(Integrated Coastal Zone Management Project) Department of Disaster Management Government of West Bengal.

Similar presentations


Presentation on theme: "(Integrated Coastal Zone Management Project) Department of Disaster Management Government of West Bengal."— Presentation transcript:

1 (Integrated Coastal Zone Management Project) Department of Disaster Management Government of West Bengal

2 Review of up-to-date status of Physical and Financial Progress

3 Project Overview State : WEST BENGAL District covered : SOUTH 24 PARGANAS Blocks covered (No. of sites): 1.Pathar Pratima (05 sites) 2.Basanti (05 sites) 3.Gosaba (07 sites) 4.Namkhana (03 sites) 5.Sagar (05 sites) Total 25 sites in 05 nos. Blocks Total Bid Amount: Rs. 105.40 crores World Bank share : Rs. 62 crores Total No. of Packages : 05 nos. (1 package for each block)

4 Key Agencies SPMU : Institute of Environmental Studies and Wetland Management (IESWM) under Department of Environment, Government of West Bengal. PEA ( for MPCS) : Department of Disaster Management, Government of West Bengal. Supervising Agency: PMGSY Divisions, South 24 Parganas Zilla Parishad Successful Bidder: Mackintosh Burn Ltd.

5 Important dates MOU signed between SPMU and PEA : 09.06.2010 CRZ Clearance for all 25 sites obtained : 15.09.2014 World Bank Clearance for DPR & Bid Documents: 29.09.2014 Bid floated : 27.11.2014 Contract signed with successful bidder : 24.09.2015 Notice to proceed with the work issued : 06.11.2015

6 Important dates Advertisement published for appointment of Construction Supervision Consultant : 01.01.2016 RFP for Construction Supervision Consultant published on : 15.04.2016 Pre proposal conference held on : 05.05.2016 Last date for submission of proposal : 25.05.2016 Expected date for contract negotiation : 20.06.2016 Expected date for commencement of service : 05.07.2016

7 Physical progress status as on 30.04.2016 Package No. - 1 (7 MPCS) Block - Gosaba

8 Location of MPCSType of Pile Date of Commencement Status as on 30.04.2016 Multipurpose Cyclone center at Pathankhali of Gosaba Block. Concrete Pile Foundation NA As per instruction of collage authority layout of new location completed procurement of material started.

9 Location of MPCS Type of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Sambhunagar of Gosaba Block. Ballah Pile Foundation 28.01.16 Casting of foundation Raft 100% completed.

10 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Santigachi, Lahiripur of Gosaba Block. Concrete Pile Foundation NA Pilling rig reached at site and pilling work started from 05.05.16.

11 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Rangabelia of Gosaba Block Concrete Pile Foundation 22.01.16 Vertical load test completed excavation of pile cap in progress.

12 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Safakachari N.C Memo F.P School of Gosaba Block Ballah Pile Foundation 02.03.16 100% ballah driving completed. Procurement of filling sand started.

13 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Mangal Chandra H.S of Gosaba Block Concrete Pile Foundation 4.04.16pilling work 50% completed.

14 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Gobindapur Jr.H.S of Gosaba Block Ballah Pile Foundation 11.01.16Sand filling completed.

15 Physical progress status as on 30.04.2016 Package No. - 2 (5 MPCS) Block - Basanti

16 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Harbhangi of Basanti Block Concrete Pile Foundation 17.02.16 Pilling work 94% completed

17 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Purandar of Basanti Block Ballah Pile Foundation 16.01.16 Reinforcement of raft foundation complete casting of raft foundation will be held very soon.

18 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Gadkhali of Basanti Block Ballah Pile Foundation 08.1.16 Beam up to EGL Level complete, Earth filling started very soon.

19 Location of MPCSType of Pile Date of Commencem ent Status as on 30.04.2016 Multipurpose Cyclone center at Birichibari of Basanti Block Ballah Pile Foundation 12.01.16 Beam up to EGL Level complete, Earth filling started very soon.

