Download presentation
2
Customer Pakistan LNG Terminals Limited (“PLTL”)
PROCUREMENT PROCESS Customer Pakistan LNG Terminals Limited (“PLTL”) Rules Public Procurement Rules, 2004 Consultant U.K.-based Galway Group Bids Deadline Feb. 26, 2016 Operator Pakistan GasPort Tariff $ per mmbtu Capacity 600mmcfd Award June 24, 2016 Contract* July 1, 2016 First Gas June 30, 2017 *The 15-year LNG Operations and Services Agreement (the “Contract”) was signed after approvals from, among others, the Federal Cabinet’s Economic Coordination Committee and the Ministry of Law and Justice
3
PROJECT PARTIES Operator
PGP Consortium Limited (“PGPC”), which is wholly owned by Pakistan GasPort Limited (“PGPL”) EPC Consortium (For PGPC and FOTCO) Xinjiang Petroleum Engineering Co., Ltd. (“XPE”) CCCC Third Harbor Engineering Co., Ltd. CCCC Third Harbor Consultants Co., Ltd. Project Associate Fauji Oil Terminal and Distribution Co., Ltd. (“FOTCO”) FSRU Provider BW Gas Limited (“BW”) Owner’s Engineer COWI Gulf A/S (“COWI”) Financial Advisor Arif Habib Limited Insurance Advisor Marsh Limited
4
LOCATION Chara Chan Waddio Creek, Mazhar Point, Port Qasim
1.3km across navigation channel from FOTCO jetty, clear of existing navigation channel Close to designated Delivery Point Compliant with safety standards Chara Chan Waddio Creek, Mazhar Point, Port Qasim
5
SCOPE OF WORK FSRU Provider Provision of new-build FSRU on lease Operations and maintenance of FSRU 750mmcfd regasification capacity (six x 125mmcfd) PLTL: 600mmcfd (average over 350 days) Excess: mmcfd over 175 days 170,000m3 LNG storage 96-percent annual availability No dry docking for 15-year duration of Contract Owner’s Engineer Complete supervision of all technical design aspects Certification of all completed works
6
Dredging of turning basin Construction of 1.3-km subsea pipeline
SCOPE OF WORK EPC Consortium Long-lead items ordered, mechanical completion on May 31, 2017 For PGPC For FOTCO Dredging of turning basin Construction of 1.3-km subsea pipeline Dredging of approach channel Construction of 4-km trestle-mounted pipeline Construction of jetty Construction of 7-km onshore/underground pipeline Construction of jetty topside Installation of gas measurement system
7
PROGRESS / contracts PGPC has signed/agreed the following contracts with various parties for the timely implementation of the Project: LNG Operations and Services Agreement with PLTL, July 1, 2016 Agreement for Engineering, Procurement, Supply, Dredging and Construction with the EPC Consortium, July 26, 2016 FSRU Lease Agreement with BW, Aug. 20, 2016 FSRU Operation Services Agreement with BW, Aug. 20, 2016 Schedules to the EPC Agreement, Aug. 30, 2016 Facility User Services Agreement with FOTCO, Sept. 9, 2016 Agreement for Purchase of Loading Arms with BW, Sept. 22, 2016 Supplemental Implementation Agreement (“SIA”) agreed with, and approved by the board of, Port Qasim Authority (“PQA”) to amend the Implementation Agreement of April 2007
8
PROGRESS / studies Layout confirmation
Survey/route selection for subsea and online pipelines HAZID, QRA assessments by Lloyd’s Geotechnical, bathymetric, route surveys of site and channel Fast-time navigation simulation for passage of LNG vessels Environmental and Social Impact Assessment from SEPA Environment protection regime, social action plan per WB guidelines Civil and electromechanical design basis, marine civil specifications Channel layout and passing-bay assessment ADCP current measurement Sedimentation study Design verification Pipeline FEED Full bridge simulation studies conducted by Siport21 Study to measure current velocities Hydrodynamic modeling for silting/sedimentation behavior after dredging
9
PROGRESS / payments PGPC has taken significant exposure, and provided requisite advances/deposits/guarantees, including but not limited to: Operator Guarantee to PLTL $39 million Performance Guarantee to PLTL $11 million Security Deposit to BW $2.5 million Advance for Loading Arms $120,000 FOTCO Mobilization Deposit $4.716 million PQA Performance Guarantee $1 million
10
PROGRESS / reviews Process of review and coordination among all stakeholders— PGPC, FOTCO, XPE, CCCC THEC, CCCC THCC, BW, COWI, PQA, PLTL, financial institutions—is taking place regularly, in Pakistan and abroad. This continued coordination is vital to harmonize all aspects of the Project and achieve timely completion Recent review meetings Project Kickoff Meetings, Dubai, Aug Design Workshops, Dubai, Shanghai, Karamay, Sept. 29-Oct. 3 HAZID/HAZOP Workshop, Dubai, Oct
12
FINANCING STRUCTURE Equity (Subscribed) Rs. 4,293 million
Preference Shares Rs. 1,500 million Loan/Sukuk Rs. 8,517 million Rs. 14,310 million Strong JCR-VIS Credit Ratings: “A-/A2” for PGPC (highest for Greenfield Projects), “BBB” for Preference Shares issue, “A” for Sukuk, “Stable” outlook State Bank of Pakistan approval for remittance of Mobilization Advance and establishment of Letter of Credit in favor or XPE
13
Pakistan GasPort Consortium Limited
For more information: Mr. Syed Saquib Ali Vice President, Investment Banking, Arif Habib Limited Mr. Muhammad Kashif Manager Finance, Pakistan GasPort Consortium Limited
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.