Download presentation
Presentation is loading. Please wait.
1
Civil Design for Tunnel Case Studies
October 12~13, 2011 GDE-CFS Meeting at KEK
2
Common Design Two tunnels (Beam tunnel and Service tunnel) are allocated for BDS part On TBM case (Case 1 ~ 5) are the same layout (φ 4.5m for both tunnel) On NATM case (Case 6 ~ 8) are the same layout (W=4.5m H=4.0m for both tunnel) RTML loop part is constructed by NATM Sub tunnel (Case 3, 4, 5 and 6) is allocated Damping ring side BT ST AH AT BT AH AT BT SbT AT PM BT SbT AH AT PM KL Case 1 Case 2 Case 3 Case 4 BT SbT AH AT LC BT SbT AH AT LC BT AH AT BT AH AT Case 5 Case 6 Case 7 Case 8
3
Case 1 D-T-R (Double/TBM/RDR)
Main Transformer Above Ground Sub Transformer A/H Based on the RDR tunnel design Inner diameter is 4.5m both Using TBM to excavate these tunnels Six access halls with access tunnel (1km long sloped tunnel) from ground surface AC DC PM TR KL Service-T Accelerator Cryo-Module Beam-T Beam tunnel Service tunnel
4
Case 2 S-T-R (Single/TBM/RDR)
Main Transformer Above Ground Sub Transformer A/H Single large diameter tunnel includes all equipment Inner diameter is 7.4m Using TBM to excavate these tunnels The tunnel is separated with 0.4m thick concrete floor Six access halls with access tunnel (1km long sloped tunnel) from ground surface AC DC PM TR KL Beam-T Accelerator Cryo-Module Beam tunnel
5
Case 3 JS-T-X (J Single/TBM/XFEL)
Main Transformer Above Ground XFEL layout (TR and KL is located in Beam tunnel, other equipments are in A/H) Tunnel configuration is composed of Beam tunnel & sub tunnel Inner diameter is 5.2m and 3.2m for Beam tunnel and sub tunnel respectively Using TBM to excavate these tunnels Six access halls with access tunnel (1km long sloped tunnel) from ground surface Pulse modulators are installed in A/H Sub Transformer AC DC PM A/H TR KL Beam-T Accelerator Cryo-Module Beam tunnel Sub tunnel
6
Case 4 JS-T-K (J Single/TBM/KCS)
Main Transformer Above Ground Sub Transformer KCS layout Tunnel configuration is composed of Beam tunnel & sub tunnel Inner diameter is 4.5m and 3.2m for Beam tunnel and sub tunnel respectively Using TBM to excavate these tunnels Twelve access halls with access tunnel (1km long sloped tunnel) from ground surface All equipments are installed in A/H A/H AC DC PM TR KL Accelerator Cryo-Module Beam-T Beam tunnel Sub tunnel
7
Case 5 JS-T-D (J Single/TBM/DRFS)
Main Transformer Above Ground Sub Transformer A/H DRFS layout Tunnel configuration is composed of Beam tunnel & sub tunnel Inner diameter is 5.7m and 3.5m for Beam tunnel and sub tunnel respectively Using TBM to excavate these tunnels Six access halls with access tunnel (1km long sloped tunnel) from ground surface Local caverns at 617m intervals (4 cryo strings length) for installation of cooling equipment AC L/C DC PM TR KL Accelerator Cryo-Module Beam-T Beam tunnel Sub tunnel
8
Case 6 JS-N-D (J Single/NATM/DRFS)
Main Transformer Above Ground Sub Transformer DRFS layout Tunnel configuration is composed of Beam tunnel & sub tunnel Inner section is 5.7m and 3.3m for Beam tunnel and sub tunnel respectively Using NATM to excavate these tunnels Six access halls with access tunnel (1km long sloped tunnel) from ground surface Local caverns at 617m intervals (4 cryo strings length) for installation of cooling equipment A/H AC L/C DC PM TR KL Accelerator Cryo-Module Beam-T Beam tunnel Sub tunnel
9
Case 7 S-N-D (Single/NATM/DRFS)
Main Transformer Above Ground Sub Transformer A/H DRFS layout Appropriate section can be excavated to install various equipments The tunnel is separated by partition concrete wall (t=0.4m) The wall thickness is selected to be sufficient to protect installed equipments from radiation Inner section of Beam Tunnel is W=9m H=4.5m Using NATM to excavate these tunnels Six access halls with access tunnel (1km long sloped tunnel) from ground surface Local cavern can be omitted because of enough space for equipments installation AC DC PM TR KL Accelerator Cryo-Module Beam-T Beam tunnel
