Facilities Development Division California’s Building Department for Hospitals
Paul A. Coleman, Architect, Deputy Director Chris Tokas, S.E., Deputy Division Chief Gordon Oakley, Fire Marshal, Deputy Division Chief Roy Lobo, Ph.D., S.E., Principal Structural Engineer Gary Dunger, Manager, Electronic Services Glenn Gall, Supervisor, Building Standards Unit Nanci Timmins, Fire Marshal, Chief Fire Life Safety Officer CHA Update November 8, 2016
2
Relocations Update Sacramento Headquarters
Target move date Spring 2017 Lease signed Permit issued and TI construction began October 25, 2016
3
Relocations Update Sacramento Warehouse
Target move date late 2016 or early 2017 Lease signed TI work in progress Electrical and data New warehouse racks Electrical connection for fork lift charger 3 – 16,000 cfm min. evaporative coolers for warehouse 2 – 100,000 btuh min. space heaters for warehouse Supervisor space in office
4
Relocations Update Los Angeles Office
Target move date unknown at this time Most likely location at this time is: Wells Fargo South Tower 355 Grand Ave, Los Angeles floors 19 and 20 Architect currently working on drawings based on plans prepared by: Paul A. Coleman, Architect
5
Relocations Update
6
Relocations Update
7
Relocations Update Employee Break/Lunch Room Location
8
Plan Review and Field Performance Update
Facilities Development Division California’s Building Department for Hospitals Plan Review and Field Performance Update CHA Update November 8, 2016
9
Workload in Construction Values 2012+
63%
10
Workload in Construction Values for projects in Collaborative Plan Review - Custody Status
* *Projects Not in Collaborate or phase review
11
No. of Reviews - October 2016 65.5% 34.5% ≈ 63 reviews/day
12
No. of Reviews Year 2015 ≈ 64 reviews/day ≈ 61 reviews/day
63% 64.6% 37% 35.4% ≈ 64 reviews/day 2014 Numbers ≈ 61 reviews/day
13
Project Plan Review Data Analysis – October 2016
63% of the Plan Reviews are completed w/in 21 days or less 93% of the PAD Reviews are completed w/in 21 days or less Or 44% of Office Plan Approval Reviews S=144 or 12% of All Projects
14
Workload Summary/Performance
15
Workload in Construction Values for projects in the Plan Review State
Meeting with client required
16
Workload Summary/Performance
17
Number of Permits – 4th Qtr. 2010 thru 3rd Qtr. 2016
Statewide combined Office and Field Number of Permits Issued by Quarter 724 577 With SB 1838 Permits Without SB 1838 Permits
18
Workload in Construction Values for projects in Construction - % Completion
58% 32% 10% 50% 36% 14% (1st Qtr Numbers)
19
Number of SB 1838 Projects – 3rd Qtr. 2016
Statewide Number of SB 1838 EXEMPT Projects Approved by Quarter 113 44
20
Workload in Construction Values for projects in Pending Construction State By Region
21
Building Standards Update
Facilities Development Division California’s Building Department for Hospitals Building Standards Update CHA Update November 8, 2016
22
2016 California Building Standards Code Intervening Cycle Supplement
Part 1 – California Administrative Code Functional Program – Addition of Patient Safety Risk Assessment for Psychiatric services. Maintenance of existing sections Part 2 – California Building Code (CBC) Section – Maintenance of General Construction Items Section Telecommunication Rooms Section – Number of Operating Rooms CONT’D
23
2016 California Building Standards Code Intervening Cycle Supplement
Part 1 – California Administrative Code Section – Clarification of Cesarean Suite Requirements Section 1225 – Maintenance of Skilled Nursing Facility Requirements Section 1228 – New Section “Acute Psychiatric Hospitals” to address specific requirements that differ from General Acute-Care Hospitals. CONT’D
24
2016 California Building Standards Code Intervening Cycle Supplement
Section 1228 – New Section “Acute Psychiatric Hospitals” Proposed supplemental and amended language where specific to acute psychiatric hospitals for definitions and general construction. Basic services include: Psychiatric Rehabilitation Activities Service Space Psychiatric Nursing Service Space Pharmaceutical Service Space Dietetic Service Space Support Services (administrative space, etc.) Maintenance of existing sections CONT’D
25
2016 California Building Standards Code Intervening Cycle Supplement
Part 3 – California Electrical Code Maintenance of existing sections and coordination with new CBC and 1228 Part 4 – California Mechanical Code Adoption of model code for health facility ventilation requirements (ASHRAE 170) sections amended to include California specific amendments Maintenance of existing sections and coordination with new CBC CONT’D
