1 E & I 8 th Summit Shree Power Bwr 22-Jan-2015

2  25 MVA TR-1 testing carried out. TR-1 Power-Transformer-Testing-12jan15.pdf

3  Rewiring of booster fan VFD. TTPL 260KW VFD PANEL-Model.pdf12.pdf

4  Damage ESP coil replace with new coil instead of replacement of whole assembly,Saving of Rs1500 per coil  Aux reduction to 900 units.  DG set and lights provided for tower erection work in Bwr Khaas.  Review APC and APFC scheme of GPP-1  Under frequency setting of cement plant drives revised.

5  Safety mat at ACC mcc,SMP mcc & ht vfd room.  Isulation coating at LAVT,NGR & PCC area.  Fire alarm sytem in ACC,RO-2 & SMP mcc  Damaged ESP rapper coil replacement.  RLA of old equipments such as Transformer,CB,CT & PT  TR-1 132 KV breaker pole overhauling.

6 Shree Power RAS 22-Jan-2015

7  Best practices implemented.  Technical issues.  Future plans.

8  In gland seal valve set point was given through pneumatic PID controller for its operation.  Its failure will result in tripping of TG.  Now a bypass arrangement is made in which input signal is given through I/P converter and whose output is given to gland seal control valve.  Set point is given through PID which is programmed in DCS  Benefits:- Tripping can be avoided. Maintenance & spare cost of Controller is reduced

9  Fuji make CO analyzer is installed in Boiler-2.  In CO analyzer the value is oscillating form negative to positive and at last it is showing max value 9999.  The Analyzer also showing Error no-3 which means circuit is faulty.  Action taken :- Detector voltage set as per given voltage.  Counter set 40000  Sensor signal voltage set to1.8V.

10  Cooling coil replace with new one in Package AC-1  Its wiring modification done as per requirement  Protection circuit is now in line.

11  Check Charging and discharging cycle of Battery bank and replace faulty batteries.

12  Work permit and work clearance system implementation through ERP.

13  Life of FGD plant PH sensor.

14  Replace all JORC make ADV with Solenoid valve.  AC450 DCS upgradation.  GPP-1 UPS battery bank replacement.

15 THANKS