Presentation is loading. Please wait.

Presentation is loading. Please wait.

This is the final release: 13Jun09 Review: 15 June 2009 Brooke Gregory

Similar presentations


Presentation on theme: "This is the final release: 13Jun09 Review: 15 June 2009 Brooke Gregory"— Presentation transcript:

1 This is the final release: 13Jun09 Review: 15 June 2009 Brooke Gregory
Blanco Clean Room – CDR This is the final release: 13Jun09 Review: 15 June 2009 Brooke Gregory 1

2 Requirements Clean – Class 10,000 – 100? Enough room: ESD
NEWFIRM – 15’ x 20’ (down from 20’ x 20’ orig.) DECam – 12’ x 20’ Tom Diehl’s PPT ESD Materials - static dissipative Humidity >~40% 2

3 Main Features Area – 14.5 x 20.5 ft plus gowning area
Wall panels – static dissipative PVC Floor – Antistatic vinyl tile 50% FFU ceiling coverage Use Coudé as plenum Positive pressure in Coudé Air-locked pass-through Controlled humidity - >35% 3

4 An example Gemini’s Base Facility Cleanroom
Same area as what we are proposing 7 FFUs No gowning area Uses main room as plenum Performance ? 4

5 Gemini BF Cleanroom 5

6 Gemini Cleanroom – 12May09 8:30am-5:30pm 12May
average = 97 part./cu.ft. 6

7 Notes on activity 7

8 Location of the Cleanroom
8

9 Cleanroom elevation 9

10 Perspectives 10

11 Constructional details
Anti-seismic frame – steel roof and corner pillars Panels – dissipative PVC; aluminum frames; stainless stripping Seals Vents – low level slots with self-adjusting covers and magnetic sealing strips. Doors – 2 large instrument access Air-locked gowning area Air-locked pass-through for tools, etc. (Possible emergency crash exit gowning area?) Floor – static dissipative vinyl tile 11

12 Construction - movie 12

13 Panel mounting 13

14 Vents; covered with flexible plastic sheet
Panel details Vents; covered with flexible plastic sheet 14

15 Gowning room doors 15

16 Sliding doors for Big Instruments
16

17 FFUs and Lamps 17

18 Electrical Breaker box
110 v, 60 Hz outlets at each corner at floor level Ground connections 18

19 Cleanroom in Coudé Intentionally left blank. (It is always good that one’s intentions be less than 100% clear.) 19

20 Preparations to Coudé Remove all spectrograph pillars (done)
Prepare floor: floor will be ground to eliminate relief between main concrete segments (small area). Then grouted. Prepare ceiling (remove interfering lamps; tape holes) 20

21 Flooring Requirements: Solution chosen: ESD safe Clean(able)
Load-resistant Solution chosen: Staticworx: 3mm, solid vinyl tile over grouted concrete ESD characteristic: ANSI ESDS standard Load – 2500 lbs/sq.in. Steel Transition ramp Installed by AOSS in cleanroom structure 21

22 Fabrication and Assembly
Welded steel modules pre-fabbed by contractor: pillars and roof modules Modules brought to Coudé Panel vents pre-cut Cable trays incorporated in roof sections Cabling of roof sections done in Coudé on floor Pillars cemented to floor, joined to roof sections (bolted joints); Roof installed on pillars and beams between them FFUs, lamps, installed on roof and connected to cables Panels, fixed and on doors, installed 22

23 ESD Management Room construction
Panels – static dissipative PVC Floor – static dissipative vinyl tile, connected to ground Humidity – automatic control; implementation in Coudé modifications Station tooling (TBD) ionizers, table mats, grounding lines, monitors 23

24 Seismic Performance The roof of the clean room weighs about 1 ton. The structure needs to be stronger than the typical all-aluminum room. We did not have the engineering resource to investigate the solutions in-house. The solution was to contract out the analysis of the requirements and the architectural solution to Rodrigo Pino and Co. 24

25 Seismic analysis Performed by Ingenieria CRAM Ltda., Concepcion; report received. Proposed structure and then analyzed the structure, based on very conservative assumptions. Acceleration assumed: 0.4g Maximum stress on each member of the structure computed and shown to be below safe limits. 25

26 Operations Model Cleanroom normally off: vents will be sealed, doors locked, humidifier and all but one ventilator will be off. Coudé will be at positive pressure (this is new). A fan/filter inlet to the Coudé will be constantly acting. (Requires periodic filter maintenance). Procedure for cleanroom use, depending on nature of use: Un-lock necessary doors Un-block vents Turn on FFUs and lamps and dust monitors Possible wipe down of cleanroom Turn on humidifier and space heaters (if required) Wait until dust-counter reading has settled to a steady state and, depending on application, humidity has reached appropriate level 26

27 Tools and furniture A 3 ton gantry crane will be ordered; 1.5 ton hoist More tools are not proposed in this presentation. Rehearsal at Fermilab will lead to good input on tools. We propose to solicit suggestions from both teams. Our philosophy is to minimize the use of the clean room. We will also be providing lab space in the Coudé room or in Las Tacas. 27

28 Approximate Milestones
15 June - Review 16 June - Issue requisitions 17 June - Start floor preparations 17 June - Start clearing Coudé 1 July - Steel arrives, Benjamin starts fabrication 8 July - Move wall of Coudé 16 July - All materials arrive 17 August - Coudé ready for Cleanroom installation 17 August - Assembly begins 17 September - Cleanroom complete 28

29 Project Capital Costs Panels - $17k FFUs – $12.9k Crane (s) - $11k
Humidifier - $5.8k Steel structure (erected) - $5k (not current) Lamps - $2.8k Total: Does not include tools and instruments 29

30 END Some extra slides follow. 30

31 DECam in COUDE; perspective
31

32 Coude w. NEWFIRM and DECam
32

33 NEWFIRM, crane, Ron Probst and Ron George.
This is with a 20 x 15 ft room, but a superseded gowning area concept. 33


Download ppt "This is the final release: 13Jun09 Review: 15 June 2009 Brooke Gregory"

Similar presentations


Ads by Google