Project Management Earned Value Management Demonstration
2
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Task A Task B Task C Per day Running
3
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Task A Task B Task C Per day Running BAC
4
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC
5
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC Planned Value (PV) = 675
6
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC Planned Value (PV) = 675 Earned Value (EV) = (100% of 300) + (25% of 800) + (0% of 575) = 500
7
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC Planned Value (PV) = 675 Earned Value (EV) = 500 Actual Cost (AC) = = 575
8
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC Planned Value (PV) = CPI = EV/AC = 500/575 = .87 Earned Value (EV) = 500 Actual Cost (AC) = 575
9
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = EV/PV = 500/675 = .74 Actual Cost (AC) = 575
10
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
11
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC EAC = BAC/CPI = 1675/.87 = 1925 Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
12
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC EAC = 1925 ETC = EAC – AC = 1925 – 575 = 1350 Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
13
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC EAC = 1925 ETC = 1350 (BAC – EV) TCPI = = ---- = 1.07 (BAC – AC) Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
14
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC EAC = 1925 ETC = 1350 TCPI (BAC) = 1.07 (BAC – EV) TCPI = = ---- = .87 (EAC – AC) Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
15
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC EAC = 1925 ETC = 1350 TCPI (BAC) = 1.07 (BAC – EV) TCPI = = ---- = .87 (EAC – AC) Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
16
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running BAC EAC = 1925 ETC = 1350 TCPI (BAC) = 1.07 TCPI (EAC) = .87 Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
17
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running VAC = BAC – EAC 1675 – 1925 -250 BAC EAC = 1925 ETC = 1350 TCPI (BAC) = 1.07 TCPI (EAC) = .87 Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
18
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running VAC = BAC – EAC 1675 – 1925 BAC EAC = ETC = 1350 TCPI (BAC) = 1.07 TCPI (EAC) = .87 Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
19
Earned Value Management (EVM) demo
Mon Tue Wed Thu Fri Total Status Cost Task A % 325 Task B % 250 Task C % 0 Per day Running VAC = BAC – EAC 1675 – 1925 BAC EAC = ETC = 1350 TCPI (BAC) = 1.07 (BAC – EV) TCPI = = ---- = .94 (EAC – AC) Planned Value (PV) = CPI = .87 Earned Value (EV) = SPI = .74 Actual Cost (AC) = 575
20
Earned Value Management (EVM)
Know all formulas PMBOK® pg. 224 For any EAC calculation, use BAC/CPI EV is emphasized; EV -, or EV numerator Cost formulas use AC Variances > 0 implies behind schedule/over budget <0 implies ahead of schedule/under budget =0 implies on schedule/on budget Indicies <1.0 implies behind schedule/over budget >1.0 implies ahead of schedule/under budget =1.0 implies on schedule/on budget