Interconnecting Wind & Solar Energy in Texas
Wind and Solar Expo San Angelo, Texas August 30, 2016 Hala Ballouz, B.Sc., M.Sc. TAMU , P.E. President , Electric Power Engineers, Inc. Board member TREIA Board Member AWE Boar Member Wind Coalition
2
Offer consulting services to
In business since 1968 Offer consulting services to Electric Cooperatives, Municipalities & Utilities Private Generators, in particular renewable energy generators Specialized in: Distribution & Transmission planning & design Energy Market Analysis Work Plans, Long Range Plans, Sectionalizing System Operation and Management Generation Grid Integration Studies 2
3
Overview Galileo Wind & Solar Grid Interconnection Basics
ERCOT Generation Interconnection Queue Wind/Solar Transmission Expansion in ERCOT NEXT -- Distributed Resources Future Strategy 3 3
4
Galileo
5
Galileo –The Earth or the Sun?
6
Vision
7
Vision
8
2016 Vision Recommendations Action
Incorporate Solar and Energy Storage in City and Electric Cooperatives Planning Standards Build Substations with land provisions and connections for 3-5 MW Solar / Energy Storage Sub Action-> Engineering Services
9
2016 Vision Planning Together Resource & Transmission Mapping
Collaboration In Resource Development Map the Resources Open Competition in Transmission Provide Ancillary Services OPTIMIZE
10
Wind & Solar
11
RESOURCE - Intensity Solar Wind Source: NREL
12
Solar Compliments Wind Production Profile
RESOURCE - profile Load Solar Thermal Solar Compliments Wind Production Profile Solar PV Wind Source: NREL
13
ERCOT Interconnection Queue
14
Table of Current Wind and Solar Interconnection Queue in ERCOT
Status Wind Solar Totals No. of MW Projects Capacity With Signed IA & Financial Security* 34 6,455 17 1,757 51 8,212 With Signed IA & without Financial Security* 14 3,952 5 532 19 4,484 Under Study 76 16,736 33 4,549 109 21,285 Total 124 27,143 55 6,838 179 33,981 Conventional Status Coal Gas Totals No. of MW Projects Capacity With Signed IA & Financial Security* -- 10 3,871 With Signed IA & without Financial Security* 1 240 14 10,276 15 10,516 Under Study 28 10,165 Total 52 24,312 53 24,552 Storage No. of MW Projects Capacity -- 1 324 3 320 4 644
15
ERCOT Queue – By Fuel Type
16
ERCOT Queue
17
ERCOT Queue
18
ERCOT Queue Legends Planned Wind, With Signed IA & SFS received by TSP
Planned Wind, With Signed IA & No SFS received by TSP Planned Wind, Under Study Planned Solar, With Signed IA & SFS received by TSP Planned Coal, With Signed IA & No SFS received by TSP Planned Solar, With Signed IA & No SFS received by TSP Planned Storage, With Signed IA & No SFS received by TSP Planned Solar, Under Study Planned Storage, Under Study Planned Gas, With Signed IA & SFS received by TSP Planned Gas, With Signed IA & No SFS received by TSP Planned Gas, Under Study
19
Grid Interconnection Basics
20
Grid Basics Interconnection to the Transmission/ Distribution Grid is the first step in the process necessary for an electricity generator to deliver/sell energy to load.
21
Resource Location vs. Process for Interconnection
The application process, information submittals, and timelines vary amongst the different ISOs and with the individual Utilities. Large generator interconnection process governed by RTOs/ISOs
22
ERCOT Process Linear Queue Process & Modest Study Fees
23
SPP Process Large deposits on initial application and studies .
PPA / turbine supply requirements . Long duration Aggregate studies .
