1 EYETS planning A.Tauro

2 EYETS planning meeting, 2 Dec 2016 - A.Tauro
EYETS general info EYETS duration: from 5 Dec to 30 Apr, 21 weeks beam to beam (w49 to w17) LHC back to BE-OP on Friday 14th April (powering tests) LHC closed Beam 21 weeks EYETS planning meeting, 2 Dec A.Tauro

3 LHC-EYETS: linear schedule InWork
EYETS planning meeting, 2 Dec A.Tauro

4 EYETS planning meeting, 2 Dec 2016 - A.Tauro
Main activities Replacement cavern lift Replacement L3 PC thyristors Install cable trays (EN-EA-CT) and LS2 fiber prototypes (EN-EL-CF) Open L3 doors Detectors: Replace TOF TDC boards, displace 12 modules Repair broken TRD optical connections Reprogramming firmware of PHOS trigger units, open one module (LV connection issue). PHOS warmed up mid December, until mid March Replace FECs on EMCAL and DCAL, shift SRUs Cryo-regeneration TRD Xe (start 9 January) Switch TPC gas to Ne (March). Replace broken FEC EYETS planning meeting, 2 Dec A.Tauro

5 EYETS planning meeting, 2 Dec 2016 - A.Tauro
W49-50 (5 Dec to 18 Dec) W49: Beam stopped at 6:00 AM  ramp down both magnets (SL) RP survey: Uli Fuchs between 8:00 and 9:00 ALTEAD: remove shielding (PX24, UX25) Reinstall crane electronics, remove stabilizers, bring nacelles down Weld valve on N2 pipe (SG2) on Mon  stop N2 dewar (batteries) TE-VSC: close manual valve on Mon 9:00 Mon: inspection for cable-trays work (Gianluca Canale + EL) Confined space training session on Tue , 14:00 – 17:00 TPC (Chilo): remove wood GEM IROC EN-MME: remove accelerometers cables and instruments (tbc) Visitor centre: test ventilation control – whole week Wed 17:30, 2 private visits Thu 14:40, protocol visit “CH FR Signature tripartite”– passage via PX24 Fri 17:30, 2 private visits W50: ALTEAD+P2tech: open L3 doors Remove L3 and PMD ventilation, lift PMD crocus Wed 8:00 – 10:00: CR lift maintenance – possible? UX25 access after working hours (17:30 onwards) No access CR5 Mon-Tue w49 EYETS planning meeting, 2 Dec A.Tauro

6 EYETS planning meeting, 2 Dec 2016 - A.Tauro
W51-1 (19 Dec to 8 Jan) EN-HE: PX24 lift replacement UX25 access via PM25 Rescue mask training required to access PM25 (and UX25) from 19 Dec to 4 Jan CERN closure: 22 Dec - 4 Jan  no access P2 Daily tours surface and underground Safety test: 30 Dec  no access UX25 W51: Mon: request PX24  PM25 switchover (Klaus) Mon: inspection survey (beampipe, PHOS) Inspection TOF supports (Yannick) Wed: restore normal access to CR (no longer from outside) Lift replacement schedule EYETS planning meeting, 2 Dec A.Tauro

7 Inspection rounds during CERN closure
As every year a daily inspection will done at P2 during CERN End of Year closure (22.12 – 04.01) Thanks to all people listed below! Inspection of SX2 (ARC), CRs, SG and Cavern Remote monitoring of infrastructure and equipment remains possible (DCS is available) Contact Andre if there is anything special you want to be checked Provisional schedule: Thu 22-Dec Klaus Fri 23-Dec Klaus Sat 24-Dec Klaus Sun 25-Dec Sasha Mon 26-Dec Sasha Tue 27-Dec Chilo Wed 28-Dec Chilo Thu 29-Dec Arturo Fri 30-Dec Arturo (safety tests) Sat 31-Dec Andre Sun 01-Jan Andre Mon 02-Jan Arturo Tue 03-Jan Andre Wed 04-Jan Andre EYETS planning meeting, 2 Dec A.Tauro