26
2016 California Building Standards Code Intervening Cycle Supplement
Part 5 – California Plumbing Code (CPC) Maintenance and updates to CPC Table 4-2 Minimum Plumbing Facilities [OSHPD 1, 2, 3 and 4] Maintenance of existing sections CONT’D
27
Building Standards Update
HBSB Administrative Processes and Code Changes Committee Meeting November 18, 2016 10:00AM - 4:00PM Sacramento: Office of Statewide Health Planning and Development Los Angeles: Metropolitan Water District Headquarters
28
Building Standards Update
29
Building Standards Update
2018 Cycle Public Comment Period September 29 – December 12, 2016 The draft 2018 FGI Guidelines documents are available for public review and comment until December 12. The Health Guidelines Revision Committee counts on public review of the proposed changes, and we hope you will review the documents and submit your comments using the comment system for each book: 2018 FGI Guidelines for Design and Construction of Hospitals, 2018 FGI Guidelines for Design and Construction of Outpatient Facilities, and 2018 FGI Guidelines for Design and Construction of Residential Health, Care, and Support Facilities. To learn more about the drafts and the public comment period, please read this FGI press release. FGI and MADCAD.com have built a relationship in which MADCAD includes the FGI documents in their cloud-based reference library of codes and standards. For the 2018 Guidelines revision cycle, FGI has chosen to distribute our draft documents through the MADCAD website. On MADCAD’s platform, you will be able to review the documents online or download PDFs of the drafts to review offline.
30
Seismic Compliance Update California Hospital Association 11/7/2016
31
Structure Performance Categories
* Based on 2001 Hospital Survey Results based on hospital “self-report” and then “state-of-the-art” FEMA 178 standards from 1996 ** SPC-5 includes buildings currently under construction For SPC - "Not Assigned" is for non-building structures such as equipment yards, cooling towers etc. that are still under construction
32
Hospital Seismic Compliance to Date
228 11/3/16 1085 Buildings 82.6%
33
SPC History ~ 3 years
34
SPC -1 Buildings = 228 SPC-1 Buildings with Approved SB 90 Extensions
170 SPC-1 Buildings with only SB 1661/AB2557/SB81 Extensions 18 SPC-1 Buildings with only SB 306 Extensions 26 SPC-1 Buildings that currently have an extension 214 SPC-1 Buildings that do not have any extension beyond 2013* 14 Total 228 *No acute care services – some of these building have removal-of-acute-care-services projects – all have been sent a letter urging removing building from inventory.
35
SPC-1 Buildings with Extensions beyond 1/1/2013 = 214
SPC-1 Buildings with expired SB 90 Extensions 8 SPC-1 Buildings with expired SB 1661 Extensions 18 SPC-1 Buildings that have expired extensions 26 SPC-1 Buildings with expired extensions that have occupancy/construction final - 23 Remaining* 3 * 2 of 3 have active revisions in OSHPD/FDD for extending the SB90 extension.
36
SB90 Extensions (170 – 19 with CO/CF = 151)
37
SB 306 Extensions (26 Buildings)
County Facility Nbr Facility Name SB 306 Extension Status No of SPC-1 Buildings CO/CF ** 01 - Alameda 11288 Highland Hospital 1/1/2020 3 Yes 13 - Imperial 10190 El Centro Regional Medical Center 8 19 - Los Angeles 11976 LAC/Rancho Los Amigos National Rehabilitation Ctr 38 - San Francisco 12463 Priscilla Chan And Mark Zuckerberg San Francisco General Hospital And Trauma Center 2 56 - Ventura 11162 Ventura County Medical Center 5
38
Nonstructural Performance Categories
***Includes buildings under construction, tunnels and equipment yards For NPC - "Not Assigned" are for buildings and nonbuilding structures either under construction or where the nonstructural performance category has not been verified
39
NPC History ~ 3 years
40
All Reports Submitted by
2016 SB499 Report Timeline Building Inventory/SB499 Preparation Letter – 6/29/16 Building Inventory/SB499 Preparation Reminder Letter – 7/25/16 Building Inventory Revisions cutoff deadline – 7/29/16 Release of Online Report with passwords – 8/26/16 Online Report Reminder Letter – 9/26/16 Online Report Warning Letter – 10/17/16 Online Report submittal deadline – Tuesday, 11/01/16 OSHPD Website Final Report posting deadline 2/01/17 All Reports Submitted by COMPLETED November 1, 2016
41
Number of Reports submitted per SB 499, as of Nov. 7, 2016
Trend line
42
