1 Technical Procurement Plan
Nate Laverdure LCLS-II 2 K Cold Box FDR March 9, 2017

2 Technical requirements for
Outline Procurement sequence QA requirements Technical requirements for MLI installation Leak check and pressure test Cleaning Surface treatment and coating Rigging and lifting Site installation LCLS-II 2 K CBX FDR, Mar 9, 2017

3 Engineering Standards
SNO Topic CODES Edition 1 Pressure Vessels-Materials ASME Boiler & Pressure Vessel Code, Sec. II 2015 2 Pressure Vessels-NDE ASME Boiler & Pressure Vessel Code, Sec. V 3 Pressure Vessels-Welding & Brazing Qualifications ASME Boiler & Pressure Vessel Code, Sec. IX 4 Pressure Vessels ASME Boiler & Pressure Vessel Code, Sec. VIII-Div 1 & Div II 5 Relief Valves API 520-Part 1, Sizing , Selection , and Installation of Pressur e-Relieving Devices in Refineries, Part I – Sizing and Selection 2014 6 CGA S-1.3, “Pressure Relief Device Standards Part 3 – Stationary StorageTanks” 2008 Process Piping ASME B31.3 Process Piping 7 Seismic LCLSII-4.8-EN-0227, LCLS-II Engineering Note on Cryogenic Plant Seismic Design Criteria 8 Control Valves ISA-S75.01, Flow Equations for Sizing of Control Valves 2007 9 Flow-Meters ISO , Measurement of fluid flow by means of pressure differential devices 2003

4 Procurement sequence On site Offsite Initial
construction by Subcontractor Supply of some components by Jlab Final integration by Subcontractor Installation of the cold compressors by ALAT Supply of the cold compressor lower volutes by ALAT On site Offsite LCLS-II 2 K CBX FDR, Mar 9, 2017

5 Procurement sequence – technical specifications
LCLS-II 2 K CBX FDR, Mar 9, 2017

6 Procurement sequence – initial construction
Build-to-print fabrication of cold box vacuum shell and all internal piping Build-to-print fabrication of components and spools shipped loose Examination, testing, inspection, and delivery Components outside scope of initial construction by Subcontractor CC lower volutes (supplied by ALAT) Control valves, venturis, female bayonets (supplied by JLab) Witness points During leak and pressure checks After MLI installation and before vessel is closed LCLS-II 2 K CBX FDR, Mar 9, 2017

7 Procurement sequence – final integration
Delivery off-loading Installation and anchoring Installation of prefabricated ambient-temperature external piping and other attachments Final installation and testing of instrumentation Pre-commissioning quality testing including pressure and leak testing Witness points Throughout final integration LCLS-II 2 K CBX FDR, Mar 9, 2017

8 QA Spec Requirements and Expectations
General QA Requirements: Vendor to supply QA Program Plan/Manual and/or Project Specific QA Plan Includes QA elements critical to quality such as: Procurement Manufacturing, Inspection, and Test Plans Manufacturing Travelers Inspection/Test Hold and witness points Non-Conformance Controls Suspect/ Counterfeit Items Prevention Awareness Materials Traceability Spec calls for chemical and mechanical material certs for the documentation package. Material Handling Packaging, Storage and Shipping Documentation & Document Control LCLS-II 2 K CBX FDR, Mar 9, 2017

9 QA Spec Requirements and Expectations
General QA Requirements– Continued - Jlab SME’s and QA to perform site visit if Vendor is not currently on the Approved List for Code Products Supplier/Vendor Oversight by Jlab and SLAC personnel Performance oversight Witness points LCLS-II 2 K CBX FDR, Mar 9, 2017

10 QA Spec Requirements and Expectations
ASME and AWS Code Requirements Welding Section: Details are adequately covered for various weld types, fit up, machining, cleaning, and finishing Re-work expectations cited Inspection requirements articulated Eg. ASME Section IX Spec cites requirements for qualification and certifications of personnel doing the work (welding) or inspections. LCLS-II 2 K CBX FDR, Mar 9, 2017