8 EL, CV and gas activities
Test secours: 9 Jan between 6:00-6:30 AM – see next slide Test auto-transfer: 4 Feb (10’ interruption on general services) AUG: Mar 16th – NO ACCESS P2 whole day Put SLIMOS+DCS console on DCS-UPS after power cut of 18.9 (Andre) SPIE: Cable trays for LS2 fibers (lights, SU support to be displaced) Pull 2 spare cables + connectors for SSD (CR4-UX) (Caterina Deplano) Pull 2 cables MCR  ARC (Pascal Blanc) Pull 2 cables CV-DC (Yann Lupkins) Redo test on TPC HV cables, redo connectors if needed (11 January) All the requests to pull long cables in the cavern during the EYETS (e.g. from CR4/surface to the cavern) must be submitted before Friday 2nd December, 2016 (today) Cooling: P2 cooling maintenance: w Stop towers w11 Detector cooling maintenance: w10-11 – see next slide EN-CV: install heat exchanger ITS air duct (C-side) SPIE: re-routing mixed water pipes (racks) side C (Philippe) Gas: EP-DT-FS: upgrades to the Gas system WinccOA. 1 day in weeks 5-6 Maintenance gas systems – see excel file EYETS planning meeting, 2 Dec A.Tauro

9 EYETS planning meeting, 2 Dec 2016 - A.Tauro
EN-EL: test secours Planned for Monday, 9th Jan, at 6:00 AM (10’) For P2 this will affect: all buildings including SX2 and SXL2 all offices, meeting rooms, wall outlets, light, coffee machine the non UPS part of the ARC the non UPS part of the detector cooling plants (this will trigger interlocks, e.g. LV) the gas systems (PLCs stopped, interlocks triggered)  Albin to stop gas systems beforehand the circulation of iced and mixed water, ventilation (will restart after the 10 min. interruption) Are NOT affected at P2: all equipment on UPS (notably all CRs and inside ARC) all racks in CR and UX As we do not know if all ventilation will restart OK, we will suspend cavern access until we confirm that all is nominal EYETS planning meeting, 2 Dec A.Tauro

10 EYETS planning meeting, 2 Dec 2016 - A.Tauro
Detector cooling RP samples collected on Dec 5th EYETS planning meeting, 2 Dec A.Tauro

11 EYETS planning meeting, 2 Dec 2016 - A.Tauro
Gas (EN-EA-CT) Stop Ic4h10 and CH4 on 5th Dec (stop  purge  P test/leak test of lines with N2) Switch Arcal15Arcal10 on 19th Dec Note: gas point facing b.2270 will be full of bottles. These bottles will be removed: 1BT N2 (14/03/2014, Marraffa) 2BT Arcal21 (15/03/2012) 2BT Arcal5 1BT N2/CO2/Ne 4.80/9.50/85.7  keep! 1BT Acetylene EYETS planning meeting, 2 Dec A.Tauro

12 Gas system status during EYETS
Run supply Backup Comment MCH 61 ST1 ON Ar-CO2 CO2 Switch to N2 on Dec.19th, and back to Ar-CO2 on Jan 9th Nominal mixture (Ar-CO2) during rest of EYETS  MCH 61 ST2 MCH 62 ST3-4-5 MTR OFF C2H2F4-iC4H10-SF6 Outlet chambers to atmp. Stop on Dec 5th PMD Stop on Dec 5th   CPV N2 HMPID CH4 Flushing by Argon HMPID envelope N2 manual supply PHOS TOF C2H2F4-SF6 C2H2F4  Backup TRD Xe-CO2 Freeze the Xe in January and put it back around March  TPC Fill the TPC with Ne-CO2-N2 in March  TPC envelope CO2 Bronkhorst supply EYETS planning meeting, 2 Dec A.Tauro

13 EYETS planning meeting, 2 Dec 2016 - A.Tauro
Other activities DSO test: 7 and 8 April  NO access underground DCS: Netgear ethernet redundancy (Andre) TE-EPC: Replace thyristors L3 power converter (planning tbc) Replace coils of the Thyristor Controlled Reactance (TCR) of LHC Static Var Compensator (w3-4). Acoustic noise test one night in w11 (tbc) HSE-RP-IL: annual source tests of all RAMSES on Jan 11th BE-ICS-AC: maintenance PX24 access door. 26 and 27 Jan BE-ICS-AS: Maintenance gas and ODH detection in UX25, SG2, SD2 and PX24. Will stop flammable gases for ½ day. 22 and 23 February Maintenance red phones. 20 Dec Maintenance rack smoke detection. w6 EN-ACE-SU: Measure the RB24 beampipe flanges (at least F0-F1). 2 to 5 days in w2 or 3 Survey PHOS ALTEAD: maintenance CR1-4 drawbridges (January) UX25 floor painting: I-side w4 and O-side w5 (access via C/4 during I-side painting) EYETS planning meeting, 2 Dec A.Tauro

