1 ELCITA UPDATE February 2017

2 Estate Management E – Toilets
18 e-toilets operational. 2 More E- Toilet Installation Work in Progress Estate survey Final Data check & Software Training work in Progress

3 Modification of Existing street light pole foundation with new concealed Cable routing.
West Avenue 8 (Pump House Road)

4 KSSIDC Complex Internal Road
Road Works – Under Progress KSSIDC Complex Internal Road

5 Drain Works – Under Progress
West Avenue-9 (Petrol Bunk Road) West Avenue-8 (Police Station Side)

6 Drain Works – Completed
Concrete Drain at Pumphouse Shoulder Drains along West Avenue 10 (Fire Station Road)

7 Footpath Works – Under Progress
Footpath works near Erkadi Systems – West Avenue 2 Pavers Laying Work along West Lane 1 (Opp HCL)

8 Footpath Works – Under Progress
Footpath Work along East Avenue 1 (TCS Road) Footpath Work along East Avenue 4 (Shanthipura Road)

9 Fabrication Work – Under Progress
Providing MS Railing for pedestrian safety – West Avenue 1 (Infosys Avenue)

10 Steel shed for 15 HP pump & Chain link Fencing for Tank at Pump House
Fabrication Work – Completed Steel shed for 15 HP pump & Chain link Fencing for Tank at Pump House

11 Chain-link fencing for Siemens RMU Yard
Fabrication Work – Completed Chain-link fencing for Siemens RMU Yard

12 Improvement work– Completed
Replacing old Chambers with New Chequered sheet (Tata Power) Footpath work (Lord Plaza)

13 Footpath Works – Under Progress
Barbed Wire Fencing Opp Tech Mahindra Road Drain slab raising work - East Lane 1 (Hical Road)

14 Fixing Led Display – Completed
HP Entrance Median (West Phase) Median Opp XIME College (East Phase)

15 Estate Management Contract Awarded
Providing and laying of Asphalting using 60/70 grade bitumen along Café Corner & JP IT Park Road

16 Estate Management TENDER PUBLISHED
Providing and laying of Asphalting using 60/70 grade bitumen from Edizi Tools to TCS gate no 3 via Y- Junction, .(East Avenue 1& 4) Electronics City East Phase, Bangalore Proposed construction of Drains, laying of Pavers, Kerb stones and Drain cover slabs from Xime Jn to Tata power rear gate & TCS Gate no 2 to Edizi Tools Jn (East Avenue 2 & 4), Electronics City East Phase, Bangalore

17 Estate Management Contracts on Anvil
Providing House Keeping Services to ELCITA within Ecity Industrial Area. Construction of Concrete Drains, laying of Pavers, Kerb stones and Drain cover slabs Erkadi System to Arvind Mills (West Phase) Construction of 500 KLD STP in KIADB Land, Electronics City East Phase.