Presentation is loading. Please wait.

Presentation is loading. Please wait.

LCR Sexual Health Strategy Project Board 6 October 2016

Similar presentations


Presentation on theme: "LCR Sexual Health Strategy Project Board 6 October 2016"— Presentation transcript:

1 LCR Sexual Health Strategy Project Board 6 October 2016
Project Status Report

2 Project Status – October 2016
Overall Status Status Change Plan G No change Benefits Budget Project Lifecycle Stage Initiate R A G Summary of Project Progress against plan Overall project status GREEN Leicestershire Strategy approved at Cabinet 19 April 2016 Rutland Strategy approved 21 June 2016 Key achievements and successes this period PID amendments made for sign off at Implementation Board 6 October 2016 First bi-annual Sexual Health Commissioners Meeting on 6 July 2016 Paper re: strategy to LLR GP workforce group 28 June 2016 Monthly CCG meetings set up until April NWL IUS/D federation pilot agreed C-Card implementation started 1st August 2016.

3 Project Milestone Progress
Key Milestone Baseline Target Date Status Comments and mitigation Proposed revised target date for approval SH Strategy Implementation Board & SH Commissioners meetings held & TOR agreed 6/7/16 G First meetings held, TOR amendments made. Future meeting dates set. Identify commissioning arrangements for menorrhagia 31/10/16 Paper drafted for City GP reference Group 6/10/16 and Joint Collaborative Commissioning Board end October 2016, outlining issues & options. Follow up actions/dates to be agreed Start Implementation of C-Card 1/7/16 Service commenced 1/7/16. Transition progressing well. Leicestershire: 10 sites transitioned, 12 new sites 90% former safer sex sites booked for training November 2016. Rutland: 9 sites transitioned. Pregnancy testing sites to be reviewed by end December 2016 to determine next steps. Map Psychosexual pathways 30/11/16 Pathways developed & presented to CCG subgroup Paper to be presented at LLR commissioners meeting December Follow up actions/dates to be agreed Support offer for teenage parents to be confirmed. (Leicestershire only) TBAG meetings & Baby Box commissioned to 31/3/17. Funding bids being progressed to continue work Longer term support offer needed as part of 0-19 work from April 2017.

4 Project Milestone Progress
Key Milestone Baseline Target Date Status Comments and mitigation Proposed revised target date for approval RSE evaluation complete 1/1/17 A Planning in progress, however possible delays due to linking with other lifestyles school support. SH communication group established 1/10/16 Workshop held to identify approach & priorities. Lead to take forward next steps. Awaiting recruitment of new post in Leics PH. (Programme Delivery Manager) 1/11/16 SH training Task & finish group 6/10/16 G Scoping of training work presented to Implementation Board Follow up actions/dates to be agreed Understand SH opportunity in community prevention & wellbeing service in Rutland. tbc Service specification for tender complete. C-card and signposting to Sexual health Services included. Bidders process is developmental. C-card training to be organised following contract awarded. Review ISHS clinics for at risk groups 31/10/16 Linked to demand & capacity work. Follow up meeting date to be organised. Delay due to staff absence.

5 Project Milestone Progress
Key Milestone Baseline Target Date Status Comments and mitigation Proposed revised target date for approval Review HIV self sampling & community testing protocols & pathways. 1/8/16 A Work in progress. Delay in appointing lead due to staffing review at ISHS. Lead now identified. Next meeting 18/10/16. 1/12/16 Completion of LARC competency audit for 15/16 1/11/16 G Audits collated & reviewed by SRH consultant. Responses to be communicated to practitioners & overview report to be produced Completion of SRH standard audit Report considered at SH Commissioning meeting July 2016 Follow up actions/dates to be agreed Planning Implementation of online self sampling service 1/9/16 Meeting planned for September rescheduled November 2016 due to key staff absence. Increase links between sexual violence prevention & SH services Presentation re: SH strategy to SV prevention delivery group. 10/16. Agreed actions to be followed up including a) meeting ISHS & SARC managers. b) linking CSE to RSE/healthy schools agenda and comms group.

6 Key activity, Milestones and Challenges over the next period
3 Month Forward Look Key activity, Milestones and Challenges over the next period To be finalised once PID approved, draft milestones include: Final approval of SH strategy implementation board and commissioning meeting ToR SH Communication group workshop proposals to be implemented. Establish strategic & operational groups Establish SH training task & finish group following agreement of scope. Support bidding process for continued offer for teenage parents. (Baby Box scheme) Completion of RSE evaluation Follow up outcomes of CCB meeting re: commissioning arrangements for menorrhagia Follow up actions relating to mapping psychosexual services across LLR Review ISHS clinics for at risk groups Review HIV self sampling and community testing protocols and pathways Produce summary of LARC audit responses & review audit format for 2017/18 submissions. Follow up actions re: SRH standard audit Planning implementation of online STI self sampling service Assess local LARC recertification applications Confirm milestones for ISHS re-procurement & gain LA agreement for LLR procurement model Follow up actions from SV delivery group meeting Contact midwifery/antenatal commissioner re: changes in chlamydia screening & embedding in mainstream service. Termination of Pregnancy paper to Commissioning Group Follow up commissioning options for cervical cytology in ISHS Progress federation pilot NWL re: LARC fitting

7 Key Decisions for Project Board
To confirm revisions to PID including appendices. To note actions and risks To agree actions/revised timescales & milestones as detailed above. To agree the revised sexual health dashboard indicators


Download ppt "LCR Sexual Health Strategy Project Board 6 October 2016"

Similar presentations


Ads by Google