PM08-How we went from dynamics 3.7 to nav 2015 in 4 weeks
Michelle Scott, Terso Solutions, Inc. Yvonne Steinhauser, Terso GmbH
2
Your presenters Yvonne Steinhauser Michelle Scott Accounting Manager
headshot headshot Yvonne Steinhauser Accounting Manager Terso GmbH Michelle Scott Director, Finance & Operations Terso Solutions, Inc. Who is in the room? Do we have Finance, Management, IT? What Version are you running? Earlier than 2009, 2009/R2, 2013, 2015/2016?
3
Session objectives Share our story on our upgrade
Identify ideas for you to make your upgrade/implementation easier Learn from our mistakes
4
Company Background High Tech company – Healthcare and Life Science
10 years 20% growth annually Branch in Mannheim, Germany – working on Singapore High investment in R&D – Agile methodology
5
Who are we? Cutting edge & lean organization
Why we were on 3.7 for so long? Parent Company – modifications @ 3.7 (2003) until 2015 Great advice early – No modifications 6 months
6
Our Problem Everyone has a reason to upgrade
What’s yours? Ours = Collect and Remit Sales and Use Tax No add-on for 3.7 Nexus in 45 state jurisdictions
7
Business Case Parent Company – SAP rollout 2009-2015
Average Spend $1 million per instance NAV-10th of the cost with no additional staff required
8
Estimated Project Timeline/Challenges
Struggle with project mgmt Hosting difficulties Paperwork ISV Assessment Approval Dec 2014 Kick-Off May 2015 Testing System August Go Live Sept 1, 2015 Test Environment available August 5, 2015
9
Actual Project timeline
Project brainstorm with team Calls 3 times a week Each Member took portion of work Tested 2 days straight in room together Test Environment available August 5, 2015 Go Live Sept 1, 2015
10
So Many benefits Supported system Efficiencies with new
Always staying current with new features Take what we learned and apply to EU upgrade
11
EU Perspective Project Impact GmbH Take Away
Start June 1 – little contact during August Heard the feedback on the system early Experienced the level of detail to launch project Take Away importance regular meetings Bring in experts early Make sure we have more time
12
Thank you for attending
Contact information Michelle Scott, Terso Yvonne Steinhauser, Terso
13
Thank you for attending
Reminders: Please download the session slides from the NAVUG Congress Community or through the Congress App Please complete your session survey in the Congress App
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.