Download presentation
Presentation is loading. Please wait.
Published byLeslie Kelley Modified over 7 years ago
1
PERT CPM assumes duration of activity is known with certainty.
PERT assumes duration of activity as a random variable. For an activity, PERT estimates three quantities: a : optimistic duration under most favorable condition b : pessimistic duration under least favorable condition m : most likely value for activity’s duration
2
Probabilistic Estimates
Activity start Optimistic time Most likely time (mode) Pessimistic time to tp tm te
3
Let Tij be the duration of activity (i,j)
Let Tij be the duration of activity (i,j). PERT assumes that Tij follows a beta distribution and, mean and variance of Tij may be approximated by : expected duration of activities on any path : variance of duration of activities on any path
4
Example variance of PROJECT = variance of CRITICAL PATH
if more than one critical path, PROJECT VARIANCE=largest of CRITICAL Example Activity a b m (1,2) 5 13 9 (1,3) 2 10 6 (3,5) 3 8 (3,4) 1 7 (4,5) 12 (5,6) 15
5
Project Diagram
7
Specified time – Path mean Path standard deviation
critical path = B-D-E-F. Thus, E(CP) = = 38 var(CP) = = 7.22 standard deviation for CP is (7.22)1/2=2.69 What is the chance of completing project within 35 days ? there is a 13% chance of completing project within 35 days. Z = Specified time – Path mean Path standard deviation Z indicates how many s.d the specified time is beyond the expected path duration.
8
PERT Example activity duration predecessor te A 2 / 3 / 6 weeks - 3.33
B 3 / 6 / 10 weeks A 6.17 C 1 / 1 / 2 week A 1.17 D 3 / 3 / 3 weeks B, C 3.00 CRITICAL PATH: A-B-D EXPECTED DURATION: = 12.5 VARIANCE: { (6-2) / 6}^2 + {(10-3) / 6}^2 + {(3-3) / 6}^2 = 1.805 STD = 1.344 e.g. if critical path expected = 9.5, and STD = 1.354 target=10 , Z = (10-9.5) / = .369 probability = .644
9
EXAMPLE
10
EXAMPLE (Cont.) Identify all paths and their estimated completion times and variances.
11
Probability of Critical Path Being Completed in 39 Weeks or Less
12
PERT Example 1 2 4 6 7 3 5 9 8 Manual Testing Dummy System Training
System Testing Orientation Position recruiting System development Equipment testing and modification Final debugging System changeover Job training Equipment installation 25
13
Example (Cont.) Time estimates (wks) Mean Time Variance
Activity a b c t s2 26
14
Example (Cont.) Activity t s2 ES EF LS LF S 1 - 2 8 0.44 0 8 1 9 1
27
15
Example (Cont.) ( ) ( ) ( ) ( ) 1 2 4 6 7 3 5 9 8
( ) ES=8, EF=8 LS=9, LF=9 ES=6, EF=9 LS=6, LF=9 ( ) ES=3, EF=5 LS=14, LF=16 ES=0, EF=3 LS=2, LF=5 ES=0, EF=6 LS=0, LF=6 ES=3, EF=7 LS=5, LF=9 ES=9, EF=13 LS=12, LF=16 LS=9, LF=16 ES=13, EF=13 LS=16 LF=16 ES=13, EF=25 LS=16 LF=25 ES=8, EF=13 LS=16 LF=21 ( ) ES=0, EF=8 LS=1, LF=9 ( ) ES=13, EF=25 LS=16 LF=25 s2 = s s s s2 79 = = weeks 28
16
. Determining Probability From Z Value s Z 0.00 0.01 … 0.09
What is the probability that project is completed within 30 weeks? s2 = weeks, s = = 2.62 weeks Z = x - m = = 1.91 P(Z < 1.91) = 2.62 s P( x < 30 weeks) = = . Z … 0.09 … m = 25 Time (weeks) x = 30 33
17
What is the probability that project will be completed within 22 weeks ?
Time (weeks) x = 22 P( x< 22 weeks) = P(Z< -1.14) = = Z = = -1.14 34
18
PERT Probability Example
A project has an expected completion time of 40 weeks, with a standard deviation of 5 weeks. What is the probability of finishing the project in 50 weeks or less? T = 40 s = 5 50 X Normal Distribution Z = - 40 5 2 . m z = 0 = 1 2.0 Standardized Normal Distribution 48
19
Obtaining the Probability
m z = 0 s Z = 1 2.0 .00 .01 .02 0.0 .50000 .50399 .50798 : .97725 .97784 .97831 2.1 .98214 .98257 .98300 Standardized Normal Probability Table (Portion) Probabilities in body 49
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.