Folder New! SMT Scenarios ScheduleSMT Scenarios Schedule Change Tracker spp.org > Integrated Marketplace > Marketplace Documents 33