Primary Reformer (F-101) Tee Collector and Transfer Line Problems
Muhammad Waqas Younas (Mgt. Associate) Projects-TSD
2
OBJECTIVE The objective of my presentation is to discuss the replacement plan and problems associated with; Primary Reformer (F-101) outlet Tee Collectors b)Transfer Line (F-101 to C-102)
3
CONTENTS Problems observed Brief history Replacement Project
Introduction Brief history Problems observed Way Forward Replacement Project Recommendations
4
F-101 Piping Inlet Pigtails Top Flanges C-102 Inlet Miter Elbow
Riser Tee Tee Collector Transfer Line Bottom Flanges Catalyst Tubes Outlet manifold
5
F-101 Transfer Line Plan View
North West Header North East Header South West Header South East Header C-102 Inlet
6
TEE COLLECTOR PROBLEMS
7
Background At LCA : One Manifold each chamber, connected by a tube Material A-297 Two manifolds each chamber Material : Incoloy 800 Grade 2 (800H) Design life 100,000 Operating Hrs Cracks observed in both cells outlet manifold Cracks repaired by Welding as per FW procedure At PQA : Hair line cracks observed in Bull head tee weld joints At FFBL : Procurement of Bull Head Tees and Manifold initiated FW regret to provide Bull Head Tess of Incoloy 800 H Bull Head Tees and manifolds replaced with upgraded material New material 2032Nb 1966 1972 1991 1997 1998 2000
8
Tee Collector Component Material Replacement Year Outlet manifold
Wiscolloy 2032Nb Replaced in 2000 Bull head Tee Expander Incoloy 800H Replaced in 1972 Cone C - 1/2 Mo Cone Bull Head Tee Expander
9
Outlet Manifold Tee Collector Crack
Severe circumferential cracks in weld toe of all four bull head Tee to expander joints. Bull Head Tee (20Cr-32Ni-1Nb) Cracked weld Joint Expander (Incoloy 800H)
10
Outlet Manifold Tee Collector Crack
Grinding of crack
11
Short Term Remedial Actions for Cracks Repair
Stabilization Heat Treatment was carried out prior to welding 125˚C/hr above 425˚C to 980 ˚C Soaking temperature hrs Followed by rapid air cooling Root pass : Inconel 82 Weld completion : Inconel 182 Stage wise DPT and 100 % RT (Root + Final)
12
TRANSFER LINE PROBLEMS
13
Transfer Line Refractory
Hot Face Cold Face Greencast 94 High Alumina, Low Silica, Outstanding abrasion resistance Thickness 3” Max Temperature 1870 ˚ C Thermal 870˚ C 2.03 W/mK Kaolite 2300 LI Backup Insulation, Light weight, Low thermal conductivity Thickness 5” Max Temperature 1260 ˚ C Thermal 870˚ C W/mK
14
Riser Edge Diffuser and Pipe Junction
15
Transfer Line Refractory Problems
Partly refractory damages observed in TA-2011,12 & 13 Location : Approximately 7.0ꞌ eastwards from manway center Approximately ~ 2ꞌꞌ thick refractory missing from a band of 2.5” from 8 O’clock to 11 O’clock 7’0 Eastwards from manway center Refractory damage
16
Transfer Line Refractory Damages TA-15
East Leg Opposite the Riser Crack 5mm wide and 10 cm Long Refractory damage in Junction of Diffuser and Pipe (West Leg) Refractory detached at East Side about 1.5’ above Riser edge
17
Transfer Line Access Problem
Visual inspection to access health of 1998 vintage refractory not possible due to access problem Thermo-graphic inspection was carried out Riser Tee Access Manway
18
Transfer Line Skin Temperature Problem
Gradual rise in skin temperature is observed in the past few years (130˚C ~ 230˚C)
19
Scope of Project Material Up-gradation for complete scope
Refractory evaluation and upgrade Flexibility analysis of process gas for complete circuit Refractory and component joint design Material Supply VSM Services for Project execution monitoring
20
AMEC-FW Response Proposed material: Transfer Line Fabrication: Transfer line to be supplied in 22 no. pre-lined and fully heat cured section due to dry out problem at site. Part Description Existing Material New Material Bull Head Tees 20-32 Nb (Centrifugally Cast) Expanders Incolloy 800H Transfer Line Tee Collectors C Mo 1.25 Cr – 0.5 Mo Transfer Line
21
Proposed Assemblies of Tee Collector
AMEC-FW proposed to provide 2 X complete assembly as shown below: Transfer Line Fabricated Tee Centrifugally Cast Bull Nose Tee Spun Cast Cone
22
Transfer Line Inspection Points
AFW Proposal: 1 peephole in each horizontal straight section. Total Peepholes: 9 FFBL proposed 4 manways instead of peep holes in TL ID 508mm ID 406mm
23
Cost Break Down of Project
Sr. No Description Cost Currency 01 Design Services 76,800 GBP 02 Additional Engineering Cost if required 50,000 03 Material Cost CFR Karachi 1,423,145 04 Sub Total 1,549,945 05 AFW VSM Cost 337,078 06 FFBL Execution Cost 142,898 Total cost in GBP 2,029,921 Total cost in PKR with 5 % Contingency 346,355, 270
24
To be confirmed with AFW
Tentative Timeline Task Start Date Duration End Date Budget Approval CAPEX 1- Oct 2 months 1- Dec VSM Visit Plantsite 4 - Jan 6 days 09 - Jan Contract and PO 10 - Jan 1 months 10 – Feb Kick Off Meeting 25 – Feb 2 days 26 – Feb Design Work 01 – Mar To be confirmed with AFW 01 – May Material Arrival 01 – May 7 months 01 – Nov Pre-fabrication 01- Jan Execution in TA-2017 08 – Jan 22 days 30 – Jan – 2017
25
Gantt Chart Complete execution of the project (Replacement
of 2 X Tee Collectors and Refractory Lined Transfer line) will be carried out in TA-2017 planned in Jan-17.
28
References
29
Hot spot (~334C) & (~554C) were observed only at west side Tee collector (controlled with steam application during startup after TA-2012 & 15 respectively). No Hotspot at other locations.