Download presentation
Presentation is loading. Please wait.
Published byGavin Freeman Modified over 7 years ago
1
PEP-II Status John Seeman SLAC Particle and Particle-Astrophysics
DOE SLAC HEP Program Review June 6, 2006
2
Topics Overview Present status Long range schedule
Upcoming fall down activities Conclusions
3
The PEP-II Team Accelerator Systems Division SLAC Support Groups BaBar
LBNL ILC Machine Advisory Committee 1x1034
4
Internal Citizen Committees and Subject Matter Experts
Safety Overview Radiation Safety Non-Ionizing Radiation Safety Hazardous Experimental Equipment ALARA Electrical Safety Earthquake Safety Fire Protection Safety Hoisting and Rigging Safety Environmental Safety Radiation Safety Officer Laser Safety Officer Electrical Safety Officer Fire Marshal Crane Inspector ESH Environmental Protection Department ESH OSHA Experts ESH Industrial Hygienists Emergency Management Coordinator
5
Recent and Near-term External PEP-II Reviews
BaBar International Finance Committee January 20, 2006 BaBar Collaboration meeting February 25, 2006 DOE P5 Review April 21, 2006 DOE PEP-II Operations Review April 26, 2006 DOE HEP Program Review June 6, 2006 BaBar Collaboration meeting June 24, 2006 BaBar International Finance Committee June 26, 2006 PEP-II Machine Advisory Committee 1) Jan 4-6, 1995 2) August 24-25, 1995 3) April 11-13, 1996 4) January 6-8, 1997 5) November 10-13, 1997 6) December 14-16, 1998 7) October 9-11, 2003 8) April 15-17, 2004 9) December 13-15, 2004 10) January 16-18, 2006 11) Late fall 2006
6
PEP-II e+e- Collider Overview
BaBar Detector
7
PEP-II RF Cavities PEP-II LER RF
8
PEP-II Interaction Region Components near BaBar
LER HER BaBar Collision point
9
How the beams enter and exit the PEP-II Interaction Region
M. Sullivan
10
B-Factory Overall Parameters
Parameter PEP-II (LER/HER) Circumference (m) Beam energy (GeV) 3.1/9.0 Number of bunches Beam currents (A) (e+/e-) 2.9/1.76 Horizontal emittance (nm) 30/45 by* (mm) 9/11 Bunch length (mm) 11 xy /0.045 IP beam sizes (microns) (x/y) 120/4 Luminosity (x 1033/cm2/s) 10.9
11
PEP-II Long Term Run Schedule
Run 5b: November 14, 2005-August 21, 2006 Down: September-December 2006 Safety checks Major upgrades for PEP-II Major upgrades for BaBar LCLS installation Run 6: January-August (or September?) 2007 Down: September-November 2007 Run 7: December 2007-September 2008.
12
Luminosity: Run 5 April 2005 – June 2006
1.09 x 1034 Vacuum issues found fixed Luminosity
13
PEP-II Luminosity versus Time
> 1 x 1034 LER current Luminosity HER current
14
1.088 x 1034
15
M. Sullivan
16
Prediction March 2006 Actual
18
PEP-II Luminosity Integration
19
PEP-II Machine Advisory Committee
Meeting: January 18-20, 2006 Members: D. Rice (chair), J. Corlett, K. Harkay, S. Henderson, I. Koop, J. Marriner, K. Oide, D. Rice, D. Rubin, L. Bertolini, F. Pedersen, P. Raimondi, F. Zimmermann, Report available. Words from the report: Impressive progress in all areas since the last the review a year before. Congratulates achievement of 1034 luminosity (3.3 x design). Trickle charge injection is very effective. Accelerator plan is sound for optimizing the collider productivity though FY2008 Vacuum burst studies are being intensely investigated. [Committee made several suggests what to look for.] Suggest re-examine increasing the specific luminosity.
20
Highlights of the PEP-II DOE Operation Review April 2006
PEP-II has a solid past track record on achieving milestones. Adequate man power is in place but must be watched. Adequate management systems in place for communicating priorities, tracking progress, and resolving problems. The integrated luminosity trends in FY2006 should be (just) sufficient to reach the FY2006 DOE milestones. (Still true.) Encourages the emphasis on accelerator lattice modeling for improving the peak luminosity, i.e. specific luminosity. (Recent luminosity records made with smaller beam currents.) Increasing luminosity with higher beam currents and shorter bunches is a concern for vacuum heating. (More studies are underway. Adding more HOM absorbers in the IR and BPMs.) Concerned about the short length of the fall down. (Added a work week to the down and a “float” week.) Need to maintain reliability. (New look at all spare part inventories.) Develop scenarios for minimum and maximum integrated luminosity predictions though September ( In progress.) Provide a SLAC-wide staffing plan through FY2009. ( In progress.)
21
Two Vacuum Issues in December 2005 – March 2006
Two major vacuum problems developed in the month of December limiting the peak luminosity to about ~0.5 x 1034/cm2/s: Gap ring (RF seal) problem near LER RF cavity caused e+ beam instability Higher Order Mode absorbing bellows caused vacuum bursts in IR The first problem was quickly identified (~ 2 weeks) and solved in late January. The second problem was thoroughly investigated, replacement parts manufactured, and repaired in late March with elapsed time of about three months.
