1 CONDITIONAL GRANTS AND CAPITAL EXPENDITURE
PUBLIC HEARING ON CONDITIONAL GRANTS AND CAPITAL EXPENDITURE 08 May 2006

2 INTRODUCTION The Free State Department of Education has been invited to Public Hearings and to address the NCOP Select Committee on Finance on the following: Data trends in conditional grants and capital expenditure allocations 2005/06 Transfers and actual expenditure Assessment on Department’s monitoring capacity Indication of under spending/ overspending Capacity constraints and their impact

3 2001/02 – 05/06 CONDITIONAL GRANTS DATA TRENDS SUMMARY
2002/03 2003/04 2004/05 2005/06 2006/07 Total Amount Received 73,355 177,471 130,454 196,662 217,193 239,157 Total Spending 20,579 76,606 111,978 181,409 204,218 N/A Balance 52,776 100,865 18,476 15,253 12,975 % Spending 28% 43% 86% 92% 94%

4 CONDITIONAL GRANTS SPENDING TRENDS

5 2005/06 CONDITIONAL GRANTS RECEIVED
Appropriated R’000 Roll-overs Additional Funds Total HIV and AIDS 7,947 0,455 8,402 NSNP 53,817 2,951 11,747 68,515 Provincial Infrastructure grant 55,913 4,638 60,551 Own Infrastructure grant 73,360 6,365 79,725 191,037 14,409 217,193

6 2005/06 SPENDING ON CONDITIONAL GRANTS

7 2005/06 CONDITIONAL GRANT SPENDING

8 LEARNERS FED THROUGH Bread Menu: NSNP DURING 2005/06
District No Learners No of schools FEZILE DABI 17 941 197 LEJWELEPUTSWA 21 923 239 MOTHEO 26 317 168 THABO MOFUTSANYANA 488 XHARIEP 26 128 79 TOTAL 1171

9 2005/6 SCHOOLS FED COOKED MENU
District No Learners No of schools FEZILE DABI 34 638 50 LEJWELEPUTSWA 45 294 61 MOTHEO 38 130 49 THABO MOFUTSANYANA 3 854 5 XHARIEP 16 127 44 GRAND TOTAL 209

10 NSNP GRAND TOTAL 2005/06 Number of Learners Number of Schools
feeding of cooked meals 209 feeding of bread menu 1171 GRAND TOTAL 1380

11 LEARNER SUPPORT PROGRAMMES
Learner transport provided to farm school learners in Province. 3 more Hostels (initial 8); in Edenburg for 55 learners, Villiers for 40 and Thaba Nchu for 100 learners Feed total learners through NSNP; exceeding initial target of Provide hot meals to 21 schools in pilot project, feeding over learners

12 HIV AND AIDS PROGRAMMES
A total of 1,818 educators have been trained in Basic Counseling Skills A further 1,000 educators were trained from all schools at GET and ECD level in Life Skills and HIV and AIDS education 1,000 educators were trained in awareness programmes that include prevention, care and support at school level All School Management Teams were trained in the management of the impact of HIV and AIDS, programme extended to SGB’s ABET educators were trained in Life Skills and HIV and AIDS education

13 ADDITIONAL FUNDING R70,7 MILLION

14 MINOR REPAIRS: EPWP PROJECTS
252 schools completed, entails renovations at R31,6 million where SMME’s were utilised Further 355 schools allocated by end of February 2006 for similar project at R39,1 million 22 farm schools refurbishment with unsafe structures utilising mobile classrooms Letsema projects completed at 90 schools to repair broken windows, painting of ceilings and walls etc.

15 TRANSFER PAYMENTS TO SCHOOLS
Funds transferred to schools for renovations were executed through a selected process and training was given before payments were made into their banking accounts Teams were set up in order to monitor and manage individual school projects Teams consist of the School Governing Bodies and the principal plays a critical role. District teams assisted schools in their respective districts, lead by the Physical Planners and at Head Office level, a Project Manager was appointed to co-ordinate the above.

