1 RSOC Overview at SWT #26, 11/12 June 2009
Kristin Wirth for the RSOC team RSOC team and tasks Planning software Payload constraints User Manual review status Comet phase preparation

2 RSOC team and tasks Work package lead persons:
Mike (support Claire): Active / Passive Payload Checkouts, interference Juan (support Michael): Earth Swingby 3 Michael: Lutetia Flyby Viney: Systems engineering, EDF modelling Claire, Michael: Baseline planning for comet phase Michael, Viney: Science Operations and Data Handling concept for comet phase Maud: Archiving Jose: SPICE Bernhard: Interface software, GDP Experiment interface persons: Mike: CONSERT, PHILAE  Viney: OSIRIS, RSI Juan: COSIMA, MIDAS, GIADA  Michael: VIRTIS, ROSINA Claire: ALICE, RPC  Kristin: MIRO, SREM

3 Planning Software (1) CVS (Concurrent Versioning System):
Detailed information for configuration has been sent to PI teams. PI teams should set up CVS now that ITL iteration for Active PC10 / ESB3 starts. CVS use will simplify ITL iteration between PI teams and RSOC. Used by RSOC to distribute and archive all planning files and software. PI teams have read access to: All scenario planning files related to EPS (and MAPPS), i.e. OIOR, LOR, POR, top-level ITLs, EVF, EPS output files. EDFs for telecommands, telecommand sequences and modelling. EPS configuration files. EPS and MAPPS software. EDF modelling: EDFs need many updates. Improvements will be made to support ITL development for Active PC10 / ESB3.

4 Planning Software (2) MAPPS (Mapping and Planning Payload Science):
MAPPS computes and visualises geometry as map projection and parameter plots. MAPPS performs timeline visualisation of ITLs. MAPPS for MSB, ESB2/3 and Steins have been distributed to PI teams. Please provide feedback on usefulness! MAPPS for cruise phase (timeline visualisation only) is used by RSOC internally for Active PC10/12. MAPPS for Lutetia is in preparation. An improved MAPPS version (for Rosetta some bug fixes only) is being tested. PTB (Project Test Bed): PTB computes and visualises geometry as 3D graphics. PTB generates data packages and events. PTB is used by RSOC internally to support the remaining cruise phase scenarios. Validation is complete.

5 Payload Constraints FOP Volume 2 Annex 11 contains all attitude constraints related to spacecraft and payload safety. Update planned for September 2009. Rosetta Constraints Summary and Implementation, RO-SGS-TN-0015, in addition contains all other geometry and operations constraints for payload, e.g. constraints related to science degradation and interference. Updated version 1/c of document after iteration with PI teams will be released soon. Formal inputs for both documents are the Rosetta UM and experiment UMs. Updated constraints that are not yet reflected in experiment UMs, are marked “pending formal submission”. Please provide updated experiment UM to confirm updated constraints! Checking of geometry constraints is done manually during cruise phase. Implementation in planning tools will be done for comet phase.

6 UM Review - Status June 2009 Instrument
Updated User Manual at ESA (or confirmation that none needed)? User Manual reviewed by ESA? ALICE Sent a version 2.0 with an indication that another version may come. Waiting for update. CONSERT Work on second update in progress. Delivery after TM definition modification in RSDB (2008). COSIMA Sent a version 3.5 (05 Jun 2009). Review by ESA pending. GIADA Sent a version 4.0 (29 Sep 2006). Review done at ESA, back with (minor) comments to GIADA beginning Mar 2007, finally closed Jul TBC. MIDAS Second update planned for Jan Still pending. MIRO Sent a version 4.4 (01 Apr 2009). RSOC final cross-check pending. OSIRIS Only version 1/- (30 Apr 2002) available. Outdated before delta EFOR process started. Waiting for revised version to start review. PHILAE Second update pending. ROSINA Second update planned for early Still pending. List sent out 31 Aug 2006, waiting for update. RPC Second update sent 06 Sep 2007. RSI List sent out 31 Mar 2006, waiting for update. SREM No. No update expected. VIRTIS Only version 2/- (10 May 2002) available. Waiting for first version or confirmation that we can use what we have.

7 Comet Phase Preparation
Baseline planning: PI teams contribute through the Science Working Groups. Work must be intensified. Science themes are almost complete, table is being cleaned up. Prototype of science themes database is available. Work on test case has started. Top-level operations requests for all observations (e.g. geometry criteria, pointing, duration, data volume and power) shall be collected by end 2009. A baseline plan for the escort phase shall be developed by end 2010 considering the scenario options presented by FDyn. Science Operations and Data Handling concept: RSOC has completed the top-level planning concept for the escort phase. User requirements for planning software will be derived in the 2nd half of 2009. Comet modelling: Implementation of ISSI science models at ESAC.