10
Case 8 wS-N-D (Wide Single/NATM/DRFS)
Main Transformer Above Ground Sub Transformer A/H DRFS layout Appropriate section can be excavated to install various equipments The tunnel is separated by partition concrete wall (t=3.5m) The wall thickness is selected to be sufficient to protect personnel in tunnel from radiation Inner section of Beam Tunnel is W=11m H=5.5m Using NATM to excavate these tunnels Six access halls with access tunnel (1km long sloped tunnel) from ground surface Local cavern can be omitted because of enough space for equipments installation AC DC PM TR KL Accelerator Cryo-Module Beam-T Beam tunnel
11
Damping ring
12
Cavern shape Experimental Hall According to KEK’s information
Longitudinal section Plan Section
13
Cavern shape Local Cavern In consideration of equipment layout,
1st floor 2nd floor Cooling system for dispersed power source Longitudinal section
14
Cavern shape Access Hall Sub transformer Cooling water system
Ventilation & air conditioning facilities Cryogenic cooling plant 2nd floor 1st floor Longitudinal section
16
Cavern shape Access Hall (XFEL & KCS)
Attached access hall that contain the following facilities is considered for XFEL & KCS
17
Construction Schedule & Cost Estimation
October 12~13, 2011 GDE-CFS Meeting at KEK
18
Contents Basic condition Construction plan & procedure Schedule
Cost estimation assumption Unit cost for estimation Component of unit cost Unit cost Construction cost for each case
19
Basic Condition In consideration of the situation that ILC site is in Japanese mountainous area, tunnel layout and design are planned As access route to Experimental Hall and Access Hall, inclined tunnel (drift) is adopted in all cases
20
Summary Cost for Case 7 is the lowest
Case 7 and Case 8 have almost the same construction period The difference between Case 7 and Case 8 is the thickness of partition wall
21
Construction Plan Beam Tunnel (TBM)
After the end of Access Hall (A/H) construction, Beam Tunnel excavation will be commenced TBM assembling will be carried out in A/H One way excavation from A/H In double tunnel case (Case 1, 3~6), 2 months later from first tunnel excavation commencement, second tunnel will be commenced
22
Construction Plan Beam Tunnel (NATM) Beam Tunnel (others)
Construction Adit will be constructed in addition to the Access Tunnel at A/H As a result, Beam Tunnel and A/H can be excavated in parallel Tunnel excavation can be carried out in the opposite direction from A/H (2 faces) Beam Tunnel (others) Excavation and concrete lining can be carried out in parallel on Case 2, 7 and 8 However, detail construction method should be considered for Case 7 especially, because the tunnel size is comparatively-small NATM excavation is adopted on RTML loop part in all cases
23
Construction Plan Access Hall (A/H) Approaching through Access Tunnel
Top and bottom drift will be constructed, one is a top drift for the top of A/H, the other tunnel is for the bottom of A/H Pier and slab which is needed for installation various equipments will be constructed after Beam Tunnel construction in the meantime
24
Construction Procedure (A/H & Beam Tunnel)
TBM Beam T Around 5000m Access T excavation Concrete lining Drainage, Partition Wall A/H Concrete 1 2 3 4 5 6 A/H excavation Beam T excavation (One way)
25
Construction Procedure (A/H & Beam Tunnel)
NATM Beam T Around 5000m Access T excavation A/H excavation Partition wall etc. 1 2 3 4 A/H Concrete Lining concrete for Beam T
26
Construction Plan Experimental Hall (E/H)
Approaching through Access Tunnel Access Tunnel will be branched into two tunnels along the way, one is a top drift for the top of E/H, the other tunnel is for the bottom of E/H Excavation method is bench cut Shaft (glory hole) will be constructed and utilized for mucking Plan Longitudinal profile
27
