Download presentation
Presentation is loading. Please wait.
1
Cold Diode Project TE/MPE - TM
Introduction Aim of Project Diode stack inventory Procurement of new parts Complementary activities on diodes New diode Lab in Bd 272 Coming steps Conclusion Giorgio on behalf of M.Bednarek, S.Deleage, M.Favre, S.Pemberton, G.Seweryn, K.Stachon, Z.Toch,
2
Introduction The cold diode assembly is a protective component of the superconducting magnets: in case of a quench, the diode bypass the magnet: Like the other components of the circuit, the cold diode has to carry 12 kA during the current decay: 100 s. for RB and 30 s. for RQ Schematic of the RB circuit (main dipole)
3
Introduction: dipole and quadrupole stack
Main Quadrupole busbar Diode 1 Diode 2 Ansys model from S. Izquierdo Main Dipole busbar Diode Heat Sink Diode 1 Diode Heat Sink
4
Introduction: dipole diode stack
Rbus-bus (‘half moon’) R < 2 µΩ (300K) Upper diode busbar Diode box, Helium contents : 5 liter RHS-bus R < 2 µΩ (300K) Upper heat sink Voltage taps on the diode press-pack Rdiode-HS Lower heat sink
5
Aim of the Project The aim of the project is to have enough spare diode stacks, MB and MQ type, to cope magnet replacement during next LS2 and have some spares. Dipole diode stack (MDA or MDB): 30 pc + 10 optional Quadrupole diode stack (MQA or MQD): 10 pc Reminder: during LS1 we replaced 17 MDs (dipole type) and 4 MQs (quadrupole type) Restart R&D program on protection diode.
6
Diode stack inventory (actual status)
Spares diode stacks on stock Spares diode stacks under preparation MDA : 10 MDB: 13 MQAs: 1 MQBs: 5 MDA-0185 MDB- 0200 MQA 0441 (*) MQB 2003 MDA-0213 MDB-01179 MQB 2004 MDA-0673 MDB-2008 MQB 2006 MDA-2004 MDB-2010 MQB 2007 MDA-2013 MDB-2011 MQB 2008 MDA-2015 MDB-2017 MDA-2021 MDB-2018 MDA-2022 MDB-2019 MDA-2023 MDB-2020 MDA-2024 MDB-2025 MDB-2026 MDB-2027 MDB-2028 MDAs : 3 MDBs: 13 MQAs: 1 MQBs: 5 MDA-0302 MDB-0107 MQA 0401 (*) MQB 0528 (*) MDA-1281 MDB-0111 MQA 0280 MQB 2001 (*) MDA-1353 MDB-0131 MQA 0312 MQB 0203 MDB-0169 MQA 2101 MQB 0456 MDB-0333 MDB-1334 (*) Diode “grignotée” (*) Ready for cold testing in SM18 MQA 2101: assembled with new components from 2016
7
New parts procurement Main components of diode stack: more than 25 parts into a dipole stack: Lower diode bus bar Upper diode bus bar Top plate Bus bar insulator Upper heat sink Spring washers Tie rod Diode press-pack Lower heat sink Bottom plate Dipole stack insulator Quadrupole stack
8
New parts procurement The order DO-27528, went through in Feb.2016 with the main improvements: Dipole bus bar in one piece (no e-beam welding) Isolating parts (molded instead of machined) Prototypes received in May 2016 Quadrupole’s copper parts: (DSM) dimensional verification visual inspection dummy assembly Electrical contact resistance measurement OK for series production ! Series production received in September 2016 Dipole’s bus bars…OFE copper (TRIPLECUT) dimensional verification, visual inspection
9
New parts procurement Dipole’s copper parts…(HST)
dimensional verification visual inspection: heat sink circular shape… dummy assembly Electrical contact resistance measurement Dipole heat sink not OK for series production ! Exchange of samples, finally satisfactory on a dummy heat sink (Alu)! Production of new copper prototype (Nov.2016), before launching series production… Final series production received after CERN acceptance (Jan.2017)
10
New parts procurement Belleville washers Isolating pieces…
dimensional verification visual inspection dummy assembly Apply correction Improve varnishing Insulation test on dummy assembly OK for series production ! Series production received in September 2016 Belleville washers Large stock of used one : 700 pc. 8/stacks 87 stacks Mechanical lab testing of new and used washers Confirmation from manufacturer that they can be re-used No need to buy new Belleville washers !