14 EYETS planning meeting, 2 Dec 2016 - A.Tauro
Other activities Fire Brigade Visit and Exercise. 13 and 17 Mar EYETS planning meeting, 2 Dec A.Tauro

15 Access & services status Red = no access, Orange = access restrictions
AUG LHC1, access after 12:00 Cavern closing Cavern opening DSO Test auto transfer Cooling plants maintenance w10-11 Test secours Acoustic noise measurement (date tbc) S12 warm-up, access with self-breathing mask training CV maintenance w (no cooling at all in w11) AUG Safety test EYETS planning meeting, 2 Dec A.Tauro

16 EYETS planning meeting, 2 Dec 2016 - A.Tauro
DAQ, DCS DAQ: Shutdown of CR1/ARC (excepted the DCS stations) on the last working week (Tue20-Wed 21 Dec 2016) Logbook will move to CERN 1 and remain available all the time (with some small pauses around the two moves) Restart of CR1/ARC on Mon 9/Tue 10 Jan 2017 DCS: Short term Monday 5-December 09:00: backup of all WinCC projects Reference ‘snapshot’ of the systems at end of 2016 run Expected down time ~ 2hrs DCS available uninterrupted until end January Usual support during working hours ‘Best effort’ outside working hours and during CERN closure Further activities Install new fileservers End January (~1 day) Upgrade WinCC (v 3.15), Windows/Linux patches, etc. Date to be decided (not before end January), ~2 days DCS shutdown for emergency stop test (16 March) EYETS planning meeting, 2 Dec A.Tauro

17 EYETS planning meeting, 2 Dec 2016 - A.Tauro
Underground visits From 5 Dec to 18 Dec (2 weeks) After working hours (17:30 onwards) From 19 Dec to 24 Feb (10 weeks) NO visits (lift replacement) From 25 Feb to 2 April (5 weeks) Private visits allowed From 3 Apr to 13 April (2 weeks) From 14 Apr to 27 April (2 weeks) EYETS planning meeting, 2 Dec A.Tauro

18 EYETS planning meeting, 2 Dec 2016 - A.Tauro
Backup EYETS planning meeting, 2 Dec A.Tauro

19 Opening/closing L3 doors
Usual access restrictions during opening/closing Closing Opening Maintenance UX25 crane: 4 to 6 Jan EYETS planning meeting, 2 Dec A.Tauro

20 EYETS planning meeting, 2 Dec 2016 - A.Tauro
PX24 lift replacement 10 weeks, from 19 Dec to 24 Feb ALICE personnel via PM25 (transparent) From 12 Dec to 4 Jan: S12 warm-up between K (risk of helium spill)  access only for those with rescue mask training S12 cool-down (300-80K) w8-9-10 EYETS planning meeting, 2 Dec A.Tauro

21 EYETS planning meeting, 2 Dec 2016 - A.Tauro
UX25 floor painting Resin Access via C/4 during I-side painting O-side O-side I-side I-side Cavern entrance EYETS planning meeting, 2 Dec A.Tauro

22 Replacement L3 converter thyristors (TE-EPC)
36 thyristors in operation, dating from LEP times Many of them have ‘bad contact’ L3 magnet tripped several times over the last months Replacement of all thyristors foreseen in EYETS: Finding compatible thyristors on the market (obsolete reference) Purchasing them (approximate budget: 50kCHF) Upgrading firing electronics for compatibility with new thyristors Bridge output voltage measurement Thryistor bridge 1x thyristor pulse missing [3.3ms]

23 LHC Point 2 SVC : installation of new TCR coils (1)
EYETS planning meeting, 2 Dec A.Tauro Purpose Reduce the acoustic noise by exchanging the coils of the Thyristor Controlled Reactance (TCR) of LHC Static Var Compensator in Point 2 by new special low-noise coils Requested by CERN Top Management 2275 2260 2265 LHC POINT2 TCR Coils

24 LHC Point 2 SVC : installation of new TCR coils (2)
EYETS planning meeting, 2 Dec A.Tauro Schedule proposed Switch-off: (date to be checked concerning Alice and TI2) W49-W : Dismantling of the coils W3-W : Installation of the new coils W5-W : Tests and commissioning (adaptation of the control system, first energization and powering tests)  W7 2017: Acoustic noise measurements (one night)  new date: W10 (8-9/3) Switch-on: probably in W7, and latest before 28 Febr. 2017 Safety Delimited worksite area without any coactivity (VIC already done) Consequences AC network quality deviation during this period (no more reactive power and harmonics compensation) Impacted systems: No powering test possible for ALICE experiment and TI2