Presentation is loading. Please wait.

Presentation is loading. Please wait.

P08002: Raising the Bars Ryan Hellems Project Lead Justin Knowles ME

Similar presentations


Presentation on theme: "P08002: Raising the Bars Ryan Hellems Project Lead Justin Knowles ME"— Presentation transcript:

1 P08002: Raising the Bars Ryan Hellems Project Lead Justin Knowles ME
Justin Vowles ME Jeff Osborne ME Jessica Stalker ISE Dr. B. DeBartolo Project Advisor Customer: Nazareth Physical Therapy Clinic, JJ Mowder Sponsor: This material is based upon work supported by the National Science Foundation under Award No. BES Any opinions, findings, and conclusions or recommendations expressed in this material are those of the author and do not necessarily reflect the views of the National Science Foundation

2 Project Rationale The physical therapy clinic at Nazareth uses parallel bars to aid in walking rehabilitation for stroke and other neurological patients. Peg and pin system is difficult, time consuming, and inaccurate when adjusted. Redesign needs to simplify raising and lowering of parallel bars, and insuring they remain level.

3 Key high level customer needs
Must be safe Support patient load without drop (350 lbs) Stable upright supports No pinch points or sharp edges No trip or snag hazards Accurate height adjustment Must be easy to use <9 Lbs force to raise Reasonable time to adjust (90s) Bars remain level along full length Reliable for 5 years of service

4 Current System

5 Selected Concept Selected Concept Existing Parallel Bars
Hand Crank Tower Lifting System Drive Shaft w/cover

6 Design Details – Lifting System
Three posts tied-in series by singular drive shaft 1:1 perpendicular miter gears transmit rotation from drive shaft to ACME rod 5/8-8 ACME Rod supports vertical loads, transmits weight to outer post. ACME nut welded to inner post rides up/down rotating threaded rod

7 Design Details – Hand Crank Tower
4:1 gear ratio for belt drive provides 0.5 inch lift per revolution Ergonomically located hand crank, easy to turn Removable handle prevents incidental adjustment

8 Testing & Lessons Learned
ACME Nut Alignment Test Results: Nuts not square, rod contacts shaft wall Corners of the acme nut were turned down from the as-built to a standard sized hole. Half-part chamfer was added to keep the part square to the shaft as it was welded. Miter Gear Alignment Test Results: Too much movement of gears, bad mesh Thrust plates redesigned to tighten some tolerances Snap rings added to prevent any gear travel Split ring collars added to restrict motion of drive shaft

9 Testing & Lessons Learned
Ease of Installation Check Results: Uneven floor, drive shafts not straight, need to calibrate towers to ensure level Added universal joints with slot for drive shaft length and set screws for angular adjustment Changed bearing design Full Extension Deflection Test Results: Current system better than redesigned at max height Limit functional max height to 42” Powder coat inner post Proposed plastic shim at top of outer post

10 Budget Lifting System - $310.03 Drive Shaft System - $371.30
Hand Crank Tower – $327.04 Powder Coating - $235.00 Misc. Hardware - $80.00 Shipping & Handling – $132.37 Total Cost - $1,455.74

11 Project Evaluation Strengths Easy to use Easy to adjust
central location to adjust both sides; saves walking Easy to adjust Low torque requirement - ergonomics Ability to revert to previous set of parallel bars if design is unacceptable or customer is dissatisfied 16 gauge steel cover to protect against rotating drive shaft can withstand 250 individual falling or jumping on it Professional looking – powder coating won’t rust over time

12 Project Evaluation Weaknesses
Lack of safety cover for hand crank tower exposed belt and sprockets poses pinch point Lack of height indicator Sprocket misalignment may cause premature belt wear Too much deflection from clearance between inner and outer posts

13 Current State Of Design
Design does not meets all customer needs Lacks height indicator & safety covers for hand crank towers Design does not current meet all engineering specs Horizontal deflection is still unknown, close to spec without powder coating, expect better results Torque to raise needs quantification – passed usability trial Budget: Below target Schedule: Schedule slipped, due to long lead time at powder coaters, delay of assembly and testing Successful prototype had unrealized flaws Partial installation scheduled for this afternoon; target completion next week during clinic downtime Future Improvements Easy to convert to electric drive in future Tighter tolerances on posts, looser control of ACME nuts

14 Acknowledgements A special thanks to: Guide: Dr. Beth DeBartolo
Corporate Contact: Nazareth Physical Therapy Clinic JJ Mowder-Tinney Lindsey Pendleton A special thanks to: Rob Kraynik Steve Kosciol Dave Hathaway Paul Gaylo Frank Lucisano (welding) Andrew Cappella (welding) Dr. Daniel Haines (Manhattan) Brian Kolenich (Bailey)


Download ppt "P08002: Raising the Bars Ryan Hellems Project Lead Justin Knowles ME"

Similar presentations


Ads by Google