Download presentation
Presentation is loading. Please wait.
Published byAnnabella May Modified over 8 years ago
1
Public Information Meeting St. George Road - Oak Hill Road Intersection Reconstruction Project
2
Project History Project originated from traffic studies done by the Evansville Urban Transportation Study (EUTS) Traffic counts that were completed in 1999 and 2002 showed that a traffic signal was justified at the intersection Traffic increased by 9.7% on Oak Hill between 1999 and 2002
3
Project Development Left turn lane needed for northbound left turns from Oak Hill to St. George in addition to traffic signal
4
Project Development Large culvert structure south of Keystone Hills Drive needs replaced
5
Project Development – Culvert Replacement
6
Project Development – Drainage Improvements Storm water from 24” pipe from Ivy Meadow Subdivision drains to 15” and 18” pipes on Oak Hill Road
7
Project Limits
8
Project Development Design contract signed with RQAW Corporation on Oct. 21, 2002 Survey work completed in Nov. 2002 Preliminary plans submitted to the county in May 2003 Copies of plans sent to affected property owners in May 2003
9
Project Development Right of way engineering and acquisition began in February 2004 Right of way acquisition completed in December 2004 Final draft of plans submitted to county in March 2005 Final plans submitted on April 25, 2005
10
Evaluation of Maintenance of Traffic Plan Original plans showed two road closure periods on Oak Hill Road; estimated project completion was October 2005 based on that plan
11
Evaluation of Maintenance of Traffic Plan Two options were evaluated to attempt to leave Oak Hill Road open during construction – a temporary runaround and a temporary traffic signal
12
Temporary Runaround Design INDOT design standards require 2 12’ lanes with 6’ shoulders
13
Temporary Runaround Options Construction of temporary runaround on west side of Oak Hill not possible due to proximity of houses to Oak Hill
14
Temporary Runaround Options Temporary runaround would fit on the east side of Oak Hill; safety concerns do not make it practical; road closure would still be needed to replace large culvert
15
Temporary Traffic Signal A temporary traffic signal could be installed at both ends of the project; safety concerns due to all of the driveways in between the signals
16
Project Schedule April 26, 2005 – County Commissioners approve advertising of notice to bidders April 29, 2005 – First advertising date May 6, 2005 – Second advertising date May 17, 2005 – Open bids May 24, 2005 – Award Bids
17
Project Schedule May 25, 2005 – First day that Oak Hill Road is allowed to be closed May 28, 2005 – Scheduled completion date of INDOT project on Highway 41 August 5, 2005 – Final day of road closure for Oak Hill Road; St. George may remain closed September 16, 2005 – Project completion date
18
Contract Provisions Contractor will receive $1,000.00 per day bonus for each day prior to Aug. 5 that Oak Hill is opened (up to a maximum of $20,000.00) Contractor will be assessed liquidated damages of $1,000.00 for each day that Oak Hill remains closed past Aug. 5 The large culvert structure has already been ordered by Vanderburgh County
19
Detour Routes Signed detour routes will be Heckel Road, Green River Road, Lynch Road, and Hitch Peters Road
20
Other Upcoming Projects Green River Road between Lynch Road and Hirsch Road Project will consist of widening Green River Road to four lanes and elevating Green River Road out of flood plain Estimated bid date: Fall 2005
21
Other Upcoming Projects Green River Road – Millersburg Road Intersection Reconstruction Project will consist of adding turn lanes and installing a traffic signal Estimated bid date: Fall 2006
22
Other Upcoming Projects Oak Hill Road – Bergdolt Road Intersection Reconstruction Project will consist of adding turn lanes and installing a traffic signal Estimated bid date: 2007
23
Other Upcoming Projects Green River Road between Hirsch Road and Heckel Road Project will consist of widening Green River Road to four lanes and elevating Green River Road out of the floodplain; will also include new bridge over Pigeon Creek Estimated bid date: 2008
24
Contact Information County Engineering Dept. phone number: 435-5773 E-mail: jstoll@vanderburghgov.org
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.