22
Location of the First Vacuum Problem
Vacuum spike area RF seal installation procedure problem
23
Second Vacuum Event: BaBar Background Trip
Spikes
25
IP Vacuum Issue Resources
Help from many groups: PEP-II, BaBar, Material Science Group, Klystron Dept., High Power RF Group, Vacuum Dept., Pulsed Kicker Group, and LBNL. Many studies done: Beam current thresholds Beam instability identification External leak checks Transient leak checks during spikes Gas pressure profiles Gas pressure flow rates Gas injections (puffs) (He, N2, Air) (various locations) Transient gas analysis during spikes NEG pump heating to make H2 gas Background timing with BaBar Borescoped 100 m of vacuum chamber (several times) Replaced RF seals and four vacuum chambers SiC-AlN HOM tile lab tests and thermal calculations This vacuum problem was the most subtle and hard to diagnose problem PEP-II has had. However, we solved it in a timely way over two months with a strong team. In the end as will be shown later, the chamber at fault was anticipated to be a long term problem and was scheduled to be replaced in Fall 2006 (AIP project). (The problem came 6 months too early!)
26
LER Forward Q4 Location
28
“Discharge” on Absorbing Tile
SiC/AlN HOM Tile Arc site Cu heat sink RF seal fingers
29
New RF seal to correct problem: New seat on Cu base not tile
N. Kurita
30
New Q1/Q2 bellows unit for Fall 2006
Absorbing tiles behind fingers N. Kurita A. Novokhatski S. Weathersby
31
Future PEP-II Overall Parameters and Goals
Units Design Present best 2007 goal I+ mA 2140 2940 4000 I- 750 1776 2200 Number bunches 1658 1732 by* mm 15-20 10 8-8.5 Bunch length 15 11-12 8.5-9 xy 0.03 Luminosity x1033 3 10.9 20 Int lumi / day pb-1 130 760 1300 3.6 times design 5.8 times design
32
Goal: A factor of two in PEP-II luminosity
PEP-II Upgrades Goal: A factor of two in PEP-II luminosity (1.1 2 x1034/cm2/s) will come from: Increasing each beam current by 40%. Lowering by* from 11 to 8.5 mm giving 20%. Increasing the beam-beam parameters by 10%. Keeping detector backgrounds at the predicted levels. Maintaining (and improving) accelerator reliability.
33
Integrated Luminosity Projection March 1, 2006
2007 down 2006 down Now
34
Accelerator Improvement Projects on track for Fall 2006
X-Y BPM upgrades New HER Q5 vacuum chambers New HER/LER Q2 chambers HER-10 RF station HER-11 RF station HER power supply upgrade for higher tunes 2006 New HER Q4 vacuum chambers 2006 New IR2 Q2 bellows LER IR HOM absorber HER IR HOM absorber LER BPM monitor upgrade LER new high power bellows LER NEG vacuum chamber upgrade 2006 New Longitudinal feedback processor 2006 Cost of these AIP projects is about 7 M$ spread over FY2006 and FY2007. PEP-II AIP expenditures from averaged about 5 M$ each year.
35
B-Factory RF Klystrons (1.2 MW) under construction
C. Pearson
36
RF Cavity Production Finished cavity ACCEL Germany Ports to be welded
Cavity bowls welded together. Cavities due at SLAC in one month. H. Schwarz, A. Hill
37
Example: HER QF5R Chamber (Fall 2006)
Specifications Construction: Now on vacuum bake. R. Pope Design
38
New LER Beam Position Monitors
New button design HOM absorber Button puller design N. Reeck M. Kosovski N. Kurita
39
PEP-II Accelerator Technology for Future Accelerators
High beam currents World record e+ current (2.95 A) World record e- current (1.78 A) High power vacuum chamber design Large number of bunches World record number of colliding bunches (1732) Very fast and strong bunch-by-bunch feedbacks (4 nsec) Electron Cloud Instability (ECI) cures (solenoids, antechambers) High power RF systems >1.2 MW CW klystrons 476 MHz High power Cu cavities (600 kW) Complex interaction region design with two rings PEP-II provides continued strong input into new accelerator designs: ILC damping rings, low emittance light sources (PETRA-3), Super-B Factories, eRHIC, LHC ECI, BEPC-II, …
40
PEP-II Conclusions PEP-II achieved a new luminosity level (1x1034) in October 2005 and set several integrated luminosity records. Run 5b started well but two serious vacuum problems occurred keeping the luminosity peak to about half the former peak. Both vacuum problems have been identified with the help of many people and experiments and have been solved in a timely way. Over the past two months, the luminosity has risen steadily to new PEP-II records of 1.09 x1034 with several 760 pb-1 days. Issues from the MAC review and DOE Operations Review are being addressed. Planned upgrades towards ~21034 are on track. Run plans are in place with a target of ~1 ab-1 in 2008. We strongly believe that the combined performance of PEP-II and BaBar will remain competitive through 2008.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.