Technical Information on How the Planning Run Works: Contents
Steps in the MRP run Control parameters in the material master, in the BOM and in Customizing for MRP Net requirement calculation Lot-size calculation Scheduling BOM explosion and routing selection
2
MRP in SAP SEG 7420 on 13 Mar 2003
3
Technical Information on How the Planning Run Works: Unit Objective
At the conclusion of this unit, you will be able to: Explain the individual steps of the MRP run Explain and apply the most important parameters for the MRP run configuration and their combinations.
4
Course Overview
5
Steps in the Planning Run
6
Net Requirement Calculation
7
Net Requirements Calculation in MRP
8
Net Requirements Calculation - Process
9
How to Deal with Unforeseen Developments in Requirement Quantities?
Safety stock Safety stock partially available Dynamic safety stock Safety time
10
Safety Stock Reqmt Receipt
11
Safety Stock Partially Available
Reqmt Receipt
12
Range of Coverage Profile / Dynamic Safety Stock (1)
13
Range of Coverage Profile / Dynamic Safety Stock (2)
14
Range of Coverage Profile: Intervals
15
Safety Time Reqmt Receipt
16
Safety Time in Multi-Level Production
17
Lot-Size Calculation
18
Overview of Lot-Sizing Procedures
19
Static Lot-Sizing Procedures
20
Period Lot-Sizing Procedures
21
Lot Sizing According to Planning Calendar
22
Optimum Lot-Sizing Procedures
23
Long-Term Lot Size Reqmt Receipt
24
Planning Run Executed Regularly
Today Reqmt Receipt
25
Scheduling
26
Overview of the Procurement Types
Special procurement types
27
Backward Scheduling
28
Forward Scheduling for In-House Production
29
Scheduling in Production Planning
30
Order Data for Basic Scheduling
31
Lead Time Scheduling
32
Scheduling / In-House Production Time
33
Order Dates for Lead Time Scheduling
34
Changing Dependent Requirement Dates
35
BOM Explosion
36
BOM Explosion
37
BOM Selection
38
Selection of Alternative BOM
39
Order Quantity (Lot Size)
40
Explosion Data - Customizing
41
Explosion Date
42
Explosion Date using the Order Finish Date
43
Explosion Using the BOM Explosion Number
Gross Date
44
Production Versions
45
Defining the Change Status Using the Order Start Date
46
Defining Change Status Using the Order Finish Date
47
Defining Change Status Using BOM Explosion Numbers
Gross Date
48
Route Selection
49
Technical Information on How the Planning Run Works: Summary (1)
The steps of material requirement planning consists if net requirements calculation, determining the procurement type, scheduling and the BOM explosion. The net requirements calculation determines the available quantity for planning. The lot-sizing procedures and the procurements type are assigned in the material master.
50
Technical Information on How the Planning Run Works: Summary (2)
Basic scheduling or the lead time scheduling are two possible scheduling types in MRP. The BOM selection is influenced by the selection ID, the alternative selection indicator and the selection of the explosion date.