T-76.115 Project Review MalliPerhe PP Iteration 3.11.2004
2
2 T-76.115 Project Review Agenda Project status achieving the goals of the iteration project metrics Work results presenting the iteration’s results Used work practices
3
3 T-76.115 Project Review Introduction to the project Goal of the project is to build a modeling tool for Configurable Software Product Families (CSPF) Customer is SoberIT An engineering tool Both the architectural and the feature-based view are modelled And the relations between the different entities Modeling tool must support the Kumbang language The customer already has a configurator tool for Kumbang
4
4 T-76.115 Project Review Introduction to the domain Software Product Family Products share common assets and architecture Configurable SPF significant part of the deployment process is done without adding new code by configuring existing assets Kumbang Synthesis of two earlier modelling languages
5
5 T-76.115 Project Review Status of the iteration’s goals Goal 1: Project planning OK, slight slipping from the deadline Goal 2: Understanding the domain OK, group members have studied the material provided by the customer Goal 3: Requirements specification OK Goal 4: Work and communication methods and environment PARTIAL, practices have been agreed upon, but their deployment is still in progress
6
6 T-76.115 Project Review Status of the iteration’s deliverables Project Plan OK, chapters 5.5, 5.1.10 and 5.1.11 were left out from the initial delivered version Requirements document OK Eclipse plugin technology assesment OK Glossary OK
7
7 T-76.115 Project Review Realization of the tasks Task durations were not estimated Observations Project plan 90 h (31 %) Lectures 43 h (15 %) Meetings 38 h (13 %)
8
8 T-76.115 Project Review Working hours by person Some hours from PP phase were moved to later iterations Realized hours in this iterationPlan in the beginning of this iteration Latest plan 290 40 50 40 Plan 286 47 43 48 32 38 36 Real 7 Rauli -4 Total 3 Matti -2 Mikko -8 Juha -2 Jukka -4 Antti 2 Antero Diff 42
9
9 T-76.115 Project Review Changes to the project Project started No major changes to the project template Glossary delivered as a separate document
10
10 T-76.115 Project Review Risks Significant risks have been identified and are being followed Major risks Communication problems with the customer and between group members Team does not react to risks Eclipse plugin technology is not suitable for the project Risks are followed in weekly meetings using a follow-up template Decision on the need for a corrective action
11
11 T-76.115 Project Review Project Stakeholders and staffing Project group Customer Mentor Most important project goals Compatibility with the Kumbang language Good expandability Good architecture High quality of code Learning something
12
12 T-76.115 Project Review Requirements Customer's requirements have been identified Quality over features and usability Basic use cases extracted Load/save/create models Modify components and features Browse the model Add bindings and constraints
13
13 T-76.115 Project Review Project practices Iteration planning Iteratative development Time reporting Trapoli Defect tracking Bugzilla and Excel Documenting Reviews Internal and project Requirements management Version control CVS Recording the meetings SEPAs Progress tracking and control Static methods Heuristic evaluation Refactoring
14
14 T-76.115 Project Review Tools Tools Eclipse CVS Bugzilla Trapoli JavaNCSS IRC/ICQ/Skype Audacity
15
15 T-76.115 Project Review Questions?