Technical overview PM2 Stockholm 14-15 June 2017
2
WP1: ended in M9 MS1-Best performing microalgal/bacteria consortium identified Results: Tested WW: tannery, fish ponds, cheese whey Tannery: D. salina on 10% (sterilised WW - not applicable) reality salinity will be too low, mixed consortium of self selected algae expected Algen salinity tests for existing & marine & saltpan species Fishpond: Spirulina and Chlorella low nutrients in WW; how will be solved? Whey WW (original WW from Silvio or not?): Tetraselmis suecica on 5% WW, WW inhibitory for Spirulina and Chlorella Study of microbial community: dominant algal and bacterial species and their associations; primers designed for quantification of algal-bacterial ratio in demos-done Pending tasks: MS1 to be submitted (reviewed by CO and TM)
3
WP2: Valorisation of Sludge
M2 - Design and dimensioning of process for Primary Treatment and pre-treatment (i.e. DAF) (BBA M12): done for all demo sites M3 – Anaerobic Digestion processes and CO2 recovery optimised at lab scale (NOVA M18): in progress! Pending: supply of equipment to demo sites – Who, Where, What – WG discussion! AD trials for methanogenic phase – results needed for further work and construction salinity levels (needed for AD reactors construction, DCU needs it) optimisation of CO2 recovery? List of equipment for demos: in deliverable D2.1– communication with partners – is there anything unclear about who delivers what & who pays? Containers equipment at KOTO (BBA, KOTO; ALGEN) - what goes in to the containers? WG dissussion
4
WP3: Valoristaion of HRAP effluents
M4 – Selection of pre-treatment strategy; Relevance of ED on each studied sample assessed; New pump and ERD tested in lab environment (iBET M16) Pending / deviations: ED tested on WW from Arava and KOTO at lab scale, will not be implemented (no budget, not feasible) - report to PO? (EXT, BBA no budget for ED EXT does ED lab scale tests: delivery of WW (done? Costs!) few m3 of pretreated WW delivered to who/when?? WG discussion! Pump tests needed on demo sites: transfer of PM / hours from WP3 to WP6? Delay in supply of pumping station – BBA BBA has no budget for pretreatment and RO (who delivers and pays for demos?) + pumps – does DCU supply? WG discussion! Only RO at ARV and kOTO (really both?)
5
WP4: Valorisation of algae biomass
Objectives: optimisation of harvesting, biomass refinements, develope and demonstrate animal feed, coatings and adhesives, 3D printing Results / pending: optimisation of harvesting biomass refinements animal feed trials: need to adapt to situation Produmix new numbers and proposed changes (no need for PO approval probably): testing for fish meal and antimicrobial activity (instead of soya replacement and omega 3); partners need to send algae (200g dry sample); NEW CALCULATIONS-is this acceptable/feasible for partners to provide? Fish meal: 76,5kg needed, AB: 64,6 kg algae needed (141 kg total, previously: 533 kg) Archimede sent 150kg of algae for tests; Coatings: what has been done? 3D printing, progress?
6
WP4: Valorisation of algae biomass
Pending: D4.1. (M14) - next month! Systems design for harvesting and refinement, algae characterisation
7
WP5: HRAP Integration and Process Optimisation
Pending: D5.1 deliverable Sensor system construction and integration in existent system (OXI-BBA-DCU-ARV-KOTO-ARCH)-WG discussion! OXI: Chemitec doing tests for P and Chl (Sample from ARCH in process, KOTOs will be delivered after PM) Decision about how many modules, which sensors, range (budget!) Proposed: pH, cond, NH4, NO3, PAR, Chl; one per pond// offline: P in supernatant after harvesting (tests running) OXI needs info on Chl levels Sensors for WP3 (RO-DCU), WP2 (AD-BBA), anyone else?: WG discussion!
8
Working Groups discussions: topics to cover
WP2 Supply of equipment to demo sites – Who, Where, What Containers equipment at KOTO (BBA, KOTO; ALGEN) - what goes in to the containers? WP3 BBA has no budget for pretreatment and RO (who delivers and pays for demos?) + pumps – does DCU supply? EXT does ED lab scale tests: delivery of WW (samples sent? Costs!) few m3 of pretreated WW delivered to who/when?? WP5 Sensor system construction and integration into existing system (OXI-BBA-DCU-ARV-KOTO-ARCH Sensors for WP3 (RO-DCU), WP2 (AD-BBA), anyone else?
9
Deviations Species ED only lab scale Salinity in Italian demo
Biomass use Size of AD DoW partA & partB
10
Deliverable planning Table of contents Assignment of work Main story
Coverage of DoW Structure Spelling Language Dates, avoid unnecessary delays Next: D4.1 Systems design for harvesting and refinement, algae characterisation (IBET M14 Jul-2017 ) D2.2 Optimisation of anaerobic processes and CO2 recovery solution (NOVA M18 Nov-2017 ) D3.2 Optimisation of final systems ready for demonstration trials (IBET M18 Nov-2017) WP leader Deliverable editor