PALM BEACH COUNTY WATER UTILITIES DEPARTMENT
PRESENTATION FOR OPTIMIZATION AND IMPROVEMENTS – DESIGN/BUILD SERVICES Project Number: WUD November 4, 2014
2
Hillers Electrical Engineering
2 PROJECT TEAM Hillers Electrical Engineering
3
Cardinal/CGA Design Build
$32.5 Million Cardinal/CGA Design Build 3 TEAM HISTORY PBCWUD-WATER, WASTEWATER AND RECLAIMED WATER IMPROVEMENTS DESIGN BUILD SERVICES ($5.0 M) Royal Palm Beach Emergency Generator Storage at NROC Morikami Reclaimed Water Storage and Pump Facility WTP #3 Chemical Containment Area and Corrosion Inhibitor Storage Diesel Generator Catalytic Converters (RICE NESHAP Rule Compliance) WTP #9 SCADA System Tower Improvements WTP #3 Degasifier No.3 and Odor Scrubber Central Region Reclaimed Water Facility Improvements OTHER DESIGN BUILD SERVICES ($27.5 M) Pembroke Pines Phase II WTP/WWTP Improvements Miramar WRF Expansion Pembroke Pines WWTP High Efficiency Blower Upgrades
4
PALM BEACH COUNTY SBE PARTICIPATION
4 4 PALM BEACH COUNTY SBE PARTICIPATION Total Value of SBE Signed Sub-Contracts $1,304,393.93 26.07% of Cardinal/CGA Team’s Total Work
5
TYPICAL PROJECT APPROACH
5 TYPICAL PROJECT APPROACH PROJECT SCOPE PREPARATION OF PROPOSALS REVIEW AND SCOPE REFINEMENT DESIGN AND PROCUREMENT CONSTRUCTION
6
DESIGN PHASE CHECKS & BALANCES
6 QUALITY ASSURANCE & PERFORMANCE STANDARDS DESIGN PHASE CHECKS & BALANCES CGA INTERNAL QA/QC PROCESS FIELD VERIFICATION OF DIMENSIONS BY CCI CARDINAL CONSTRUCTABILITY INPUT SUBCONTRACTOR & VENDOR REVIEWS COST OPTIMIZATION DESIGN BY CGA & DESIGN TEAM
7
CONSTRUCTION PHASE CHECKS & BALANCES
7 QUALITY ASSURANCE & PERFORMANCE STANDARDS CONSTRUCTION PHASE CHECKS & BALANCES ENGINEERING CONSTRUCTION SERVICES INSPECTIONS CONSTRUCTION OVERSIGHT PROFESSIONAL TESTING SERVICES CLOSE KNIT TEAM APPROACH & SOLID DOCUMENTATION TO HANDLE UNFORESEEN FIELD CONDITIONS CONSTRUCTION BY CARDINAL
8
POTENTIAL PROJECT LIST
8 POTENTIAL PROJECT LIST Degasification / odor control WTP#9, WTP#11 Chemical Storage / Pumping Systems WTP(s) #2, #3, #8, #9, #11 & SRWRF Membrane softening treatment WTP#9 & WTP#11 Water storage / booster pumping morikami, Pahokee & south bay Electrical / emergency generator WTP#9, WTP#11, morikami, belle glade & Pahokee wwtp(s)
9
RELEVANT EXPERIENCE Degasification / odor control
9 RELEVANT EXPERIENCE Degasification / odor control PBC WTP#3 Degasifier #3 & Odor Control Degasifier & Odor Control Design Cleaning system addition Ground Water Rule Compliance - Clearwell Modifications PBC SRWRF Odor Abatement Improvements 2 Stage Odor Control System Pembroke Pines WWTP Odor Control Air Duct Improvements Cape Coral Everest WTF Odor Control System
10
RELEVANT EXPERIENCE Chemical Storage / Pump Systems
10 RELEVANT EXPERIENCE Chemical Storage / Pump Systems PBC SRWRF Odor Abatement Improvements Hypochlorite, Caustic & Citric Acid Tanks Chemical Metering Pumps Pembroke Pines Phase II WTP Improvements Hypochlorite Tanks Metering Pumps & Delivery Piping Sunrise Springtree WTP Sunrise Sawgrass WTP Improvements Hypochlorite, Sulfuric Acid & Fluoride Tanks Scale and Corrosion Inhibitor Storage & Mix Tanks
11
RELEVANT EXPERIENCE Membrane softening treatment
11 RELEVANT EXPERIENCE Membrane softening treatment Sawgrass WTP Improvements Project, RO Skid Rehabilitation Clewiston RO WTP, Low Pressure Reverse Osmosis WTP Port of the Islands Water Treatment Plant in Naples, FL Lee County Pinewoods WTP, Concentrate Line Replacement Tampa Bay Water Desalinization Plant/Corrective Work Town of Jupiter RO Expansion and RO Retrofit Lee County Utilities Expansion and Desalinization Pilot Marathon Reverse Osmosis WTP Stock Island Reverse Osmosis WTP City of Sarasota WRF RO Retrofit Design Build Town of Davie WTP/WRF City of Pembroke Pines Reverse Osmosis System Pilot Study
12
RELEVANT EXPERIENCE EMERGENCY GENERATORS / electrical PBC RICE-RULE
12 RELEVANT EXPERIENCE EMERGENCY GENERATORS / electrical PBC RICE-RULE City of Tamarac Generator Replacement TIER IV Sarasota County Pump Station No. 3 Improvements City of Mulberry Wastewater Treatment Facility Improvements Broward North Regional WWTP Generator Replacement Broward 440 Pump Station Pembroke Pines WTP Phase II
13
Hillers Electrical Engineering
13 PROJECT TEAM WHY OUR TEAM? WHAT DOESN’T CHANGE WITH OUR TEAM: PEOPLE & CONTINUITY Our team knows the PBC facilities and the people in them. PBC STANDARDS No learning curve for our team, either with each other or with the County. QUALITY Provide cost-effective, reliable, quality service to the customer Hillers Electrical Engineering
14
Hillers Electrical Engineering
14 PROJECT TEAM WHY OUR TEAM? WHAT’S NEW! WEST PALM BEACH OFFICE SHARED OFFICE FOR CONSTRUCTION & DESIGN NEW LOGO NEW TEAM MEMBERS Hillers Electrical Engineering
15
EXPERIENCE – SONG & ASSOCIATES
15 EXPERIENCE – SONG & ASSOCIATES Palm Beach County Water Utilities Experience Green Cay Nature Center Central Regional Operations + Maintenance Center Water Utilities Dept. Customer Service Center Southern Regional Operations + Maintenance Center Other Utilities Experience Abacoa Generator Building, Jupiter SWA Waste-to-Energy Facility Utilities Administration Building, Boynton Beach Master Pump Station, Lake Worth Nanofiltration Plant, Jupiter Reverse Osmosis Plant, Lake Worth West Water Treatment Plant, Boynton Beach Water Treatment Plant, West Palm Beach Emergency Operations Center, Jupiter
16
Hillers Electrical Engineering
16 PROJECT TEAM WHY OUR TEAM? SIMPLICITY Contracts Insurance Bonding/Form of Guarantee Transition Hillers Electrical Engineering
17
Project Number: WUD 14-071 November 4, 2014
THANK YOU! Project Number: WUD November 4, 2014
18
Project Number: WUD 14-071 November 4, 2014
QUESTIONS? Project Number: WUD November 4, 2014