1 g2p/GEp Beamline Status Tim Michalski Project Lead

2 Overview Facilitate the design, procurement, and build of the beamline – up to the target chamber Experimental Plan Project Overview Project Status Project Challenges with risk mitigation

3 Experimental Plan Run # Beam EnergyBeam Current Target AngleTarget LocationSepta MagnetDumpTartget MaterialComments 12.2571 uAN/A87 cm upstreamN/A Hall A DumpN/AStraight Thru 22.25750-130 nA9087 cm upstreamg2pYes - 6 degLow Energy DumpNH3 32.25750-130 nA2087 cm upstreamGEpYes - 6 degLow Energy DumpNH3 42.257150 nA max9087 cm upstreamg2pYes - 6 degLow Energy DumpCarbon(?)Thru Target(?) - Optics 51.1571 uAN/A87 cm upstreamN/A Hall A DumpN/AStraight Thru 61.15750-130 nA9087 cm upstreamg2pYes - 6 degLow Energy DumpNH3 71.15750-130 nA2087 cm upstreamGEpYes - 6 degLow Energy DumpNH3 81.157150 nA max9087 cm upstreamg2pYes - 6 degLow Energy DumpCarbon(?)Thru Target(?) - Optics 91.7061 uAN/A87 cm upstreamN/A Hall A DumpN/AStraight Thru 101.70650-130 nA9087 cm upstreamg2pYes - 6 degLow Energy DumpNH3 111.70650-130 nA2087 cm upstreamGEpYes - 6 degLow Energy DumpNH3 121.706150 nA max9087 cm upstreamg2pYes - 6 degLow Energy DumpCarbon(?)Thru Target(?) - Optics 133.3551 uAN/A87 cm upstreamN/A Hall A DumpN/AStraight Thru 143.35550-130 nA9087 cm upstreamg2pYes - 6 degLow Energy DumpNH3 153.35550-130 nA2087 cm upstreamGEpYes - 6 degLow Energy DumpNH3 163.355150 nA max9087 cm upstreamg2pYes - 6 degLow Energy DumpCarbon(?)Thru Target(?) - Optics 173.35550-130 nA087 cm upstreamg2pYes - 6 degLow Energy DumpNH3 182.2571 uAN/AAt pivotN/A Hall A DumpN/AStraight Thru 192.25750-130 nA90At pivotg2pNo - 12.5 degLow Energy DumpNH3 202.257150 nA max90At pivotg2pNo - 12.5 degLow Energy DumpCarbon(?)Thru Target(?) - Optics 212.25750-130 nA90At pivotGEpNo - 12.5 degLow Energy DumpNH3 223.3551 uAN/AAt pivotN/A Hall A DumpN/AStraight Thru 233.35550-130 nA90At pivotg2pNo - 12.5 degLow Energy DumpNH3 243.355150 nA max90At pivotg2pNo - 12.5 degLow Energy DumpCarbon(?)Thru Target(?) - Optics 253.35550-130 nA90At pivotGEpNo - 12.5 degLow Energy DumpNH3 263.35550-130 nA0At pivotg2pNo - 12.5 degLow Energy DumpNH3 271.157***50-130 nA90At pivotNo – 12.5 degLow Energy DumpN/AOptics Transform *** - FZ1 and FZ2 in position for 2.2 GeV run, but with half field strength on FZs and Target magnets

4 Project Overview Design, procurement, component calibration and testing –Now through May, 2011 –Some components arrive after May Access to Hall A for installation –May 16, 2011 Installation completion – start of Physics –November 19, 2011

5 Project Status Regions 1 and 2 designs complete and material ordered Region 3 design complete – final review and procurement in coming weeks Calorimeter controller repaired and SW upgrades nearly complete I&C electronics designed and being built Addition of SR PS chamber, w/ cooling Resource planning integrated into 6MSD schedule Several changes to the run plan being evaluated

6 Project Challenges Instrumentation for Low Current data –BPMs and BCMs –Mitigation BPM – short M15 style, new electronics, tested BCM – new receiver FZ Magnet PS requirements evolving –Need up to 4 kG, requiring 231A for FZ1 –Need up to 8 kG, requiring 465A for FZ2 –Mitigation – assessed capabilities of magnet power supplies in Hall C – meet requirements – assembling spares

7 Project Challenges Acquisition of equipment from various sources –FZ magnets, corrector magnets, slow raster, new BPMs, power supplies, controllers –Mitigation – get control as soon as possible, test and calibrate early (before installation) Resurrection of Tungsten Calorimeter –Reposition in beamline, re-establish functionality, recalibrate –Mitigation – Controller extracted from Hall A, repaired, new PC104 SW nearly complete

8 Project Challenges Slow Raster issues raised at last collaboration meeting – waveform generators and “hole” in raster pattern –Mitigation – New function generator – Testing in Progress Installation at the same time as 12 GeV upgrades during 6 month down –Mitigation – tied to detailed 6MSD planning – all resources identified in schedules – have ~3 weeks float

9 Project Challenges Proposed changes to run definition – a) target height when upstream, b) 1.157 GeV run when target at pivot –Mitigation – Run new orbits on optics, address changes in FZ2 magnet position and articulating arm – defined impact to work and calendar time Maintain strong communication – highlight issues early!