16 ACTUAL SPENDING ON CAPEX AS 31 MARCH 2006
Description 2005/06 Allocation R’000 Spending as at 31 March 2006 % Spending Capital transfers 213,683 210,583 99% Buildings and fixed structures 56,799 39,998 70% Machinery and equipment 27,708 23,116 83% Total 298,190 273,697 92%

17 TRANSFER OF FUNDS FROM EDUCATION TO PWR&T
Funds for capital projects implemented by Public Works were transferred as per the agreements between the two departments A total amount of R106,942 million was made available to Education and subsequently transferred to the Department of Public Works to speed up capital projects As at 31 March 2006 an amount of R95,634,845 was spent This amount includes R8,956,713which is for retentions and guarantees to contractors. An amount of R10,827,271 was brought forward to the current financial year, being funds already committed

18 SERVICE LEVEL AGREEMENT
The existing Service Level Agreement makes provision for the Department of Public Works to execute all Capital projects, whilst the Department of Education is responsible for the implementation of Minor Capital Projects (renovations) and day-to-day maintenance The Department of Education remains responsible for funds transferred to the Department of Public Works Meetings between the two departments take place on monthly. These meetings are attended by Senior Managers from both departments The Service level Agreement is in the process of revision to make provision that the Department of Public Works will also take responsibility for the implementation of the latter

19 PROGRESS ON CAPITAL PROJECTS IN 2005/06
Completed 6 new schools: Tawana JJ Kubheka Disasterpark SS Paki Louriepark ( completed April 2006) Tumisang (Completed April 2006) And good progress on others: JC Motumi (Kutlwanong) Kgotso- Uxolo(Reitz) Commenced with construction of 2 new schools: Dr. Mgoma- January 2006 (Welkom) EE Monesa – January 2006 (Senekal) Commenced with construction of Additional facilities at: Mmabana P/S- Jan 2006 AND finalised: PPP feasibility study completed for construction of 13 new schools to eliminate platooning schools by 2008/09

20 OVER / UNDER SPENDING It is important to note that according to MINMEC figures, only 74% was spent on Capex. This figure was disputed in that meeting and the correct figure is 90% of our budget The main reason for not spending all the funds is due to the heavy rains in the Province since January 2006 The Department of Public Works promised that the outstanding amount will be spent by June on the projects affected by rain

21 OVER / UNDER SPENDING AND CAPACITY CONSTRAINTS
The only areas of under expenditure are located in the implementation of small capital projects, day-to-day maintenance and the Letsema Project due to capacity constraints of implementers of projects . Improved planning – projects were approved prior to the commencement of the 2006/07 financial year to ensure more efficiency in 2006/07 Improving staffing levels by appointing additional technical staff to monitor progress on site

22 MONITORING CAPACITY AND PLANNING
Capital and Expenditure trends throughout the Department are now monitored by a dedicated Directorate one Management Accountant is dedicated to this assignment . Monthly reconciliation on BAS Expenditure reports are done to track expenditure against each project Monthly in-house monitoring meetings are now held to provide early warning to all Managers. The relevant Directorate must now report at the Quarterly Review meetings of its remedial measures on under/over expenditure. Regular monitoring meetings with Department of Public Works, Roads and Transport are held to monitor progress on major capital works. The full implementation of the Infrastructure Development Programme will also assist to ensure projects are effectively executed. (IDIP) National Treasury is also assisting with the Technical Assistant to support both Education and Department of Public Works, Roads and transport The Planning of Projects is also improved to ensure the projects start on time and are timeously completed. Business Plans for the 2006/07 have been submitted on time to PWR&T for the current financial year according to the Division of Revenue Act.

23 INFRASTRUCTURE ACTION PLAN 2006/07

24 INFRASTRUCTURE ACTION PLAN 2006/07 (CONTINUED)

25 2006/07 INFRASTRUCTURE DELIVERY IMPROVEMENT PROGRAMME
Align the Budget Process ; Strategic Planning Process and the multi-year Infrastructure Plans Regular Monitoring of infrastructure projects Keeping accurate expenditure and commitment register for the Capital Budget Transferred to PWR&T Regular Management meetings with PWR&T