Eps: Campus rainworks challenge
by: Haelea mcCallister, Jacob mercante, & Caleb Oliphant Et 494 – Spring 2017 Instructor: Chris Koustageras Advisor: Edward Rode
2
Purpose The EPA’s campus Rainworks challenge is for students to create green infrastructure for the campus to manage storm water runoff. Each team member will create a master plan and demonstration for the project plus engagement in the community. We each choose to create a retention pond for a selected area on campus Fifth annual campus challenge.
3
Procedures Identified the location for the Retention pond Identified
Surveyed the land and found the elevation Found where the underground utilities are located Identified water source Vegetation Water storage pump Designed Pond and berm Pump house Material take-off Schedule
4
Vegetation Soft Rush Pickerelweed Inkberry Hybrid Louisiana Iris
5
Storage Tanks Graf Underground storm water tanks - 2 x 5000L tanks
gallons stored - Filter and housing - mosquito proof - 2ft opening Plus a 100gallon overflow tank with sump pump
6
Pump and Piping Sump Pump installed in the over flow section of the storage tanks. When tanks are full, the water will be pumped out towards the pond. At a flow of 5,400 Gallons Per Hour. Piping from tanks are to be 6” schedule 40. Gutters will be used from the buildings to the filter in the tank.
7
Pump Building 5ft x 6ft building Exterior wood door 5000psi concrete
Treated lumber Metal roof 4x3 window Brick veneer
8
Pump Building
9
Pump building Material take-off
Quantity Cost per unit Total 1/2'' plywood 2 $14.25 $28.50 3/8" plywood 7 $13.43 $94.01 2"x4"x8' 46 $2.66 $122.36 2"x6"x12' 1 $9.43 concrete 0.81 cubic yards $457 / 1.5 cubic yards $247 gravel 0.44 ton $30 / ton $13.20 door $187.68 window $138.03 metal roof $25.98 $51.96 roof panel ridge $15.49 brick veneer $330 / 4 pack $2,310.00 #5 rebar $12.06 / 20' piece $12.06 $3,229.72
10
Caleb’s Site and elevation
collection Area– 21,000 sqft Pond Width- 100 ft Length – 120 ft Depth – 8 ft Total Volume – 719,000 Gallons
11
Caleb’s full Design Collection Area– 21,000 sqft Pond Width- 100 ft
Length – 120 ft Depth – 8 ft Total Volume – 719,000G
12
Caleb’s Working Drawing
13
Estimation
14
schedule Total completion time: 25 days Start date: July 3, 2017
Pond % Phase Start Date End Date Survey and Stake the Area 3-Jul-17 Clear Site 4-Jul-17 Dig Out the Pond 5-Jul-17 11-Jul-17 Build up Berm 12-Jul-17 18-Jul-17 Dig Out the Overflow 19-Jul-17 Bring in Gravel and Sand 20-Jul-17 Spread Gravel and Sand 21-Jul-17 Fill Pond 24-Jul-17 26-Jul-17 Landscape 27-Jul-17 28-Jul-17 Tanks And Piping Clear Sites Layout the Pipes and Tanks 6-Jul-17 Dig Trenches and Tank Holes 7-Jul-17 10-Jul-17 Set the Tanks and Pipes Test System 13-Jul-17 Fill Holes and Trenches 14-Jul-17 Compact Disturbed Soil 17-Jul-17 Electrical Housing Survey Dig out Footing Areas Place FormBoards for Footings Pour Concrete Place Sand and Gravel Form and Pour Slab Build Walls and Cover Outside With Plywood Build Roof Frame and Cover with Plywood and Tin Set Window and Door Place Exterior Brick Veneer Hook up all Electrical Outlets and Equipment 25-Jul-17 Total completion time: 25 days Start date: July 3, 2017 End date: July 28, 2017
15
Haelea’s site and Elevation
16
Haelea’s Full Design collection Area – 24,000 sqft Pond Width – 100 ft
Length – 100 ft Depth – 6 ft Total Volume – 449,000 G collection Area – 24,000 sqft Pond Width – 100 ft Length – 100 ft Depth – 6 ft Total Volume – 449,000 gallons
17
Haelea’s Working Drawing
18
estimation
19
schedule Total Completion time: 26 days Start date: June 1, 2017
End date: July 5, 2017
20
Jacob’s Site and Elevation
COLLECTION AREA– 76,000 SQFT Pond Width – 60 ft Length – 120 ft Depth – 12 ft Total Volume – 646,000 Gallons
21
Jacob’s Full Design COLLECTION AREA– 76,000 SQFT Pond
Width – 80 ft Length – 120 ft Depth – 9 ft Total Volume – 646,000 G
22
Jacob’s Working Drawing
23
Estimation Specialty Quantity Cost Time(8hr Days) Total Price
Material Quantity Description Cost Total Price 4"X4"X12' Post (TRTD) 4 Deck $14.82 (Piece) $59.28 2"X4"X8' (TRTD) 15 $3.54 (Piece) $53.10 Tanks 2 Water Storage $8,000 (Each) $16,000 Filter 1 Filter Water $1,500 Pump Transport Water $199 Wire (12 Gauge)Southwire 250 ft Electrical $79.97 6" Schedule 40 370 ft $2.11/ft $780.70 1" Schd PVC Conduit (Electrical)Cantex 10 ft $3.70 $37 Clay 90 yd^3 Pond $9 yd^3 $810 Gravel $19.96 yd^3 $1,796.40 Sand $10.96 yd^3 $986.40 Top Soil 3 yd^3 Landscape $2.80 yd^3 $8.40 Flowers Soft Rush 10 $26 $260 Inkberry $40 $600 Louisiana Iris 30 $12 $360 Pickerelweed 40 $7.59 $304 Lemon Grass $7.95 $80 Trees Bald Cypress(22"-26") 8 $33.90 $271.20 Eastern Redbud $64.95 $520 Grass Harmony Sod 3500 ft^2 $429 per 500ft^2 $3,003 Total Cost $27,707.15 Building Cost $3,229.72 Total Cost of Project $79,320.83 Specialty Quantity Cost Time(8hr Days) Total Price General Labor 8 crew $14.75/hr 35 $33,040 Heavy Equipment Operator 1 crewmember $19.00/hr 11 $1,672 Electrician $20.62/hr 1 $164.96 Surveyer 2 crewmembers $19.05/hr 2 $304.80 Dump Truck Driver $16.15/hr $1,421.20 Total Cost $36,602.96 Equipment Time(Days) Excavator 420 $330/day $3,630 Compactor CP44 $435/day 6 $2,610 Bulldozer D5K lb $675/day $4,050 Auger $71/day $71 Dump Truck Hydrema yd^3 $710/day $1,420 $11,781
24
Schedule Total completion time: 28 days Start date: June 5, 2017
End date: July 5, 2017