Introducing pdri for mega projects As a Planning quality Control tool

Similar presentations


Presentation on theme: "Introducing pdri for mega projects As a Planning quality Control tool"— Presentation transcript:

1 Introducing pdri for mega projects As a Planning quality Control tool
Construction Projects Network Engineer Abdel-Halim Mahmoud CEO Certified PDRI Facilitator, Projects Planning Control, Arizona State University, USA Certified Project Assessment Associate, Construction Industry Institute, Texas University Evaluators Board Member, Baldrige Performance Excellence Award, MN, USA Master Examiner, USA National Quality Award, American Healthcare Association Certified Teams & Quality Trainer, USA Agency for Healthcare Research and Quality

2 PDRI tool – The Definition
An Acronym Project Definition Rating Index An Index Score along a continuum representing the level of scope definition A Risk Management Tool A FRONT END Planning Quality Control Tool

3 PDRI IS A Front end Planning for Performing the right project.
Scoping the right “things” for a good design basis. Setting the stage for successful execution. Documenting the scope of work into an organized basis for design.

4 Projects life cycle phases
Execute Project Procurement Construct Design Start-up Close-out Effort Front End Planning Operations Operate Facility

5 Potential PDRI Application Points
when to conduct pdri session Potential PDRI Application Points 1 2 2i 3 Design and Construction Detailed Scope 2 3 1 Feasibility Concept

6 PDRI Assessment Session Goals
A thorough vetting of the team’s planning efforts to date Discovery learning (outside of each individual’s area) leading to better team alignment Generation of a good ‘planning gaps’ list to facilitate future action Better understanding of project team issues and partners (team building) Development of a Rating Index score, which is indicative of planning progress 

7 PDRI Scoring Session Participants
Project sponsor(s) Project engineer or designer Key discipline leads Technical representatives User representative(s) Design/builder or construction manager PDRI facilitator

8 Available PDRI Tools Industrial PDRI Building PDRI Infrastructure PDRI

9 REVIEWING THE Project Execution PlanS
Permitting Plan Safety Plan Quality Plan Control Estimate Schedule Materials Management Labor Management Plan Project Controls Plan Start-up Plan Change Management Plan Project Execution Plan

10 PDRI – Infrastructure Projects Score Sheet Contents
Section I: Basis of Project Decision Five categories, 23 elements “Right project” Section II: Basis of Design Four categories, 23 elements “Right product” Section III: Execution Approach Four categories, 22 elements “Right way”

11 Tool Format PDRI– Infrastructure Projects
The crucial elements that need to be included in a scope definition for infrastructure projects. Composition: 3 Sections 13 Categories 68 Elements 69 pages of detailed element descriptions; Rate each of the 68 elements to obtain a project score of up to 1000 points—the lower the better.

12 Weighted Score Sheet (Example)
Definition Levels 0 = Not Applicable 2 = Minor Deficiencies 4 = Major Deficiencies 1 = Complete Definition 3 = Some Deficiencies 5 = Incomplete or Poor Definition

13 next steps Facilitating FREE PDRI assessment session ($ Value) for a project Assessing organization needs to implement PDRI Practices PDRI Implementation Plan & Goals PDRI Training Product Champions PDRI Implementation Measure Results

14 Free Collaboration Platform Offerings
from Construction Projects Network Free Construction Best Practices Library & Training Courses. Free Collaboration System for Supply Chain Team Members. Helping you build Community uses SHARED resources (HR & Equipment)

15 Engineer Abdel-Halim Mahmoud
Thank you Engineer Abdel-Halim Mahmoud CEO Construction Projects Network Mobile: