Hardware Commissioning Review BDI Equipment

Similar presentations


Presentation on theme: "Hardware Commissioning Review BDI Equipment"— Presentation transcript:

1 Hardware Commissioning Review BDI Equipment
R. Jung, on behalf of the BDI LHC Technical Board

2 Hardware Commissioning Review & BDI Equipment
BDI equipment is not part of the Hardware commissioning proper BDI may/will interfere with the Hardware Commissioning due to late monitor deliveries BDI equipment is mainly concerned by the commissioning with BEAM Different categories, with different impact: Large distributed systems over whole LHC Many specialised systems in small numbers around IP4, injection and dump extraction

3 BDI systems installed in LHC tunnel
Two big distributed systems: BPM & BLM Two Luminosity Stations: IP1 & IP5: US LARP: pb Special systems at Injections & Extractions/Dump lines Many special systems installed around IP4: BCTs: Fast and DC monitors Special Pick-ups for Tune, Chromaticity Transverse Profile Monitors: BTV, BWS, BSRT, BGIH/V Longitudinal Profile Monitors: WCM Our reference: Sylvain Weisz’s planning Our Aim: ready for the LHC start-up: July 2007

4 Large Distributed Systems
BPMs: Arcs: follow SSS planning: OK Others: Just In Time : BPM_A Q7R8 Warm BPMs: may be JIT for LSS8 end Electronics: small pb with delay lines order & deliv: 4 cards/Q may have to be installed later: access needed BLMs: 4000 ICs production will start in Prodvino: ~JIT; if not: install 2 ICs / Q and come back later: Access Last IC installation after interconnect closure only IC on passage to be installed after last transport ~340 SEMs for SSS, IR3 & 7, after IC production

5 Special & Small Quantity Systems [IP4]
BCTs Available for installation in June/July 2006 Special Pick-Ups JIT, including Schottky for the moment Transverse profile Monitors BTV in IP4 + elsewhere in ring & dump: JIT for IP8R Wire Scanners: JIT BSRT: JIT BGIH/V: fragile equipment to be installed as late as possible Longitudinal Profile monitors: RF WCM: OK Interference with start of RF tests [15/06/06] Little interference with RF commissioning: 11/06 – 5/07

6 Open questions: IP4 & Dump Lines
IP4: Access to UA43 & 47 (ex klystron galleries) during RF tests & commissioning: shielding Dump Lines Exact location & dimension of vacuum chambers for BCT and screens to be defined with AT/VAC and AB/BT to start ASAP the mechanical design of these BCTs and special large screen [ROI] BTVs. Planning