Construction Plan Local Cavern Damping Ring Tunnel (DR)
Local Cavern will be constructed only for Case 5 & 6 for installation of cooling facilities for dispersed power source Damping Ring Tunnel (DR) Approaching through Access Tunnel from portal, which is connected with opposite side of E/H access tunnel In the case of TBM, when the access tunnel come at DR Service Cavern, DR excavation will be commenced, because DR service cavern is needed for TBM assembling In the case of NATM, when the access tunnel intersect with DR, DR excavation will be commenced. After that when the access tunnel come at DR service cavern, DR will commenced as counter excavation as well
28
Construction Procedure (Central region)
1 2 Access T excavation for DR (TBM) DR T excavation (TBM) Access T excavation for E/H E/H excavation Service cavern excavation 3 4 Beam Connecting T & Service T excavation from DR side Lining concrete for DR Tunnel Beam T & Service T excavation from Beam T side Lining concrete for DR Tunnel E/H concrete Service cavern concrete Installation of experimental equipment To the Next Page
29
Construction Procedure (Central region)
5 6 Lining concrete for Beam connecting T & Service T from Beam T side Drainage and Partition Wall 1 2 In the case of NATM Access T excavation for DR DR T excavation Access T excavation for E/H E/H excavation Service cavern excavation
30
P 11 ~ 15 Construction Plan Difference between TBM and NATM for A/H & Beam Tunnel excavation <TBM> Access Hall should be constructed initially because of TBM assembling One-way excavation for Beam Tunnel between each A/H <NATM> Access Hall and Beam Tunnel can be excavated in parallel Beam Tunnel is constructed through construction Adit that is branched from Access Tunnel. Counter excavation can be executed (two faces excavation can be carried out from each Construction Adit) Around 10 months reduction in relation to the construction time between A/H and Beam Tunnel
31
Access Hall Layout (TBM & NATM)
P 3 & 10 Access Hall Layout (TBM & NATM) TBM (Case 1) 1. Access T 2. A/H 3. Beam T NATM (Case 8) 1. Access T 2. A/H & Beam T
32
Construction Schedule (TBM)
P 16 Construction Schedule (TBM) Necessary construction period for TBM According to Japanese TBM vendor’s information, Process Period Contents TBM Assembling 2 months Starting base construction and TBM assembling Initial Excavation Installation of following trolley for TBM with excavation Excavation Refer to the following table (next page) Routinely operation of TBM Trouble 1 month/time, 3 times/10km Unforeseeable accident (unstable bedrock, breakdown of TBM, etc.) Approaching 0.3 month Removal of following trolley of TBM with excavation Dismantlement 2 month TBM dismantlement
33
Construction Schedule (TBM)
P 16 Construction Schedule (TBM) Item Unit φ3.0 φ3.2 φ3.5 φ4.5 φ5.0 φ5.2 φ5.7 φ7.4 Thickness of lining concrete m 0.2 0.3 Excavation diameter 3.5 3.7 4.0 5.2 5.7 5.9 6.4 8.1 1 stroke length 1.5 Tunneling speed m/h 3.52 3.33 3.08 3.76 3.51 3.42 3.20 2.60 Shotcrete length 5.50 5.81 6.28 8.17 8.95 9.27 10.05 12.72 Shotcrete thickness 0.05 Excavation time period min/st 26 27 29 24 28 35 Adjustment of survey and gripper position 13 Sub total 39 40 42 37 41 48 Invert segment installation (10) Fiber shotcrete 25 32 38 45 Sub total (Tunneling cycle) 64 66 69 74 79 93 Material replacement, others 46 58 Total (whole cycle) 89 98 106 115 116 125 151 Number of stroke per day st/day 12.13 11.61 11.02 10.19 9.39 9.31 8.64 7.15 Excavation progress per day m/day 18.2 17.4 16.5 15.3 14.1 14 10.7 Excavation progress per month m/month 418 400 379 351 324 322 299 246 *) φ5.5 is calculated by interpolative prediction between φ5.2 & 5.7 (308m/month)
34
Construction Schedule (NATM)