CDPH Presentation FDD presentation on to the CDPH DADM In-person meeting on 11/2/2016: Update on Seismic Compliance Presentation on available web resources from OSHPD
43
Data for Hospital Facilities
Located at: Search using any parameter
44
Example Hospital Links for license information
Links to electronic Services Portal
45
Data for Skilled Nursing Facilities
Located at: Search using any parameter
46
Example Skilled Nursing Facilities
Links to electronic Services Portal Links for license information
47
Report Center Located at http://report.oshpd.ca.gov/
For FDD, list of reports available
48
Report Center - Example
Additional reports on projects
49
Phone Applications
50
IPhone App
51
SB 499 Update California Hospital Association 11/08/2016
52
Preliminary 2016 SB 499 Hospital’s Reports Summary
53
Anticipation Completion Dates, SPC-1 Buildings
54
Method of Compliance for Facilities as reported from SB 499 reports to comply by Jan 1, 2017; Total = 18
55
Method of Compliance for Facilities as reported from SB 499 reports to comply between 2017 & 2018; Total = 17
56
Method of Compliance for Facilities as reported from SB 499 reports to comply between 2018 & 2019; Total = 9
57
Method of Compliance for Facilities as reported from SB 499 reports to comply between 2019 & 2020; Total = 50
58
Building Resolution from SB 499 Reports
59
Anticipated Compliance by, per Hospital Chain
60
Compliance Method, per Hospital Chain
61
Service Beds in SPC-1 Buildings
62
Service Beds in SPC-1 Buildings
63
Service Beds in SPC-1 Buildings
64
eServices Portal ePlanCheck Update
65
eSP Upgrades EPC Integration T&M Fee Invoice Guide Sheet Improvements
Task Assignment Simplification Closure Improvements Automatic Notifications Workflow Simplification - Review at Triage Improve Data Validation IOR Performance Tracking Bar Coding Article 10 Functional Program
66
OCM Committees Activities
Communications Collaborating with OSHPD Public Affairs to develop communications campaign, including logo, flyer, signature block, banner for OSHPD and FDD homepages, social media, and video vignettes for internal and external stakeholders. To-be Business Processes Finalized Intake, Office Triage, Office Review, Field Review, and Out-Processing Processes and socialized with key stakeholders.
67
OCM Committees Activities
Manager Talking Points Developed Talking Points presentation for OCM Education Session with Managers regarding the business reasons for change to ePC, the benefits of ePC to OSHPD and its clients, and next steps to communicate with staff. Frequently Asked Questions (FAQs) Developed 95 FAQs for OCM Education Session with Managers, including Client, Plan Review, Field Review, and Health-Related questions.
68
Detailed Process PROJECT PLAN ASSESS READINESS IMPLEMENT-MONITOR
Project Schedule Project Charter Project Management Plan ASSESS READINESS Define OCM Strategy Prepare OCM Team Develop Sponsorship Model Develop OCM Plan Develop Transition Plan IMPLEMENT-MONITOR Implement OCM Plans Implement Transition Plan Collect & Analyze Feedback Diagnose Gaps & Manage Resistance CLOSURE Knowledge Transfer Project Closeout ePC Organizational Change Management Management
69
ePlanCheck Training Southern California Field Staff – June 16
Southern California Plan Review Staff – June Northern California Plan Review Staff – June Northern California Field Staff – July 5 – 7
70
ePC First 4 Months OFFICE FIELD Central Region 13
Central Region – Field Coastal Region 62 Coastal Region – Field North LA Region 35 North LA Region – Field North Region 59 North Region – Field South LA Region 18 South LA Region – Field South Region 34 South Region – Field Rapid Review Unit Total (plus RRU) 221 (617) Total
71
ePlanCheck Issues Field staff advising clients application fee must be paid before electronic review will be started Plans in review submitted electronically for backcheck Plans uploaded electronically are then printed and presented to field for approval Clients are being advised plans must be submitted electronically for field review Clients are being advised electronic is not allowed for field review
72
eSP Next Steps Upgrade to Accela Civic Platform 8.0
Contract with Highlands/Truepoint to program triggers for new fees that go in to effect on Custom component for eTIO on all projects Custom component for eChecklist Create Document Type for eCPR Create Field Operations process for eRAD
73
Upcoming Programs/Processes
Auto Codes
74
Upcoming Programs/Processes
75
Upcoming Programs/Processes
eBAR CODES
76
Upcoming Programs/Processes
Auto Codes e
77
Upcoming Programs/Processes
78
Upcoming Programs/Processes
eRAD
79
OSHPD FDD Mobile Apps