24
Interconnection Process Constraints
Large Queue Transmission Congestion
25
Renewable Penetration
ERCOT
26
ERCOT Wind / Solar Transmission Projects in ERCOT
27
Far West Texas Load Growth
ERCOT Planning July 2015
28
Far West Texas 345 kV Grid Load+ Solar Expansion
AEP/ONCOR Proposal April 2016
29
Panhandle Wind – Lubbock Load Integration
30
Panhandle – Lubbock Load Integration
Second Circuit to be built -PUCT recommended moving forward with the second 345 kV circuit on the Alibates – AJ Swope – Windmill – Ogallala – Tule Canyon (AAWOT) line under the CREZ Order (PURA §39.904(g))at the September 24, 2015 Open Meeting. -Additional SVCs approved and on the way
31
ERCOT Long Term Studies
2031 Generation Additions and Retirements-- Current Trends (Presented at RPG , August, 16, 2016) Solar Additions: 20 GW by 2031 Unit Retirements: 13.5 GW by 2031
32
NEXT – Distributed Resources
33
Wind and Solar falling at and below $30/MWh
Cost of Renewables Wind and Solar falling at and below $30/MWh
34
Interconnection and Project Size
Distribution Interconnection < 1 MW: Small commercial or residential systems behind the meter applications to offset load. Typically no studies are required for projects less than 20 kW. Distribution Interconnection > 1 MW: Greater than 1 MW, less than 10 MW, and connected to a voltage less than 60 kV. Interconnection Study should be completed by Distribution Provider. Transmission Interconnection : Projects greater than 10 MW and connected to 60 kV or greater. Two study stages, the ERCOT Screening Study and the Transmission Provider Full Interconnection Study.
35
Innovation on Distribution
Anticipate and Prepare for Distributed Generation (DG) Growth Integrate DG in the Wholesale Market Smarter Grid Cross barriers to allow integration and information interchange between our distribution network and transmission network
36
Faster Deployment of Smaller Projects
TIMELINE ERCOT Interconnection Process Large Generation vs. Small Generator Large Generator : 10 MW or larger Goes through ERCOT Large Generator Interconnection Process Typical processing time ~ 1028 days Small Generator : less than 10 MW Bypasses ERCOT Large Generator Interconnection Process Process dictated by and completed directly with the Transmission Provider Average processing time ~ 90 days Faster Deployment of Smaller Projects
37
Specific DG-Related Statutes*
Develops provisions for: Owners/operators to sell electric power Use of T&D Facilities to transport electric power Utilities to recover costs of facilities for used for interconnection PURA – Distributed Natural Gas Generation Facilities Interconnection of DRG PUCT creation of rules and requirements for DRG Requirement for TDU to measure out-flow Ownership of Renewable Energy Credits Selling surplus electricity to REP PURA – Interconnection of Distributed Renewable Generation Customers entitled to have access to on-site distributed generation PURA – Customer Safeguards Allowing Independent School Districts to sell surplus energy form solar generation Requiring utilities to provide metering to allow sell of energy PURA – Credit for Surplus Solar Generation by Public Schools *other statutes may be applicable to DG based on operation in the ERCOT wholesale market Source: ERCOT
38
DG DG interconnection application requirements vary by DSP for DG projects. A universal interconnection agreement is already available from PUC Texas and it is being used by DSPs. DG projects greater than 1 MW must register with ERCOT to be able to participate in the Wholesale Market. DG settlement will be paid at the appropriate Load Zone Price. No telemetry requirement for DG projects.
39
ERCOT Helpful Links More information on ERCOT process for generation interconnection: More information on Distributed Generation Resource Can be found under following link: Texas PUC – Electric Substantive Rules – Chapter 25 – Technical Requirements for Interconnection and Parallel Operation of On-Site Distributed Generation can be found under following link: Texas PUC – Electric Substantive Rules – Chapter 25 – Interconnection of On-Site Distributed Generation (DG) can be found following link:
40
2016 Vision Planning Together Resource & Transmission Mapping
Collaboration In Resource Development Map the Resources Open Competition in Transmission Provide Ancillary Services OPTIMIZE
41
Recommend pro-active solutions to West Coal Retirement and Solar West Expansion
2031 Generation Additions and Retirements-- Current Trends (Presented at RPG , August, 16, 2016) Solar Additions: 20 GW by 2031 Unit Retirements: 13.5 GW by 2031
42
2016 Vision Recommendations Action
Incorporate Solar and Energy Storage in City and Electric Cooperatives Planning Standards Build Substations with land provisions and connections for 3-5 MW Solar / Energy Storage Sub Action-> Engineering Services
43
4343 Q&As Please contact Hala Ballouz, P.E. with any questions you may have. 43