Presentation is loading. Please wait.

Presentation is loading. Please wait.

System Modeling Discussion

Similar presentations


Presentation on theme: "System Modeling Discussion"— Presentation transcript:

1 System Modeling Discussion
(Open Discussion for WECC SRWG) By: Ben Hutchins

2 Intro Quote [We intend] to be candid about [our] errors; for as a wise man once said: "An error does not become a mistake until you refuse to correct it." We intend to accept full responsibility for our errors; and we expect you to point them out when we miss them. -John F Kennedy

3 Discussion Items Short Circuit Model Verification kV Base Issues
Base kV Differences Operational Voltage Range Equipment Modeling Buses Shunt Sizes Line Ratings Line Impedances Conclusion

4 Short Circuit Model Verification
Current Communication Structure: -N Interconnected Entities must communicate. 2 Entities: 2 Requests, 2 Responses 3 Entities: 6 Requests, 6 Responses 4 Entities: 12 Requests, 12 Responses 5 Entities: 20 Requests, 20 Responses … 2*N(N-1) s!

5 Short Circuit Model Verification
MOD has requirements for Short Circuit Modeling Data

6 Short Circuit Model Verification
Motion Once per year, WECC will request, from all utilities, their Short Circuit Models for the current system, in their native format. WECC will ZIP the files into a single package, and post in the same location as WECC Base Cases. First Request: Friday April 14th, 2017 Due Date: Friday June 2nd, 2017

7 Base kV Differences 525kV Base NV Energy’s Equipment Nameplates
NV Energy’s System Protection Group NV Energy’s Transmission Operations 500kV Base WECC PeakRC (West-Wide System Model, WSM)

8 Operational Voltage Range
For NV Energy: Nominal “Target”: 525kV Normal: kV Emergency: kV WECC-CRT-003: If interpreted using PSLF kV Bases, 500kV ± 5%  kV 500kV ± 10%  kV

9 Buses 500kV System: Not Operated at 500kV PSLF ±5% for most reports (475kV-525kV)

10 Shunts Example Nameplate, provides rated kV Remember: MVAR Output ∝ V²

11 Shunts – 100MVAR @ 525kV Example
Shunt Reactor Common Mistake: Entered in PSLF as B=1.00 This is wrong! At 500kV (PSLF’s Base), this reactor will only output (500/525)^2 * 100 = 90.7MVAR! Error could occur if “borrowing” impedances from a System Protection Case

12 Shunts – 100MVAR @ 525kV Example
Shunt Reactor

13 Shunts – 100MVAR @ 525kV Example
Test Reports: Applied Voltage, Resulting Current

14 Shunts – 100MVAR @ 525kV Example

15 Shunts – 100MVAR @ 525kV Example
Example calculation:

16 Shunts – 100MVAR @ 525kV Example
SCADA Measured Output: = kV Model B= (From Test Report) Calculated Output: * 100 * ( / 500) ^2 = MVAR ~1% Difference from SCADA Measurement. Not too bad!

17 Line Ratings Line Ratings: Two Limitations 1) How much heat before annealing? 2) How much heat before sag below clearance? I²R  Heat  Sag & Annealing Current drives temperature. Equipment is Temperature Limited. PSLF takes MVA ratings, but converts (using the Bus kV Base) to Amps for comparison.

18 Line Ratings Common mistake: Maintaining ratings in MVA, without a kV Base Specified. Example: If Operations uses a 525kV base, but Planning uses a 500kV base, your Amp ratings should the same, and your MVA ratings should differ! Planning: 500kV  1732 MVA Operations: 525kV  1819 MVA

19 Line Impedances Driven by three things: 1) Relative Phase Positions 2) Conductor 3) Length

20 Line Impedances AspenLC can produce R, X, B per-mile To convert from Ω to PU, divide by Zbase: 𝑍 𝐵𝑎𝑠𝑒 = 𝑘 𝑉 𝐵𝑎𝑠𝑒 2 𝑀𝑉 𝐴 𝐵𝑎𝑠𝑒

21 Line Impedances Common mistake: “Borrowing” impedances from a different model, which does not have the same base. Potential error: kV² 500kV vs 525kV Bases means up to 10% Error

22 Conclusion Motion for a WECC Short Circuit Data Request 500kV vs 525kV Base Issues: Potential for not catching low-voltages (488kV) for manual studies in PSLF. Potential for data entry mistakes: -Shunts: 10% -Line Ratings: 5% -Line Impedances: 10% Possibility to use 525kV Base in the future? -Automatic conversion routine?


Download ppt "System Modeling Discussion"

Similar presentations


Ads by Google