Eastham Water System Board of Selectmen Meeting April 25, 2016.

Similar presentations


Presentation on theme: "Eastham Water System Board of Selectmen Meeting April 25, 2016."— Presentation transcript:

1 Eastham Water System Board of Selectmen Meeting April 25, 2016

2 Items Spring-summer construction program Bid results for Contract 8 (SW area to Rt 6) Phase 1 budget status Meter procurement Ramping toward fall and operations startup

3 Spring Construction Activities: April Water Storage Tank Crews back onsite week of April 11 th Painting of the bowl (exterior) Raise the bowl – this week or next Painting of the interior Filling and testing – June/early July

4 Storage Tank – Exterior Painting

5 Well Station Buildings delivery: mid-June Installation completed: early July Startup testing: July Spring Construction Activities: April Well Fields

6 Water Main work completed Spring/Summer Work Punch list items Pavement settlement Loaming & Seeding Flushing and testing of water mains: July and August Service connections – Fall 2016 Spring Construction Activities: April Landfill Area

7 Work began week of April 4 Work zones North: Massasoit Rd to Salt Pond Road South: S. Eastham St to Rotary All water main work anticipated to be complete this Spring No work Memorial Day to Labor Day Spring Construction Activities: April Route 6

8 Return September 2016 to complete services once water is available Final paving Entire westbound (south) travel lane to be paved Spring 2017 (mill and overlay) Spring Construction Activities: April Route 6

9 Contractor – Robert B. Our Mid-Late May construction start Prioritize roads to beaches before summer season Spring Construction Activities: April Contract 7 - NW Area of Town

10 Contract 8: Southwest System Bids received April 14 th 5 bids received: $3.8 - $5.0 Million Estimate - $4.0M Recommended: RJV Construction Construction Start: mid-May

11 Phase 1 Budget Status

12 Phase 1 Funding DEP State Revolving Fund Continue to remain #1 on their funding list Principal Forgiveness on 2015 borrowing USDA-Rural Development Town awarded funding for non-SRF costs Low interest rate; 40 year term All Phase 1 costs have received special funding by Feds and State

13 Meter Procurement Qualifications Based Request for Proposals Deadline April 7: Five Proposals Received Basis: Automatic Meter Reading System, Water Meters and Meter Pits Highest Ranked Offeror: Range of Price Proposals: Recommendation for Award

14 Ramping Toward Operations Wellfield startup and testing - July Water main flushing and testing July and August Water, water everywhere Service connection coordination Public information sessions Letter to Homeowners coming soon!

15 Public Outreach & Information Eastham web page http://easthamwaterproject.weebly.com Eastham Water Projects Email Address: easthamwater@envpartners.com easthamwater@envpartners.com Eastham Water Project Phone Number 617-657-0279

16 DISCUSSION


Download ppt "Eastham Water System Board of Selectmen Meeting April 25, 2016."