Download presentation
Presentation is loading. Please wait.
Published byAnnabelle Dawson Modified over 7 years ago
1
RAIL PROJECTS AND TRACK INSTALLATION SUPPORTED BY LONG-TERM TRACK MAINTENANCE SOLUTIONS
2
Today´s Challenges of the Rail Infrastructure Industry
Economic considerations drive railway industry in an increasing complex and competitive environment Life Cycle Cost are predominant today Upfront investments are weighted against maintenance cost Clear cut requirements with regard to construction, operation and maintenance is required Total Service Contractors offer total project management planning, construction and maintenance in certain instances even financing – (ppp-models)
3
Requirements to be met by the track (1)
Tracks have to be laid and maintained to provide a cost effective infrastructure German Federal Railway defined in their Track Strategy project different levels of requirements: Mandatory Requirements Tolerated Requirements Subsidiary Requirements
4
Requirements to be met by the track (2)
and summarized criterias: Overall operational model Availability Economical Riding Comfort Construction and Maintenance Strategies Maintainability Possible Alterations Renewal Investments Reliable supply of components Risk/Failures Safety Damage Symptoms and restoration after derailment Repair of possible fault symptoms in respective tracks Other Requirements
5
Concept of Life Cycle Cost (LCC 1)
LCC Components and their interaction Emergency Repairs Maintenance Investment Inspection and Diagnosis
6
Concept of Life Cycle Cost (LCC 2)
The LCC Model – summarised in brief Life cycle costs can only be optimised as a whole Each cost component of LCC shall be analysed over an entire life cycle Different track systems (e.g. ballasted track vs. ballastless track) can be compared by defining the individual value of the individual cost component according to the track system under review
7
Ballasted Track Line Wels – Linz / Austria
8
Track Construction and Maintenance (1)
Ballasted Track Maintenance intervals – objective: achieve longest possible intervals
9
Tamping Intervals For Ballasted Tracks Depending On The Traffic Load
10
Track Construction and Maintenance (2)
Ballasted Track Maintenance Intervals – objective: achieve longest possible intervals Initial Track Quality – substructure Permanent Way Ballast – quality of ballast Maintenance of Rail Surface – grinding a key operation
11
Grinding Intervals For Ballasted Tracks Depending On The Traffic Load
12
Track Construction and Maintenance (3)
Ballasted Track Maintenance Intervals – objective: achieve longest possible intervals Initial Track Quality – substructure Permanent Way Ballast – quality of ballast Maintenance of Rail Surface – grinding a key operation Infrastructure Elasticity
13
Ballastless Track – Loetschberg Tunnel / Switzerland
14
Track Construction and Maintenance (4)
Ballastless Track – an alternative to Ballasted Track Why ballastless track? A cost effecient solution at least in certain projects Sleeper Pads An additional low cost improvement
15
General Contractor in Rail Engineering
The benefits All from one partner; use of synergies, reduced friction No planning and functionallity risk – all is general contractor‘s responsibility High level of schedule reliability Easier Budget and Cost control Complex logistical and construction site safety issues are centralized and in one hand
16
Organisation Chart of Loetschberg Tunnel Project
17
Diagram of the Loetschberg Tunnel
18
Details for Track Construction
Timing: Design: 10/2002 – 03/2004 Trials and Preparation: 01/03 – 09/04 Realisation: 04/2004 – 10/2006 Length of track: Total 57 km, 51 km in tunnel Slab track system: LVT / Sonneville Sleepers: 171‘000 blocks type LVT (60 cm spacing) Rails: UIC 60: tons High speed-turnouts: 2 on slab-track, 1 on ballasted track Concrete: 80‘000 m³ Max. Operating speed: 250 km/h (in tunnel) Totel value track construction: Euro 85 MIO
19
Requirements on Track Quality
Useful life for basic track layer, fill-in concrete (2nd pour) and sleepers at least 50 years Resisting high impact and providing the possibility for simple maintenance Keeping track tolerances of +/- 2 mm in horizontal und vertical direction Keeping track gauge of 1435 mm -1/+ 3 mm The requirements on the quality of the concrete surface regarding levelling and cleanliness are very high Further impacts due to high utilization of the tunnel, maximum speed, axle loads, corrosion, etc.
20
Logistic Challenge Real logistic challenge in single-track tunnel
Just one single access route for transport and supply Construction of various installations and temporary yards for efficient performance Just-in-time co-ordination to guarantee material supply in all fields of activities High speed of transport (about 60 km/h) requires special safety measures (control centre, identification of position) Co-ordination and interface management with tunnel carcass construction, overhead line construction, mechanical equipment, cable laying and safety installations
21
Conclusions Well defined and managed technical, functional and performance requirements in terms of construction, operation and maintenance underpin and are the essentials for the commercial success of a project and the subsequent cost-effective operation of a railway infrastructure High quality execution of works and an optimised maintenance regime are still a must for a successful Life cycle project approach For this reason the selection of the right partner – experience combined with enthusiasm for the project and commitment of executing staff
22
THANK YOU FOR YOUR ATTENTION
23
MSc Hubert Rhomberg info@bahntechnik.com www.bahntechnik.com
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.