1
San Mateo – Foster City School District
College Elementary School – Turnbull Child Development Center Modernization and New Construction Presentation to the San Mateo High School District August 27, 2010
2
Site Committees Members Schematic Design Overview Project Schedule
Presentation Items Background Project Description Meeting Dates Site Committees Members Schematic Design Overview Project Schedule Next Steps
3
1. Background The current College Park Elementary School/Turnbull Child Development Center facility was built in 1949 as a middle school, and was converted over the years to accommodate various needs The existing school offers special Mandarin Immersion and Mandarin Pre-school programs, Gate Classes and it is expected to increase in enrolment The entire property includes a little over 11 acres, and the two facilities use approximately 7 of the 11 acres The campus consists of 4 main wings in need of a comprehensive modernization The LGI is large for the existing elementary school because it was originally built for a middle school A portable 6-plex built prior to 1990, a portable 3-plex which previously housed Boys and Girls Club and the District’s Counseling center are in poor condition and need to be demolished The Child Development Center is housed in 7 portables without interior restrooms Student safety issues exist due to the District’s current bus pick-up area on Poplar Street. These issues may only increase with the projected student population growth.
4
2. Project Description: College Park Elementary School
Modernization upgrades to all permanent classrooms, library, LGI and other ancillary spaces Demolition and removal of 6-plex, a portable 3-plex (previously housed the Boys and Girls Club), and the District’s Counseling Center Modernization and expansion of existing kitchen to meet latest Health Department requirements Modernization and building new student and staff restrooms to address ADA and Title 24 requirements Construction of the following: 4 Kindergarten classrooms (5100 SF) New Administration Building (1,600 SF) Additional 15 parking spaces in northern part of campus Construction of a new central school area/plaza with lunch shelters and amphitheater type set-up New separate playground for kindergarten Underground utilities will be upgraded as required
5
Demolition and removal of existing 7 portables
2. Project Description: Turnbull Child Development Center Demolition and removal of existing 7 portables Relocation of existing administration building to a new permanent location Construction of 13 pre-engineered classroom buildings, which meet state licensing requirements (16,840 SF) Two (2) of these classrooms will be for pre-school Special Education students Construction of new playground with installation of existing play structure Addition of multiuse classroom (relocated from Fiesta Gardens) The project would add a net area of 8,200 SF to Turnbull Child Center to accommodate for projected program growth
6
Demolition and removal of existing 2 portables
2. Project Description: District Counseling and Bus Drop Off Demolition and removal of existing 2 portables Modernization and conversion of old administration area to counseling center New bus lane/ drop off and shelter on El Dorado Street
7
2. Project Description Site Committee Members: Include parents, teachers, site principal, site staff, district administration and architects. Diana Hallock College Park School Principal Adesola Seligman College Park Teacher Brenda Macias College Park Teacher Chetan Patwardhan College Park Parent Cheryl Shrewsbury Turnbull Child Development Center Principal Jocelyn Gonzalez Turnbull Child Center Parent Bernardo Marquez Turnbull Child Center Parent Micaela Ochoa District Staff – Chief Business Official Al Solis/Terry Macias District Staff – Director of Facilities Carlos Ortiz District Staff – Former Director of M&O Alex Kristal District Staff – Project Manager Thang Do Aedis Architects – President Joe Vela Aedis Architects – Associate Principal Wendy Woo Aedis Architects – Project Architect
8
2. Project Description Meeting Dates – The site committee has been meeting for the past eight (8) months as follows: October 28, 2008 – PTA Presentation February 5, Project kick off April 6, 2009 – Site Committee kick off April 28, Site Committee May 11, Site Committee June 10, 2009 –Project Scope, Budget and Schedule Development June 18, Project Scope, Budget and Schedule Development June 22, Project Scope, Budget and Schedule Development July 30, Project Scope, Budget and Schedule Development August 31, 2009 – Site Committee September 21, 2009 – Site Committee October 1, 2009 – Turnbull Staff October 7, Site Committee December 14, Site Committee January 14, Site Committee January 21, 2009 – College Park Users Group March 8, Site Committee Meeting March 9, 2009 – Turnbull Users Group Meeting March 18, 2010 – Site Committee Schematic Design Meeting April 29, 2010 – Presentation to HA NCSM, Project Highlights, Schedule August 27, 2010 – Presentation to the Principal SM High School , Project Highlights, Schedule
9
3. Schematic Design
10
4. Timeline
11
Bid for pre-engineered buildings was opened and approved by the BOT:
5. Next Steps Bid for pre-engineered buildings was opened and approved by the BOT: July 15, 2010 Start of construction March 2011 (construction duration is 24 month) Planned move-in will be phased Complete move-in expected in March 2013