MASTER PLAN UPDATE February 15, 2017.

Similar presentations


Presentation on theme: "MASTER PLAN UPDATE February 15, 2017."— Presentation transcript:

1 MASTER PLAN UPDATE February 15, 2017

2 C’mon What’s taking so long?
Votes needed to be verified by board of elections Ofcc (osfc) needed to review Elyria’s documentation submitted in spring 2016 Bond counsel and broker had to prepare for bond sales Bonds need to be sold in two groups - district rated by Moody Architect firm needs to be hired – interviews scheduled for February 17 Construction firm needs to be hired – interviews tentatively scheduled for March 27

3 Is the process the same for the sports complex?
Sports complex is a local funded initiative (LFI) – not part of co-funded issue Board hired architectural Vision Group (AVG) already for sports complex Both pre-bond and post-bond preliminary work in process on sports complex Major work re design and completion schedule nearly done - permits and approvals being sought and near completion phase 1 south portion – stadium and practice fields begin in march 2017 Phase 1 south portion ready for use august 2018 (phase 2 tentatively September 2019)

4

5 New schools site locations reminder and configurations
Ely site: k - 4 Abbe rd soccer field/spring valley site: pre-k complex Eastern heights site: k – 8 complex Hamilton site: k – 4 Township site: k – 8 complex

6 Preliminary timelines for schools to run concurrent with sports complex construction
Spring Valley abatement/demo – August through December 2017 Abbe Rd. site and ely site + program of requirements & schematics phase - March through july design phase – august 2017 through march Construction phase – April 2018 through August tentative opening date – start of school for the 2019 – 2020 school year The ely site will require approximately 4 months after school opens to allow for remaining demolition of ely school and grounds completion

7 Timelines continued Eastern heights site – grades 5-8 phase + por & schematic (both phases) – April through August design (both phases) – September 2018 through april Construction phase – May 2019 through august ready for opening sy Eastern heights site – grades k-4 phase + construction phase – june 2020 through summer of ready for opening sy Demolition of current eastern heights in phases as new school is completed

8 Timelines continued Hamilton school demolished fall/winter 2017
Hamilton site +por & schematic phase – December 2017 through march design phase – april 2018 through December construction phase – January 2019 through August ready for opening 2020 – 2021 sy

9 Timeline continued Township complex + por & schematic - august through December design phase – January 2019 through august construction – September 2019 through august Ready for opening – sy Board of education renovations at westwood 2021 upon near completion of township complex construction

10 Demolition of former schools late 2021 through mid summer 2022
Administration center Crestwood Franklin McKinley northwood Oakwood Prospect windsor