11
Prototypes with 2016 parts…
Finally, we received all new parts to assemble the new diodes stacks (30MBs and 10 MQs)
12
Complementary activities …
Temporary diode lab in Bd 867 (Thanks to Betty!) Dedicated place with appropriate condition has been used ! Measuring equipment was transported to the new room. Restarted the test setup (replacement of faulty power resistor, revised cabling) Press-pack diode inventory and testing Started wafer inventory and re-testing at 300K and 77K (Liquid Nitrogen) Learning process for Zibi ! Available wafers : 191, to be sorted, classified! Wafer tested Wafer rejected Wafer for testing 207 16
13
Electrical test on diode press-pack
All available press-pack (207) have been electrically tested at 300K and 77K: Forward measurement: Ufwd (I) Pulse test at different current Forward characteristics Limit applied: Ufwd(12000A) < 1.05 [V] | 300 K Ufwd(12000A) < 1.65 [V] | 77 K
14
Electrical test on diode press-pack
Reverse measurement: Urev (I) Measure the leakage current under reverse voltage Reverse characteristics Limit applied: Urev (1mA) > 550 [V] | 300 K Urev (1mA) > 300 [V] | 77 K
15
Electrical test on diode press-pack
Krzysztof Stachon developed a new software, based on PXI crate, to automatize the testing of the diode: Replace the oscilloscope Improve the reliability of the measurement Database storage of test results To be finalized in the new diode lab
16
Geometrical measurement…
Wafer dimensional measurement by the metrology lab In order to verify the dimensional criterion of the wafers, a sample of 20 wafers was given to metrology lab: 6 um 62 um 4um
17
Contact surface…under pressure
Fujifilm improvement… Purchase a new scanner with dedicated software to quantify the contact surface and the pressure applied Prototype parts were measured: report available Quantitative analysis will be possible !
18
Contact surface…under pressure
All diode press-packs have been qualified with dummy diode (rectified cylinder): Measure the flatness of the diode press-pack under 42 kN ! Sort the diode press-pack according to contact surface !
19
New diode Lab in Bd 272 New diode lab is being prepared in building 272: The structure of the building was installed in August, but incomplete. Electricity in the building was accepted (HSE) (Sept.2016). Air conditioning and ventilation installation completed (Jan.2017). Cupboards were ordered and installed for storage. Dedicated workshop were ordered by Hera (long delay delivery) and are being finalized. Other tooling have been ordered: new press, “chèvre”, pallet truck, packing device, etc… We should have the new lab operational very soon (April) Improvement are planned from hardware and software point of view in the diode stack testing procedure.
20
New diode Lab in Bd 272
21
Coming steps… Test and validation of 2016 quadrupole stack (MPE +MSC)
Refurbishing of 3 old MQA quadrupole stacks DONE OK ! Assembly of 1 new MQA quadrupole stack (2101) DONE OK ! Testing of the new MQA2101 stack at 300K and 77K, in Bd 272 4 stacks ready for testing in SM18 for April 2017 Installation of new diode lab, including new equipment Furniture and workshop received. Additional equipment received: New press, “Chèvre”, Pallet trucks Setting up the test stand: ongoing Improving hardware and software for the new test stand Optimize the test stand Upgrade with new equipment Contacting Dynex to assure wafer production, know how for future press-pack orders…
22
Conclusion Compare to the initial road map, there is some delay mainly due to: OFE Copper purchasing procedure (Material request) Priority was given to IGBT switch (Mathieu, Samuel and Zibi) Training period of new test operator on diode press-pack Re-installation in new building Acceptance of dipole heat sink (machining process still to be approved) Delivery of new diode lab, including furniture, air conditioning, tooling Re-qualification of existing press-pack better than expected. Enough diode stack for magnet replacement (except MQAs) We should be able to have 30 new dipole stacks and 10 new quadrupole stack, fully qualified, by the end of 2017. No showstopper for LS2 purpose
23
Thank you !
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.