P 16 Construction Schedule (NATM) Necessary construction period for NATM According to Japanese Standard for excavation (Ministry of Land, Infrastructure, Transport and Tourism), Process Period Contents Temporary facilities 1~3 month Portalling, Temporary material installation for excavation in Hall Excavation Refer to the following table Applied National Land Transportation Ministry standard Bifurcation 1 month Portalling for tunnel branch
35
Construction Schedule (NATM)
P 16 Construction Schedule (NATM) Unit: m/week (upper) m/month (lower) Cross-section area: 50~100m2 Rock mass rating Bench tunneling method Cross-section area (m2) 50 55 60 65 70 75 80 85 90 95 C1 24.07 2l.98 21.98 20.22 18.72 18.06 17.43 16.85 16.31 110.72 101.11 93.01 86.11 83.08 80.18 77.51 75.03 Cross-section area: 20~50m2 Rock mass rating Rail haulage Cross-section area (m2) Rubber-tire vehicles haulage 20 25 30 35 40 45 C1 17.43 16.31 14.87 25.28 22.98 21.98 80.18 75.03 68.40 116.29 105.71 101.11 Specific small cross-section Inner Section Muck handling Ex. speed (m/month) Application h w 3.00 3.30 Rail haulage 85 Sub tunnel for Case6 3.65 2.50 Rubber-tire vehicles haulage 108 Connecting Tunnel (Evacuation Tunnel)
36
Construction Speed (NATM)
37
Construction Schedule (various halls)
Construction schedule for large cavern apply common cycle time (count by minutes) of underground power plant Drilling, Charging, Blasting, Chipping (Scaling), Mucking, Shotcrete, Steel Support, Rock Bolt, Loss/Others
38
Construction Schedule (various halls)
Experimental Hall 22.5 month Access Hall Cavern Progress Case RDR H21m×W21m×L123m 10.2 month Case 1, 2, 3 XFEL H12.5m×W19×L113m 15.1 month ( month) Case 4 KCS H17m×W26×L113m 17.0 month ( month) Case 5 DRFS Case 6, 7, 8 Local Cavern (Case 5, 6) 2.8 month (H10 m X W10m X L 45m)
39
Construction Schedule
P 17 Construction Schedule Case HLRF Progress (month) Construction Method Remark CASE1 D-T-R RDR 76.0 TBM Basic case CASE2 S-T-R 78.6 Excavation and Concrete in parallel CASE3 JS-T-X XFEL 82.1 CASE4 JS-T-K KCS 82.8 CASE5 JS-T-D DRFS 78.3 CASE6 JS-N-D 78.8 NATM CASE7 S-N-D 60.9 Excavation and Concrete in parallel *) CASE8 wS-N-D 62.7 *) Regarding Case 7, detail construction method should be considered especially, because the tunnel size is comparatively-small
40
Construction Schedule
P 17 P18~25 Construction Schedule The detail of construction schedule is shown in P18~25 of the case studies report.
41
Cost estimation assumption
TBM tunnel Cost estimation standard issued by NEXCO (Nippon Expressway Company Limited) applied to TBM cost estimation Concrete lining support was adopted As a result of pre-cost-estimation for TBM lining in three types, one is concrete lining, another concrete segment, the other shotcrete lining, concrete lining was adopted because of inexpensive However, in the case of sub tunnel of Case 3, 4 and 5, shotcrete lining was adopted
42
Cost estimation assumption
NATM tunnel Japanese Standard (Ministry of Land, Infrastructure, Transport and Tourism) applied to NATM cost estimation However, this standard doesn’t cover small section tunnel (under 20m2), therefore previous standard in which standard cycle time for excavation is shown applied to the small section tunnel
43
Cost estimation assumption
Experimental Hall There is not a standard for large cavern cost estimation, that’s why, the cost is referred to the past cost record of similar cavern (underground power plant) Access Hall & Local Cavern Japanese Standard (Ministry of Land, Infrastructure, Transport and Tourism) applied to the excavation cost
44
Unit cost for estimation
Labor Work on a two-shift 10hrs working for one-shift Transmittal unit cost for labor for public work issued by Ministries Equipment Japanese Standard issued by Ministry applied to equipment cost estimation As for TBM, Japanese vendor’s quotation applied to equipment cost estimation
45
Unit cost for estimation
Material Economics research firm data applied to material cost estimation Material cost for TBM is referred to vendor’s quotation
46
