1
The Network Diagram
2
When to Do What? Carrying out one activity after the other may result in project completion, but it will take the longest possible time If any activities can be worked on concurrently then the project duration will be shortened How to build the project schedule? COPYRIGHT TOM SULZER © 2016
3
Gantt Charts Activities are represented by horizontal bars along a time line Bar length indicates the duration of the activity Useful for simple projects Insufficient information is used for efficient planning t COPYRIGHT TOM SULZER © 2016
4
Network Diagram Contains information on Activity precedence Activity dependence Start times Finish times Embodies Constraints COPYRIGHT TOM SULZER © 2016
5
Information Required Each activity (except for the start and ending activities) must have a predecessor and a successor Activities may have dependency relationships between them Activity durations and other time-related data COPYRIGHT TOM SULZER © 2016
6
Dependency Activity 1 Activity 2 Activity 1 Activity 2 Activity 1 Activity 2 When 1 finishes, 2 can start When 1 finishes, 2 may finish When 1 starts, 2 may start When 1 starts, 2 may finish COPYRIGHT TOM SULZER © 2016
7
Precedence Activity 1Activity 2 Activity 1 Activity 2 Activity 3 2 follows the end of 1 3 follows the end of 1 and 2 2 and 3 follow the end of 1 COPYRIGHT TOM SULZER © 2016
8
Constraints Technical constraints – force predecessor- successor relationships with finish-start dependencies Management constraints – manager forces finish-start on two activities rather than concurrency because of a need to review one activity before using it in the other COPYRIGHT TOM SULZER © 2016
9
The Schedule Activity A D Activity B D Activity C D Activity D D Activity F D Activity E D EF ES LS LF COPYRIGHT TOM SULZER © 2016
10
Durations Activity A 2 Activity B 4 Activity C 6 Activity D 5 Activity F 2 Activity E 3 EF ES LS LF COPYRIGHT TOM SULZER © 2016
11
Forward Pass to Calculate ES, EF Activity A 2 Activity B 4 Activity C 6 Activity D 5 Activity F 2 Activity E 3 2 6 8 13 11 15 1 39 39 14 LS LF COPYRIGHT TOM SULZER © 2016
12
Backward Pass to Calculate LS, LF Activity A 2 Activity B 4 Activity C 6 Activity D 5 Activity F 2 Activity E 3 2 6 8 13 11 15 1 39 39 14 1 59 3 11 14 2 813 8 15 COPYRIGHT TOM SULZER © 2016
13
Example: Activity A 2 Activity B 2 Activity D 3 Activity C 5 Activity F 4 Activity E 3 24 7 12 10 16 138 58 13 1 38 5 10 13 2 412 7 16 COPYRIGHT TOM SULZER © 2016
14
Example – How did we get the #s? Activity A 2 Activity B 2 Activity D 3 Activity C 5 Activity F 4 Activity E 3 24 7 12 10 16 138 58 13 1 38 510 13 2 412 7 16 COPYRIGHT TOM SULZER © 2016
15
Computing the Slack A (S=0) 2 B (S=2) 4 C (S=0) 6 D (S=0) 5 F (S=0) 2 E (S=2) 3 2 6 8 13 11 15 1 39 39 14 1 59 3 11 14 2 813 8 15 Activity Slack = LF-EF (or LS-ES) COPYRIGHT TOM SULZER © 2016
16
Computing Slack Cont. Activity A 2 Activity B 2 Activity D 3 Activity C 5 Activity F 4 Activity E 3 24 7 12 10 16 138 58 13 1 38 510 13 2 412 7 16 (S=0) (S=2) (S=0) COPYRIGHT TOM SULZER © 2016
17
The Critical Path Activity A 2 Activity B 2 Activity D 3 Activity C 5 Activity F 4 Activity E 3 24 7 12 10 16 138 58 13 1 38 510 13 2 412 7 16 (S=0) (S=2) (S=0) COPYRIGHT TOM SULZER © 2016
18
Using the Critical Path Note that a delay in an activity on the Critical Path will delay the whole project Note that activity durations are estimates: near critical path activities (with little slack) can become critical as duration time becomes better known COPYRIGHT TOM SULZER © 2016
19
Adding in Lag and Reserves Waiting time (for a third party to respond/deliver) can be modeled as an activity Do not pad activity estimates (work expands to fill the time allocated) Make final activity of project the “management reserve” – time to controlled and monitored by the project manager. COPYRIGHT TOM SULZER © 2016
20
Project Software Software can manage estimates of durations with variability (Earliest, Most Probable, Worst) Allows computation of ‘probability” of finishing project in a certain time. COPYRIGHT TOM SULZER © 2016
21
Next time Network Diagram Analysis