Presentation is loading. Please wait.

Presentation is loading. Please wait.

DOING BUSINESS WITH ALBERTA INFRASTRUCTURE

Similar presentations


Presentation on theme: "DOING BUSINESS WITH ALBERTA INFRASTRUCTURE"— Presentation transcript:

1 DOING BUSINESS WITH ALBERTA INFRASTRUCTURE
Presentation to Alberta’s Local Construction Associations 2016

2 Session Outcomes Work Opportunities
Where to Find Opportunities & How to Bid Contractual Obligations Improvement Initiatives

3 GoA Capital Plan $34.8 billion total

4 Infrastructure Opportunities

5 Session Outcomes Work Opportunities
Where to Find Opportunities & How to Bid Contractual Obligations Improvement Initiatives

6 Where to find our Work Construction tenders estimated at $100,000 or greater Alberta Purchasing Connection CoolNet Alberta Construction tenders estimated below $100,000 Invite 3 contractors Locally procured by Property Management Division

7 Bid Submissions Electronic Bids Hard Copy Bids NOTE
COOLNet Alberta: coolnetalberta.com Hard Copy Bids NOTE Modifications / withdrawals must be completed in the same format as the original submission. In the event a bidder submits an electronic and a hard copy version, only the electronic bid will be accepted.

8 Bid Results and Notifications
A public bid opening will be held. All bidders are invited to attend. Bid results and award information will be available on Alberta Purchasing Connection. Opening and result notification for Invitational Tenders will be provided by the Project Manager.

9 Do’s and Don’ts Common Bid Form Issues:
Use the correct form and make sure it is complete Proper date Signed Do not make alterations to the bid form text Do not attach or include conditions, assumptions or unsolicited information Qualifying the Interim Acceptance Date Late Submission

10 Do’s and Don’ts Common Bid Bond Issues Not completed properly
Wrong form Not signed and sealed by bidder and surety Wrong owner Wrong date Wrong project Bond amount is less than the bid Not valid for specified time period Submit the original Do not include qualifications

11 Bid Evaluation Checklist

12 Session Outcomes Work Opportunities
Where to Find Opportunities & How to Bid Contractual Obligations Improvement Initiatives

13 Contractual Obligations
Comply with Safety and Security Requirements Alberta Construction Safety Association COR Security protocols, criminal record checks (e.g. courts, schools, hospitals) Pre-qualifications (e.g. asbestos) Prime Contractor Typically the GC on new build Typically the Property Manager on operational buildings Comply with Facility Emergency Response Plans (FERP) Bonding (Performance) Insurance Do not qualify insurance requirements CHECK THE CONTACT PROVISIONS

14 FOIP Act Contractors providing services for public bodies must follow FOIP rules Records about the services provided, not about the contractor’s own operations. Follow same rules for collecting, using, and disclosing personal information that a public body would have to follow. Retrieve and provide records to the public body within a few days. Contractor’s obligations should be clearly set in the contract. For more information visit

15 Financial Administration Act
Applies to all GoA projects Fundamentally changes role of consultant All payments have to be approved by GoA employee Can only pay for goods and services actually received Increased scrutiny Right to audit

16 Session Outcomes Work Opportunities
Where to Find Opportunities & How to Bid Contractual Obligations Improvement Initiatives

17 Prompt Pay Recognize this is a significant issue
AI participation on Alberta Construction Association ad-hoc prompt pay committee Trade contractors coalition Two areas of focus Timely payment of progress claims Progressive release of holdback

18 Progress Claims Changes to Alberta Infrastructure Contracts
Clearer invoicing requirements AI will pay verified amount within 30 calendar days of receipt of invoice Modified Stat Dec includes that GC pay the subcontractors within 10 days of receipt of payment from GoA Subcontractor access to GoA payment information

19 Progressive Release of Holdback
Upon application, holdback funds will be released once the portion of the work is complete AI verify substantial performance After 45 day period, contractor applies for release as part of next progress claim Warranty still from date of Interim Acceptance

20 Contract Close Out Collaborated with the Alberta Construction Association Timely delivery of contract close out documents (O & M Manuals, Record Drawings) Improvements to contractual specifications: Mark-up drawings to be a standing agenda item for Progress Meetings Contractor to include each Close-out Procedure activity in the Project Schedule and Project Meetings A payment condition percentage will be applied on a sliding scale based on project dollar value

21

22 WHO TO CONTACT General inquiries
Neil Kjelland, Executive Director, Procurement or Max Amodio, Director, Construction Procurement or For project specific inquiries, please contact the person identified on the solicitation documents

23


Download ppt "DOING BUSINESS WITH ALBERTA INFRASTRUCTURE"

Similar presentations


Ads by Google