P 27 ~ 28 Component of unit cost Excavation (= Direct Cost + Indirect Cost + Others) Direct cost Excavation (labor, material, equipments, repair, maintenance, electricity, consumption articles, etc.) Mucking (labor, materials, equipments, conveyer, electricity, etc.) Shotcrete (labor, materials, equipments, electricity, etc.) Support (material, equipment, electricity, etc.) Invert segment (labor, materials, equipments, etc.) Concrete lining (labor, materials, formwork, equipments, etc.) Wave guide (labor, materials, etc.) Partition wall (labor, materials, formwork, equipments, etc.) Grouting (10% of TBM sum, 20% of NATM sum) Miscellaneous work Auxiliary cost
47
Component of unit cost Indirect cost Others
65% of TBM works + 100% of NATM & auxiliary cost TBM transportation, assembling, dismantlement Temporary works Common works Others 10% of total cost (direct + indirect cost) as contingency expense
48
Unit rate for excavation
P 26 Unit cost Unit cost for cavern excavation Structure Shape Unit rate for excavation (m) (yen / no.) (thousand yen / no.) Experimental Hall W=30, h=40, L=120 7,130,934,000 7,130,934 Access Hall W=20, h=21, L=123 560,560,000 560,560 Case3 Access Hall W=18.9, h=11.45, L=113.5 330,116,000 330,116 Case4 Access Hall W=26, h=16.5, L=113.5 479,396,000 479,396 Damping Ring Service Cavern, Local cavern W=15, h=11.1, L=42.5, W=10, h=11, L=40 57,953,000 57,953
49
Unit rate for excavation
Unit cost P 26 Unit cost for tunnel excavation Structure Shape (m) Tunnel Section (m2) Unit rate for excavation (yen / m) (thousand yen / m) Case3, 4 Sub Tunnel φ3.2 10.179 712,027 712 Case5 Sub Tunnel φ3.5 11.946 759,055 759 Case1, 4 Beam Tunnel, Case1, BDS Service Tunnel φ4.5 21.237 915,816 916 Case3 Beam Tunnel φ5.2 27.340 1,015,661 1,016 Damping Ring, Beam Connecting Tunnel φ5.5 30.190 1,061,171 1,061 Case5 Beam Tunnel φ5.7 32.170 1,091,512 1,092 Case2 Beam Tunnel φ7.4 51.530 1,382,010 1,382 Case6 Beam Tunnel W=5.7, h=4.65 31.191 501,600 502 Case6 Sub Tunnel W=3.3, h=3 11.481 290,000 290 Case7 Beam Tunnel W=9, h=4.5 45.193 582,100 582 Case8 Beam Tunnel W=11.0, h=5.5 64.738 720,000 720 Connecting Tunnel W=2.5, h=3.65 9.900 280,000 280 Damping Ring Tunnel, Beam Connecting Tunnel, Service Tunnel W=5.5, h=4.7 29.761 451,000 451 RTML Loop Part, Beam Tunnel (BDS part), Service Tunnel (BDS part) W=4.5, h=4 21.896 470,000 470 E/H Access Tunnel W=11, h=11 1,201,000 1,201 Access Tunnel W=8, h=7.5 61.724 552,000 552
50
Construction cost for each case
P 26 Construction cost for each case Part Case 1 Case 2 Case 3 Case 4 Case 5 Case 6 Case 7 Case 8 ML 51,980,868 41,307,401 48,027,490 53,027,462 58,002,102 36,088,023 23,076,292 33,461,856 RTML 4,293,726 3,866,726 4,716,358 4,924,918 4,343,042 3,442,142 3,077,152 3,525,794 BDS 12,140,628 12,372,440 6,918,812 6,687,000 DR 4,715,773 2,551,981 E/H 8,689,394 Auxiliary Method 11,494,507 10,387,262 11,033,124 12,310,184 12,710,262 12,538,070 9,816,364 11,983,205 Direct Cost 93,314,896 81,107,184 89,322,767 95,808,359 100,833,013 70,228,422 53,898,183 66,899,230 Indirect Cost 68,647,518 60,802,955 65,673,559 72,535,916 75,583,611 65,840,098 50,462,456 62,705,108 Contingency Expense 16,162,641 14,184,294 15,466,033 16,800,828 17,608,062 13,606,852 10,436,064 12,960,434 Amount 178,125,055 156,094,433 170,462,358 185,145,103 194,024,687 149,675,371 114,796,702 142,564,772 (hundred million yen) 1,781 1,561 1,705 1,851 1,940 1,497 1,148 1,426
51
Total cost for each case
P 26 Total cost for each case
52
Summary of construction schedule and cost
The construction period for Case 3 & 4 are longer than other cases because of large A/H Case 5 has the highest cost because of large diameter tunnel Case 7 has the lowest cost because of only one tunnel excavation and the tunnel size is comparatively small Case 7 & 8 has the almost same construction period The reason that Case 8 has bigger cost than case 7 is due to concrete partition wall cost
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.