11 MLI installation LCLS-II 2 K CBX FDR, Mar 9, 2017

12 Minimum leak check requirements
Volume Leak check requirement Helium Sensitive leak check with helium mass spectrometer leak detector, no allowable leaks greater than 10-8 atm*cc/s Guard vacuum Relief valve discharge collector Instrument air Bubble test, no observable leaks allowed during ASME B initial service leak test Cooling water supply and return No observable leaks allowed during ASME B initial service leak test Insulating vacuum Sensitive leak check with helium mass spectrometer leak detector, no allowable leaks greater than 10-6 atm*cc/s LCLS-II 2 K CBX FDR, Mar 9, 2017

13 Minimum pressure test requirements
Volume Pressure test requirement Helium ASME B pneumatic leak test Instrument air Piping spools per ASME B pneumatic leak test Final installation connections per ASME B initial service leak test Cooling water supply and return Piping spools per ASME B hydrostatic leak test LCLS-II 2 K CBX FDR, Mar 9, 2017

14 Cleaning requirements
Subcontractor shall provide in-process and final cleaning procedures All surfaces shall be thoroughly cleaned of all corrosion, scale, spatter, flux, lubricants and foreign materials Cleaning agents suitable for the materials of construction shall be used, and if necessary, shall be neutralized LCLS-II 2 K CBX FDR, Mar 9, 2017

15 Surface treatment requirements – carbon steel
Preparation requirement Coating requirement Carbon steel inside surface (exposed to insulating vacuum) Prepare surface per SSPC SP10 After successful leak check, inside surface shall be painted using a two-part epoxy per , or approved equal. Rustoleum #9392 white for a total dry film thickness (DFT) of 2 to 4 mils maximum. Do not prime. Carbon steel outside surface (exposed to atmospheric conditions) After successful leak check, a Three coat inorganic paint system comprising of Carboline Carbozinc 11HS (primer), Carboline 893 SG (intermediate), and Carbothane 134 HG S150 Safety Blue (finish). LCLS-II 2 K CBX FDR, Mar 9, 2017

16 Surface treatment requirements – stainless steel
Preparation requirement Coating requirement Stainless steel inside surface (exposed to process or insulating vacuum) Prepare surface per SSPC SP1 using solvents and cleaning solutions that will not induce stress corrosion cracking. Surface shall be passivated per ASTM A380. None. Stainless steel outside surface (exposed to atmospheric conditions) LCLS-II 2 K CBX FDR, Mar 9, 2017

17 Lifting and rigging plan
LCLS-II 2 K CBX FDR, Mar 9, 2017

18 Lifting and rigging plan
LCLS-II 2 K CBX FDR, Mar 9, 2017

19 Shipping plan Acceleration loads (appropriate for air ride trailer) have been incorporated into design of shipping supports LCLS-II 2 K CBX FDR, Mar 9, 2017

20 Installation sequence
Check level of floor and determine thickness of permanent spacer blocks. Lay out pattern onto floor. Drill for anchors and core for shear keys. Tape down protective measures over holes to keep out dust. LCLS-II 2 K CBX FDR, Mar 9, 2017

21 Installation sequence
Machine permanent steel spacer blocks that the base flange will rest on. The tallest block shall be 2" high, and the tops of all blocks shall be level when placed correctly on the pattern. Accept delivery. Unload from truck onto dollies, position over pattern, jack up to remove dollies, and jack down onto permanent spacer blocks. LCLS-II 2 K CBX FDR, Mar 9, 2017

22 Installation sequence
Install and weld shear keys. Pass anchors through the base flange, embed into concrete, and epoxy into place. After epoxy is cured, grout around base flange, making sure to fill ID of all shear keys with grout. After grout is cured, install double nuts to tension anchors. LCLS-II 2 K CBX FDR, Mar 9, 2017

23 Documentation Document No. Title Author Status
Technical Specification for Initial Construction of the LCLS-II 2K Cold Box N Laverdure In review Technical Specification for Final Integration of the LCLS-II 2K Cold Box Statement of Work for Rigging of the LCLS-II 2K Cold Box C Perry Engineering Note: 2K Cold Box Lifting Eyes MLI Installation Guidelines C Kaufmann LCLS-II 2 K CBX FDR, Mar 9, 2017

24 The scope of each procurement is well defined
Summary All elements related to Quality Assurance and Quality Control are adequately covered in the 2K Cold Box Spec Safe shipping and installation procedures have been adequately addressed in the design The scope of each procurement is well defined LCLS-II 2 K CBX FDR, Mar 9, 2017

25 Technical Procurement Plan
Nate Laverdure LCLS-II 2 K Cold Box FDR March 9, 2017