1 Broomfield Development Plan Extraction Oil and Gas, Inc.
December 2016

2 Conceptual Grading of Lowell Well Site
Mission Statement Safely and efficiently produce natural resources in a manner that is compatible with the community, minimizes impact and is beneficial to Broomfield and Colorado citizens.

3 A Denver-Based Operator with a Community Focus
Extraction: Who We Are Denver-based Extraction Oil & Gas is a domestic energy company focusing on the exploration and production of oil and gas reserves in the Rocky Mountains. We are committed to, and have demonstrated, safe and responsible operations in the Greater Wattenberg Field of Colorado’s Denver-Julesburg Basin. Extraction Oil & Gas was created in December 2012 and assembled a strong technical team with years of experience in horizontal drilling and completion operations. Our growth strategy includes high-quality acreage acquisitions and forming strategic joint ventures with select operators in the Greater Wattenberg Field. Committed to our Community

4 Broomfield Development Plan Overview
Proposed Operation Timeline Drill, Complete and Produce 140 New Wells Development Plan – Minimizing Footprint Consolidate Locations, Install Pipelines, Eliminate Permanent Oil Tanks Best Management Practices Reduce or Eliminate Noise, Emissions, Traffic and Implement Exemplary Landscape Design Exceeding Regulations and Standards Exceed MOU Standards, Deliver Best-in-Class Project

5 Development Timeline Anticipated Drilling, Completion, and Turn Online Schedule 2017 Late Install Landscaping Early 2018 Drilling Program Begins 2018 Mid Completion Program Begins Early 2019 Complete Phase 1 Start Pause Late 2019 Final Drilling Program Begins Early 2020 Final Completion Program Begins Mid Complete Phase 2 Reclaim Work Space Finish

6 Consolidating Well Sites and Reclaiming Legacy Wells
Further From Homes & Closer to Northwest Parkway Before After Sheridan (40) United (40) Huron (20) Lowell (40) Description Before After Well Sites (MOU & USR) 12 4 Vertical Wells 36

7 Best Management Practices Exceeding Both Regulations and MOU: Committed to Becoming Operator of Choice with Communities Environmental Stewardship Reduce Emissions Eliminate Tanks Using State-of-the-Art Pipelines Facilities Designed to Capture 99.9% of all Emissions Install Vapor Recover Units Deploy Thermal Imaging Camera to Perform Advanced LDAR (Leak Detection & Repair) Program Groundwater Protection Multiple Layers of Cement and Steel to Ensure Groundwater Protection Water Well Sampling Program, Before and After Completion Process

8 Best Management Practices Exceeding Both Regulations and MOU: Committed to Becoming Operator of Choice with Communities Safety – People and Process Trained Operations Personnel Experienced and Professional Staff Comprehensive Response Plan Local Fire District Coordination Remote Facility Monitoring and Control Robust and automated Safety Protective System Design Preprogrammed Automatic Shutdowns Real-time Alerts Real-time Data Analysis and Response Rigorous Engineering Design Professionally Engineered Facility Designs Robust, Tested and Proven Design Modular Prefabricated Design Focus Eliminates Leaks, Drips, Emissions

9 Best Management Practices Exceeding Both Regulations and MOU: Committed to Becoming Operator of Choice with Communities Noise and Traffic Noise Reduction Electric-Powered Drilling Rig Quiet Completion Fleet Electric-Powered Facility Sound Walls, Landscaping & Berms Traffic Reduction using Pipelines During Completion Phase: Eliminate 4,800 trips During Production Phase: Reduce traffic by average of 79% per day Liberty Quite Fleet Comparison (Noise Level – dBa) Sound Walls - Liberty Quiet FleetTM  - Continuous Monitoring - * Assumes all pipeline right-of-ways obtained

10 Best Management Practices
Pipelines Eliminate Trucking No Significant Traffic Impacts Pipelines Eliminate Traffic and Trucks 100% of Freshwater Piped 99% of Oil Piped Traffic Best Management Practices Stage Trips to Avoid Peak Traffic Times (A.M. / P.M.) Monitor Local Events and Adjust Operations Traffic Impact Study No significant impact Less than 2% Increase in Most Segments; all Temporarily Traffic Safety Conclusions Proposed Increase in Traffic is Temporary, Nominal and Poses no Safety Concerns United Sheridan Huron Lowell * Assumes all pipeline right-of-ways obtained

11 Compliance with Regulations and Standards Colorado oil and gas regulations are the most stringent in the nation Extraction BMPs go Above and Beyond Regulations and Standards Planning and Permitting Community Engagement Wildlife and Cultural Assessments Air and Water Protection Well, Facility and Pipeline Design, Operations and Maintenance Reclamation Inspections and Monitoring Compliance Enforcement and Penalties

12 Conceal Site with Landscaping Before Development
Home Values Studies Range from Nominal to No Impact “Get In, Be Safe, Get Out” Colorado State University Studies Less than 1% Decrease During Drilling Possible No Impact once Development Ends New York Study Overall Regional Effect of Increasing Property Values Integra Realty Resources Study Effect dissipates at around 1,000 feet “In most cases, there was little or no relation between well sites and property values” Ballotpedia No impact on home values Conceal Site with Landscaping Before Development

13 Exemplary Landscape Design
Exceeding Both Regulations and the MOU: Committed to Becoming Operator of Choice with Communities Exemplary Landscape Design Conceal Locations & Operations Using Landscaping Sheridan Well Pad Lowell Well Pad Viewed from West Viewed from Intersection (East) Viewed from North Viewed from Anthem Ranch (North)

14 Addressing Community Concerns
Extraction is exceeding standards in the Broomfield Memorandum of Understanding (MOU), as well as implementing additional best practices to mitigate any inconveniences to our local community. Environmental Colorado has strictest air regulations in U.S. EPA Natural Gas Star Program Eliminate Tanks and Venting Install Oil, Gas and Water Pipelines Safety Eliminate tanks Eliminate-Reduce Traffic Use Pipelines 24-hour Monitoring Trained and Experienced Operators Fully-Automated and Engineered Safety Systems Noise Multi-Layered BMPS Electric Drill Rigs Liberty Quiet FleetTM Sound Walls Engineered and Designed Landscaping Electric Powered Equipment Traffic Traffic Safety Study No Trucks in Neighborhoods Avoid Peak Traffic during Peak Hours on Major Roads Use Canals, Temporary Hoses and Pumps to Deliver Fresh Water Home Values Install Landscaping before Development Moved Locations Away from Homes Install State-of-the-Art Oil, Gas and Water Pipelines Deploy Maximum BMPs to 100% of Locations

15 Summary Delivering 140 new wells within 3-4 years, adding economic value to Broomfield and Colorado Plugging and Reclaiming Legacy Vertical Wells – Leave No Trace Installing Exemplary Landscaping to Conceal Sites – Protecting Quality of Life Reducing and Eliminating Oil Tanks – Reducing Emissions Operating Safely – Commitment to Employees and Community Robust Design, Operations, and Maintenance – Operator of Choice Minimizing and Reducing Noise, Dust and Traffic – Minimizing Impacts Severance and Local Taxes Approximately $180,000,000 Mission Statement Safely and efficiently produce natural resources in a manner that is compatible with the community, minimizes impact and is beneficial to Broomfield and Colorado citizens.