Presentation is loading. Please wait.

Presentation is loading. Please wait.

DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES.

Similar presentations


Presentation on theme: "DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES."— Presentation transcript:

1 DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES

2 DR. Nabil Dmaidi Purpose of An Estimate n To know in advance the expected cost in varying degree of accuracy, at different phases of the project.

3 DR. Nabil Dmaidi Owner's Purpose of Estimate 1.Making investment decision in the conceptual stage. 2.Negotiate and finalize the contract at the implementation phase. 3.To implement cost control measures.

4 DR. Nabil Dmaidi Contractor’s Purpose of Estimate 1.Determine project cost and profit. 2.To Implement cost control measure. 3.To develop data base that can be used for future project.

5 DR. Nabil Dmaidi Engineer’s Purpose of Estimate 1.Provide the owner with probable estimate. 2.Evaluate alternatives.

6 DR. Nabil Dmaidi Comparison of Contractor’s and Engineer’s Estimator n Contractor’s Estimator – Determines actual cost of project for bidding purposes. – Has detailed company cost data for labor and equipment. – Knows which construction methods are to be used. – Has knowledge of actual materials’ suppliers to be used and quantity discount prices. n Engineer’s Estimator – Determines expected cost. – Does not know who will receive award, therefore does not know contractor’s exact resource costs. Does not know actual labor rates. – Must assume probable construction methods to be used. – Does not know who project supplier will be. Must use local list prices.

7 DR. Nabil Dmaidi 1. Preliminary 2. Unit price 3. Assembly or Conceptual Cost 4. Detailed estimate n Each phase of a project life cycle requires a different type of estimate--each estimate requires different types of information. TYPES OF ESTIMATES 20% 15% 10% 5% Accuracy within Preliminary Unit Price Assembly Detailed 5min1hour1day3 weeks Time 2 Million dollars building

8 DR. Nabil Dmaidi 1. Preliminary Estimate “Order of Magnitude” n A cost prediction based solely on size and/or capacity of a proposed project. n Before any engineering or design is completed. n Rely on broad data from already executed similar project – relate cost in dollar to the main capacity/size parameter n number of beds in hospital n square feet of office space n number of students in school

9 DR. Nabil Dmaidi Preliminary Estimate (cont  ) n Advantageous – Allows a quick determination of the feasibility of a project – A quick screening on alternatives, etc. (e.g., should it be a concrete building or a steel building !). n Purpose: 1. Ranking alternatives 2. Evaluate economics and financial feasibility 3. As a check on more detailed estimates

10 DR. Nabil Dmaidi Example of Preliminary Estimates n Parking Garage $15.0/sq. ft or $4500/parking space n High School $80 to 110/sq. ft or $40,000/ student seat n Medical Centers $90 to 130/sq. ft

11 DR. Nabil Dmaidi 2.Unit Price Estimate n Unit prices are obtained from data on projects already performed. – Cost of labor, material, and equipment for all units of work are added together and divided by the number of units involved.

12 DR. Nabil Dmaidi Example of Unit Price Estimating Technique for Heavy Construction ____________________________________________________________ Work Item Estimated QuantityUnit PriceTotal ____________________________________________________________ Site Preparation 50,000 sq. yd$ 7 $ 350,000 Earth Excavation 100,000 cu.yd.$ 12 $ 1,200,000 Paving 50,000 sq.yd.$ 8 $ 400,000 Total bid price $ 1,950,000 ____________________________________________________________

13 DR. Nabil Dmaidi 3.Assembly or Conceptual Estimate n Performed when conceptual design decisions are being made. n Work package concept can be used to determine the element or assembly to be studied n We need a breakdown of cost of a completed project into its functional elements to: 1.Find the relationship between element cost and project cost 2.Distribution of cost between constituent elements (sq. feet of _____)

14 DR. Nabil Dmaidi Elemental Estimate Analysis Gross floor Area = 250,000 ft 2

15 DR. Nabil Dmaidi 4.Detailed (Definitive )Estimate n Prepared after drawings and specification are completed. n Requires a complete quantity takeoff based on drawing and the complete set of contract documents n Need information on labor rate "productivity", material cost, cost of renting or purchasing equipment

16 DR. Nabil Dmaidi Variation Factors in Estimating 1. Time n We base our estimate on the cost of existing projects that were built in the past n Price-level changes over time n We need to project costs of future projects n Many organizations publish construction cost data on regular basis: – US Department of Commerce – US Department of Labor – ENR – Turner Construction Company – Handy-Whitman Utilities

17 DR. Nabil Dmaidi 1. Time (Cont.) Cost Indices n Published by R.S. Means and ENR n Used to update old cost information Uses 1.To update known historical costs for new estimates 2.To estimate replacement cost for specific assets 3.To provide for contract escalation Limitations 1.They represent composite data, average of many projects. 2.They fail to recognize technological changes. 3.There is a reporting time log.

18 DR. Nabil Dmaidi To update old cost information to current date cost of new facility = cost of old facility x To predict future cost F = P (1 + i) F = future cost P = present cost i = predicted rate of cost escalation per period n = number of periods (years) new cost index old cost index n

19 DR. Nabil Dmaidi 2. Location n Some factors affecting cost in different locations are: 1. Transport cost 2. Taxes 3. Labor supply and local productivity 4. Codes and local inspection n Construction costs also vary in different regions of the USA. n ENR and Means publishes periodically the indices of local construction costs in the major cities.

20 DR. Nabil Dmaidi 2. Location (Cont.) ENR Regional Index CityCost Index Boston1120 Chicago1400 New York1700

21 DR. Nabil Dmaidi 3. Size n As the quantity built increases, the unit cost decreases: Size Factor = n UCM = Unit Cost Multiplier UCM = SF Proposed Size Comparison Size E - 1

22 DR. Nabil Dmaidi Table for Unit and Total Cost Multipliers

23 DR. Nabil Dmaidi Chart to Convert Unit Prices

24 DR. Nabil Dmaidi Chart to Convert Total Project Cost

25 DR. Nabil Dmaidi 4. Shape Wall height = $10 x 160 x 10= $16,000 = $10.00 of floor area Bldg. A Wall cost = $10 x 160 x 10= $16,000 = $10.00 of floor area Bldg B Wall cost = $10 x 180 x 10= $18,000 = $11.25 of floor area Bldg A Area = 15ooft 2 Perimeter = 160ft 30’ 50’ Bldg B Area =1500ft 2 Perimeter= 150ft 40’ 10’ 15’

26 DR. Nabil Dmaidi n Increased productivity by doing repeated work. – Detailed analysis will be discussed later. 5. "Learning Effect"

27 DR. Nabil Dmaidi 6. Other Factors n Hard to quantify but should be evaluated: – Quality – Soil condition – Weather Condition – Competition – Productivity


Download ppt "DR. Nabil Dmaidi F ACTORS THAT D ETERMINE V ARIATION IN E STIMATES."

Similar presentations


Ads by Google