Presentation is loading. Please wait.

Presentation is loading. Please wait.

Piero Belforte, HDT, MERITA project 2000: objectives, activities and results by Carla GIACHINO .

Similar presentations


Presentation on theme: "Piero Belforte, HDT, MERITA project 2000: objectives, activities and results by Carla GIACHINO ."— Presentation transcript:

1 MERITA: objectives, activities and results Carla GIACHINO H.D.T. Italia s.r.l.

2 ESPRIT E.S.D. The European Initiative for the Spread of Best Pratice in Design PROJECT N. 27413 MERITA

3 MERITA Methodology to Evaluate Radiaton in Information Technology Application TECHNICAL PRESENTATION

4 MERITA Effort in person months: –Bull IT: 24 p/m – H.D.T Italia: 14.5 p/m Type of the project: Demonstration project Duration: fithteen months May 98 to July 99 Project team: Bull IT S.p.A prime contractor: end-user H.D.T Italia s.r.l partner: software tool vendor

5 MERITA General overview Bull IT designs Unix Platforms with Risc Processor: –clock frequency>100 MHz In order to prevent some EMC problems: –prediction of radiated emission due to component current loop –Filtering optimization

6 MERITA Objectives Show the viability of a prototype tool, named PRESTO_POWER ver. 1.1 to perform: –predictive analysis and screening of EMC problems on PCB –extraction, analysis, improvement of critical paths –experimental validation of the tool Integration with the design methodology inside Bull IT

7 MERITA Main results Improvement of the design and analysis of PCB in IT application Product control at each development phase Viability of the prototype tool PRESTO_POWER test on an actual case

8 MERITA Project chart

9 MERITA Task 1: State of the art Objective: –knowledge of market solution & comparison with HDT Description: –prototype tool installation –training courses on SI, EMC, HDT methodology & products –case study demonstrated by HDT technical support Delivered result: –list of the tool advantages\disadvantages

10 MERITA Task 2: User’s requirements Objective: –list the user’s requirements on EMC to define a new methodology inside the company design flow Description: –EMC and methodology experts define the requirements of the prototype tool Delivered result: –list of requirements

11 MERITA Task 3: Prototype tool test & improvement Objective: –having a tool overcoming the identified problems identified during the testing phase Description: –several simulations have been run on a test board to: optimize the test board layout test the tool acting on its front end

12 MERITA Task 3: Prototype tool test & improvement (con’t) –this permits to: remove bugs fit the prototype tool improve the user interface through the user suggestions Delivered results: –list of bugs and features to be improved –comparison between simulations & measurements

13 MERITA Task 4:Test board realisation and comparison Objective: –Test of the prototype tool on an actual board Description: –The project team tested the software on an actual board and made comparison between measurement and simulation results Delivered result: –Report on comparison between measurement and simulation

14 MERITA Task 5: Design flow integration Objective: –definition of the prototype tool in the Bull methodology Description: –PRESTO_POWER inside Bull methodology –it is linked to the existing CAD/CAE methodology Delivered result: –PRESTO_POWER is included in the Bull methodology

15 MERITA Task 6: Dissemination Objective: –transfer the experience Description & delivered result: –prepare articles to be published on magazines –prepare papers for international symposium –create a mailing list of potential customers –prepare a brochure of PRESTO_POWER –present the results in a seminar –prepare the final report to submit to UE


Download ppt "Piero Belforte, HDT, MERITA project 2000: objectives, activities and results by Carla GIACHINO ."

Similar presentations


Ads by Google