20 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Chunakhali of Basanti Block Concrete Pile Foundation 17.02.16 Arrangement of pile cap excavation are in progress.

21 Physical progress status as on 30.04.2016 Package No. - 3 (3 MPCS) Block - Namkhana

22 Location of MPCS Type of Pile Date of Comme ncement Status as on 30.04.2016 Multipurpose Cyclone center at Iswaripur of Namkhana Block. Concrete Pile Foundation N/A No accessable road at site

23 Location of MPCSType of Pile Date of Commenc ement Status as on 30.04.2016 Multipurpose Cyclone center at Debinibas of Namkhana Block. Concrete Pile Foundation 18.04.16 Earth work completed, Pile head braking 50% completed and P.C.C. 30% completed.

24 Location of MPCS Type of Pile Date of Commen cement Status as on 30.04.2016 Multipurpose Cyclone center at Rajnagar of Namkhana Block Ballah Pile Foundation 08.03.16 Casting of tie beam 60% completed column up to bottom +1500 level beam 30% completed and fillin of Finishrd Ground Level 80% complete.

25 Physical progress status as on 30.04.2016 Package No. - 4 (5 MPCS) Block – Pathar Pratima

26 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Devichalk veterinary at patharpratima Block Concrete Pile Foundation 07.01.16 Pile cap in progress

27 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Gangapur of Patharpratima Block. Concrete Pile Foundation 11.01.16 Arrangement of load test are in progress

28 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Daspur of Patharpratima Block. Ballah Pile Foundation 22.02.16 Sand filling completed.

29 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Lakshmijanardanpur of Patharpratima Block. Concrete Pile Foundation 11.01.16 Arrangement of load test are in progress.

30 Location of MPCSType of Pile Date of Commence ment Status as on 30.04.2016 Multipurpose Cyclone center at Indrapur of Patharpratima Block. Concrete Pile Foundation 15.02.16 Arrangement of load test are in progress.

31 Physical progress status as on 30.04.2016 Package No. - 5 (5 MPCS) Block – Sagar

32 Location of MPCSType of Pile Date of Comencem ent Status as on 30.04.2016 Multipurpose Cyclone center at Krishnagar of Sagar Block Ballah Pile Foundation 11.01.16 Column casting up to +1500 level completed.

33 Location of MPCSType of Pile Date of Comencem ent Status as on 30.04.2016 Multipurpose Cyclone center at Bishnupur of Sagar Block. Concrete Pile Foundation 07.01.16 5 nos pile cap casting completed.

34 Location of MPCSType of Pile Date of Comencem ent Status as on 30.04.2016 Multipurpose Cyclone center at Kashimara of Sagar Block. Ballah Pile Foundation 08.02.16 Sand filling complete.

35 Location of MPCSType of Pile Date of Comencem ent Status as on 30.04.2016 Multipurpose Cyclone center at Sumatinagar of Sagar Block Ballah Pile Foundation 19.01.16 Tie beam Up to Fineshed ground level completed.

36 Location of MPCSType of Pile Date of Comencem ent Status as on 30.04.2016 Multipurpose Cyclone center at Dablat of Sagar Block Concrete Pile Foundation 28.03.16 Pilling work 31% completed.

37 Financial Progress Mobilization advance allotted on 02.12.2015 in the tune of Rs. 5.27 crores as follows: 1.Basanti : Rs. 1.01 crore 2.Namkhana : Rs. 0.58 crore 3.Gosaba : Rs. 1.40 crores 4.Sagar : Rs. 1.13 crores 5.Pathar Pratima : Rs. 1.15 crores

38 Summary of Physical Progress of Work BlockTotal MPCS Contract Awarded Work Started Basanti 555 Gosaba 776 Namkhana 332 Pathar Pratima 555 Sagar 555 Total 25 23

39 Perspective View of Proposed MPCS

40